_ SP-6102 



Readings 

in Systems Engineering 



Edited by Francis T. Hoban 
and William M. Lawbaugh 



nn«o»*221 




(NASA-SP-6102) READINGS IN SYSTEMS 
ENGINEERING (NASA) 215 p 



N93-24678 
--THRU-- 
N93-24693 
Unci a s 



Hl/31 0158570 



Readings 

in Systems Engineering 



Edited by Francis T. Hoban 
and William M. Lawbaugh 



NASA 



National Aeronautics and Space Administration 
Scientific and Technical Information Program 
Washington, DC 1993 



Readings in Systems Engineering 



Introduction by Francis T. Hoban and William M. Lawbaugh 



Author 

Robert A. Frosch 

Defense Systems Management 
College 

Paul E. Lewkowicz 



Marshall Space Flight 
Center SE Handbook 



Title 



A Classic Look at Systems Engineering 
Systems Engineering Overview and Process 



Systems Engineering for 
Very Large Systems 

What is a System ? NASA 's Phased 
Project Description 



NASA SE Handbook (Draft) Management Issues in Systems Engineering 



Tony Fragomeni and 
Mike Ryschkewitsch 

Owen Morris 
Charles W. Mathews 
John D. Hodge 

JohnE. Naugle 

Eugene Kranz and 
Christopher Kraft 

Robert O. Aller 

John F. Yardley and 
David Wensley 

Lor en A. Lemmerman 

NASA Investigation Board 

NASA Investigation Board 

George Trimble 



Spacecraft Systems Engineering: An 
Introduction to the Process ofGSFC 

SE&I and Management for Manned 
Space Programs 

The Systems Engineering Role in 
Top-Level Requirements 

Cost Considerations in the Systems 
Engineering Process 

Systems Engineering and User Requirements 127 



Page 

1. wr 
9 

17 

23 

35 
79 

87 ' 

105 
115 



SE&I in Manned Missions 

Systems Engineering for Operational 
Support Systems 

Political and Institutional Factors of 
Systems Engineering 

Optimization in the SE Process 

Initial Flight Anomalies ofSkylab I 

The Seasat Failure 

Defining Systems Engineering 



145 . 

157 

163 - 

173 ? 
181 
201 
217 



0»vl 



INTRODUCTION 



Introduction 



f,1 



by Francis T. Hoban and William M. Lawbaugh 

Systems engineering is not new— it's been 
around for quite some time. The ancient 
engineers who designed and built the pyra- 
mids practiced some form of what we today 
call "systems engineering." Modern systems 
engineering emerged during and immediate- 
ly following World War II as weapons grew 
into weapon systems, due to the degree of 
complexity in design, development and de- 
ployability. The advent of space exploration 
further increased the need for and use of sys- 
tems engineering processes and practices. 

The Apollo Program is perhaps NASA's 
best example of the application of systems 
engineering. During Apollo, systems engi- 
neering processes were in place in NASA 
Headquarters and at all field centers. At 
some locations the process was formalized; at 
others it was a back-of-the-envelope applica- 
tion, but it was in place. It was widely prac- 
ticed, and it sustained a young and vibrant 
organization during the design, development 
and operations of the world's greatest engi- 
neering feat. NASA systems engineering 
capabilities grew out of its NACA heritage, 
bolstered by people from the Department of 
Defense, industry and academia who joined 
the team during the Apollo build-up. It 
should be noted that during the Apollo era, 
systems engineering was conducted without 
Agency-wide guidance, standards or lexicon. 
After Apollo, the various NASA centers con- 
tinued to implement systems engineering on 
complex projects but perhaps with less vigor 
and enthusiasm than that displayed during 
Apollo. 

The discipline again became a priority in 
NASA when the study team of the National 
Academy of Public Administration, led by 
Lt. General Sam C. Phillips, recommended 
the strengthening of systems engineering in 
NASA. 



This group, in its final report to the 
NASA administrator on December 30, 1986 
also recommended a renewed effort in the 
education and training of the NASA pro- 
gram and project management workforce. 
Unwritten but well understood in this rec- 
ommendation was renewed emphasis on sys- 
tems engineering training. It was no easy 
task to build a knowledge base, create a li- 
brary collection and develop courses and 
workshops in systems engineering, but the 
efforts took shape, as one essential part of 
NASA's Program and Project Management 
Initiative. This became a continuing educa- 
tion process assisted on an Agency-wide 
basis by the Systems Engineering Working 

Group. 

Today most large engineering organiza- 
tions, including NASA, have a systems engi- 
neering process containing elements both 
common and unique to those practiced by 
other organizations. To document these 
processes NASA is now involved in the prep- 
aration of the first Agency-wide systems 
engineering manual. The manual addresses 
common systems engineering practices and 
tools, as well as those unique to NASA and 
the aerospace industry. This manual, togeth- 
er with those describing the individual Cen- 
ters' practices, will fully document systems 
engineering at NASA and add to the educa- 
tion process. 

This present collection was inspired by 
seven papers prepared by the NASA Alumni 
League, illustrating the members' systems 
engineering experience. These papers make 
up the heart of this collection. We have sup- 
plemented them with papers describing 
industry processes and other governmental 
practices to illustrate the diversity of sys- 
tems engineering as it is formulated and 
practiced. This is one discipline that clearly 



READINGS IN SYSTEMS ENGINEERING 



benefits from cross-fertilization and infusion 
of new ideas. 

There is also a wide variety of tools and 
techniques described herein, some standard 
and some unique. It is not unlike an elite 
crew of talented carpenters showing up for a 
job, each with some different tools in their re- 
spective toolboxes, and each with different 
tricks or techniques to save time or money — 
to do each one-of-a-kind job better, cheaper, 
faster. 

If all the authors of Readings in Systems 
Engineering were ever to assemble in one 
place, there would be some unanimity on ba- 
sics and essentials but much debate and 
downright disagreement on the particulars. 
Nevertheless, the meeting would be lively 
and interesting — a decent description of the 
dynamic process of systems engineering it- 
self. 

APPROACH 

We begin our collection with a now-famous 
speech delivered by Bob Frosch to a group of 
engineers in New York in 1969, shortly 
before his appointment as NASA Adminis- 
trator. The speech sets the tone best of all for 
this volume: Frosch urges a common sense 
approach to systems engineering. 

When weapons evolved into weapons sys- 
tems, the Department of Defense took the 
lead in systems, engineering. Today the DoD 
approach is widely recognized, and so we 
present the newly revised (1990) description 
of the systems engineering process from the 
Defense Systems Management College at 
Fort Belvoir, Virginia. A senior project engi- 
neer formerly with Hughes Aircraft, Paul E. 
Lewkowitcz, then discusses requirement 
analysis, technology assessment, solution 
synthesis and performance verification for 
very large systems. Marshall Space Flight 
Center does it differently, but one of the best 
descriptions of Phase A through C can be 
found in Marshall's systems engineering 
handbook. To close out this overview section, 
excerpts from the forthcoming NASA 



Systems Engineering Handbook stress the 
engineering aspects of successful manage- 
. mentof aerospace systems. 

In our second section, devoted to specific 
applications of systems engineering, we be- 
gin with two engineers from the Goddard 
Space Flight Center whose presentations are 
famous for explaining the process and pro- 
ducts of systems engineering in unmanned 
spacecraft. Tony Fragomeni and Mike 
Ryschkewitsch are associate chief and chief 
respectively of Goddard's new Systems Engi- 
neering Office. Owen Morris, who was 
NASA's Lunar module project manager and 
the Space Shuttle Systems and Engineer ng 
manager, then discusses the history of sys- 
tems engineering and integration (SE&I) 
management in manned space programs. 
Chuck Mathews, past president of the NASA 
Alumni League, and NASA's manager of the 
Gemini Program, director of the the Skylab 
Program and associate administrator for Ap- 
plications, then focuses upon the systems en- 
gineering role in establishing, verifying and 
controlling top-level program requirements. 
John D. Hodge, a 25-year veteran of the 
Department of Transportation and NASA, 
including the Mercury, Gemini, Apollo and 
Space Station programs, retiring as an asso- 
ciate administrator, explains cost consider- 
ations in the systems engineering process, 
urging clear definition of requirements, sta- 
ble management and strong central control 
to allocate funds properly. 

John E. Naugle, retired NASA associate 
administrator and chief scientist, describes 
the dual role of "master" and "servant" for 
the systems engineer, from the requirements 
phase to preliminary design. Eugene F. 
Kranz, director of the Johnson Space Center 
Mission Operations Directorate, and 
Christopher C. Kraft Jr., former director of 
the Johnson Space Center, stress manned 
mission operations and SE&I. Robert O. 
Aller, recently retired associate administra- 
tor for space operations, views operations 
support as the infrastructure of people, 
procedures, facilities and systems for flight 



u 



INTRODUCTION 



success. John Yardley, NASA's associate 
administrator for manned space flight dur- 
ing the Space Shuttle development, asserts 
that the systems engineer should consider 10 
different political and nontechnical groups. 
Associate David Wensley suggests ways of 
handling political and institutional factors 
in the systems engineering process. Loren A. 
Lemmerman, formerly of the Lockheed- 
Georgia Company, shows how a large air- 
craft company fits optimization into systems 
engineering and the total design process. 

Next, we present what today can be look- 
ed at as case studies in lost systems engi- 
neering opportunities. On May 14, 1973, a 
minute into flight, Skylab 1 lost its meteor- 
oid shield and one of two solar array systems. 
The NASA Investigation Board determined 
that aerodynamic loads were probably not 
accounted for in design. Likewise, the Seasat 
Mission Failure Investigation Board de- 



scribed the uncritical acceptance of "stan- 
dard" or "flight proven" equipment that 
failed in 1978. But no one wants to end on a 
negative, so we reproduce a Johnson Space 
Center engineer's attempt to define and ex- 
plain "systems engineering" a quarter of a 
century ago. 

This book is primarily for the next gen- 
eration of systems engineers, so we look 
ahead. As Bob Aller concludes, "The need for 
systems engineering is critical to NASA in 
its preparations for conducting operations in 
the late 1990s and into the next decade." 

The editors gratefully acknowledge the 
authors for sharing their information with 
us. We also wish to thank the NASA Alumni 
League for its most important contribution. 
We thank the NASA Systems Engineering 
Working Group and the entire NASA sys- 
tems engineering family for their encourage- 
ment and support. 



in 



A CLASSIC LOOK AT SYSTEMS ENGINEERENG 



A Classic Look at Systems Engineering 

by Robert A. Frosch 



Editors' Note 

Before his term as NASA Administrator, 
Bob Frosch was an assistant secretary of 
the U.S. Navy in charge of research, devel- 
opment, test and evaluation of Navy 
programs. In that capacity, he delivered a 
controversial and well-remembered speech 
to the IEEE Group on Aerospace and 
Electronic Systems during IEEE's interna- 
tional convention in New York on March 
26, 1969. Edited portions of that famous 
speech follow in an effort to preserve what 
is now considered a classic formulation of 
systems engineering as an art rather than a 
science. 

In this presentation, I really will be discus- 
sing the application of systems engineering 
to development, and in particular to military 
systems development (with which I am most 
familiar). However, from reading various 
journals and newspapers, I suspect my re- 
marks are of more general applicability. I 
have said some of these things before, but 
some bear repeating and some I hope will 
spark new ideas. 

I couple systems engineering, systems 
analysis and Management (with a capital 
"M"), because in practice they seem to be 
closely related terms, referring to the same 
constellation of systematic practices and 
attitudes. 

• We badly lack: systems engineering of 
systems engineering; systems analysis of 
systems analysis. 

• And, heaven knows, there is no: manage- 
ment of Management. 

• Therefore, I will now preach against 
home, motherhood and apple pie. 

To the charge that I am writing about bad 
systems engineering, I can only say that I 
am taking a pragmatic view: the thing is 



defined by what is done, not what is said; and 
if what I am describing is bad systems engi- 
neering, I can only say that I seldom see any 
other kind. 

What I want to do is discuss briefly a 
series of antitheses (and perhaps an unbal- 
anced question or two) that pit the systems 
world against what I believe are some 
aspects of the real world. 

If I plot a graph versus time of what 
appears to be a recent rising tide of costs, 
cost overruns, unsatisfactory performance 
and unhappiness among engineers, I have 
reason to worry. (If this trend continues, we 
may have to debate whether the question 
"whither engineering?" is spelled with one 
"h" or two.) If I plot on the same graph versus 
time the rise in talk, directives, and use of 
"systems engineering," "systems analysis" 
and "Management," I see high correlation 
between the two graphs— trouble versus 
time and the use of systems engineering 
versus time. This does not prove causation, 
but it suggests, at least, that the "new tech- 
niques" are proving to be a poor substitute 
for real science and engineering; they are, at 
the least, not doing what they are advertised 
as doing, if they are indeed actually not 
making things worse. It could be that things 
would be even worse without these new 
techniques, but I would like to ask some 
questions and suggest some reasons for 
believing that systems engineering, systems 
analysis and Management, as practiced, are 
likely to be part of the problem, and indeed 
causative agents. 

I believe that the fundamental difficulty 
is that we have all become so entranced with 
technique that we think entirely in terms of 
procedures, systems, milestone charts, PERT 
diagrams, reliability systems, configuration 
management, maintainability groups and 
the other minor paper tools of the "systems 
engineer" and manager. We have forgotten 



READINGS IN SYSTEMS ENGINEERING 



that someone must be in control and must 
exercise personal management, knowledge 
and understanding to create a system. As a 
result, we have developments that follow all 
of the rules, but fail. 

I can best describe the spirit of what I 
have in mind by thinking of a music student 
who writes a concerto by consulting a check- 
list of the characteristics of the concerto 
form, being careful to see that all of the can- 
ons of the form are observed, but having no 
flair for the subject, as opposed to someone 
who just knows roughly what a concerto is 
like, but has a real feeling for music. The 
results become obvious upon hearing them. 
The prescription of technique cannot be a 
substitute for talent and capability, but that 
is precisely how we have tried to use 
technique. 

Paper vs. People 

My first antithesis pits the systems world of 
paper and arrangements against the real 
world of people and hardware. When paper 
appears in the real-world version of a 
system, it is generally only as an abstracted 
commentary. For example, in a very basic 
sense it really is of no consequence whether 
the documentation on a weapons system is 
good, bad or nonexistent; that is only a 
commentary on whether or why the people 
and the hardware actually work when called 
upon, and a tool to help them work. If the 
systems arrangements on paper and the doc- 
umentation can help to make the stuff work, 
then they are of some use. If they are merely 
the formal satisfaction of a requirement, 
they are only an interference with engineer- 
ing. Systems, even very large systems, are 
not developed by the tools of systems engi- 
neering, but only by the engineers using the 
tools. In looking back at my experiences in 
development, including watching a number 
of Navy developments over the past few 
years, it seems quite clear that in most cases 
where a system gets into trouble, a compe- 
tent manager knows all about the problem 



and is well on the way to fixing it before any 
management systems ever indicate that it is 
about to happen. This happens if for no other 
reason than because the competent manager 
is watching what is going on in great detail 
and perceives it long before it flows through 
the paper system. That is to say, personal 
contact is faster than form-filling and the 
U.S. mails. A project manager who spends 
much time in a Management Information 
Center instead of roving through the places 
where the work is being done is always 
headed for catastrophe. The MIC can assist 
the people who are not involved in the project 
toward learning of after-the-fact problems, 
but that is roughly all that it can do, and its 
value even for this purpose is frequently 
questionable. 

Blaming deficiencies in management 
systems for problems that exist in real 
unknowns, or in the deficiencies of people, is 
mere foolishness. In a poem called "Bagpipe 
Music," by Louis MacNeice, the final couplet 
is: 

"The glass is falling hour by hour, 
the glass will fall forever 
But if you break the bloody glass, 
you won't hold up the weather. " 

Linearity vs. the Real World 

One of the key misassumptions in modern 
systems engineering and systems analysis is 
that the total problem can be, and frequently 
is, decomposed into subproblems; the 
subproblems can be solved more or less 
independently, and the total solution can be 
synthesized by combination of the subsolu- 
tions, treating the interactions of the parts 
as "interfaces." The real world is, however, 
highly non-linear, and unless real attention 
is paid to this fact, the linear decomposition 
treatment will fail catastrophically, because 
the interaction terms may be as large as the 
subproblems and not reducible to simple 
interfaces. The result may well remain 
decomposed. 



A CLASSIC LOOK AT SYSTEMS ENGINEERING 



This criticism is frequently answered by 
the comment that problems are unmanage- 
able unless sliced up and, therefore, the pro- 
cedure is used even though we know it may 
be seriously in error. This is the case of the 
man who played in a poker game that he 
knew to be crooked, because it was the only 
game in town; or the drunk who looked for 
his ring under the street lamp even though 
he had lost it a block away in the dark — the 
light was better under the street light. I have 
some difficulty seeing that a bad analysis is 
really better than an informed judgment, 
especially since faith in the analysis (and/or 
the decomposed solution to the problem) is 
frequently, nay, usually, used as a substitute 
for seeking or applying any judgment at all. I 
am often faced with a result that seems 
absurd, and can even produce a quick analy- 
sis that at least makes it obvious that the 
solution is absurd, but am then given the 
answer, "Well, that's what the analysis 
showed." 

Such a situation usually indicates room 
for deep criticism, either of the way in which 
the problem was divided up, or of peculiar- 
ities of the assumptions that drive the 
problem in curious and unsuspected ways, 
particularly through the unsuspected (by the 
systems person) nonlinearities of the 
problem. It sometimes appears that the only 
rational subdivision of the problem is to 
fractionize the blame to the point where 
approval is sought by default. 

I would argue that careful attention to 
the parts of the problem that do not seem to 
be easily decomposable into semi- 
independent parts might be one very good 
guide to areas involving high risk, since 
these are likely not to be amenable to our 
usual rules, procedures and technologies, 
and hence probably will have to be 
approached empirically. 

Serial vs. Iterative Models 

Systems engineering techniques themselves 
contribute to disaster because they are all 



paper techniques and there are only two in- 
stead of N dimensions available. What we 
end up displaying are linear sequential mea- 
sures of system progress. 

The PERT diagram and the milestone 
chart are excellent examples. These both 
essentially assume that the progress of 
development and design consists of doing 
step A, then step B, then step C, etc. Anyone 
who has ever carried out a development or a 
design (as opposed to setting up a manage- 
ment system for doing so) is well aware of 
the fact that the real world proceeds by a 
kind of feedback iterative process that looks 
more like a helix than like a line. That is to 
say, you do A, then B, then C, then you look 
at C and go back and change part of A again, 
and that causes you to fiddle with B and 
perhaps bring in a B-prime that you bounce 
against C, and then go back to A and then 
jump to D, so that there has to be continual 
adjustment, going back and forth so that the 
system is adjusted to itself and to its end 
objectives as it changes and as the design or 
development proceeds. Because it is difficult 
to predict this process or to diagram it, or to 
predict its costs precisely without using 
competent engineers, the systems engineer- 
ing procedures simply ignore the iterative, 
feedback nature of the real world because the 
process has been degraded to clerical report- 
ing. To a large extent, this tends to constrain 
project managers from doing work in the real 
way toward doing it in a way that fits with 
their management tools. This is clearly 
nonsense. 

As a specific example, doctrine says that 
one is to consider the "ilities," that is, main- 
tainability, reliability, operability, etc., from 
the very beginning of the process. This is a 
vast waste of time and effort. I do not mean 
that one should not think about these things 
at the beginning, but it is certainly ridicu- 
lous to have a complete plan for the logistics 
of the maintenance of an object that has not 
yet been designed. I have seen overruns in 
expenditure and unnecessary effort generat- 
ed by the fact that the linear sequencing of 



READINGS IN SYSTEMS ENGINEERING 



milestones had forced development of a com- 
plete maintenance and reliability plan for 
what was no longer the design, and had not 
been the design for three months. The 
machinery forced everyone to grind on and 
on because, after all, the maintenance and 
reliability milestones could not be missed 
without disaster and fear of cancellation of 
the project, even though the plan being 
worked out had nothing whatever to do with 
the hardware being designed. 

In fact, the point at which to start serious 
work on configuration control, maintainabil- 
ity and reliability cannot be very well pre- 
planned; it can be roughly preplanned, but it 
must be adjusted to be at the point at which 
the design means something and is likely to 
stay still long enough so that the redesign for 
the "ilities" will really make some sense. 
Judgment, not tools, is what is required. 

Prediction vs. Production 

This brings me to a related antithesis that I 
describe as prediction versus production. We 
have come to a time when meeting certain 
targets seems to have become more impor- 
tant than producing a satisfactory system. 
The question is not the development of a sys- 
tem that performs well and was produced at 
a reasonable cost and in a reasonable time, 
but rather replacement of this sensible 
desire by the question, "Does the system per- 
form as predicted, did you produce it for the 
cost you predicted, and on the schedule you 
predicted, and did you do it in the way you 
predicted?" Consequently, looking at what is 
actually happening in the development has 
been replaced by measuring it against a 
simplistic set of predicted milestones. Fulfill- 
ment of prediction has been seriously pro- 
posed as the criterion for judging system 
managers. It is certainly a minor criterion. 
Fulfillment of a need when fielded continues 
to be our real objective. 

I know of a number of cases where the 
pressure on prediction has been so great that 
the project managers were forced to destroy 



the possibility of having a good system 
because they were not allowed to adjust what 
they were doing to the real world; otherwise, 
they would have been so far off prediction in 
one or another dimension that the project 
would have been canceled. We fell between 
two stools. We had a system that was only 
approximately what we wanted and the sys- 
tem failed to meet the prediction. Similarly, 
we have not had the sense to cancel some- 
thing that met the predictions, but was no 
damn good. 

A Question of Predictability 

It is curious that those of us, sophisticated as 
systems engineers, and having read history 
(in which no one ever seems to anticipate 
what really happens), knowing that the pre- 
diction time for random noise seen through a 
bandpass filter is only about one over the 
bandwidth, should yet seek predictability for 
the processes with a wide bandwidth of 
unknown information. No one can predict 
politics or economics; few of us predict what 
happens in our own lives. Why then do we 
assume the predictability of development of 
the unknown? 

Should we expect development miles- 
tones to be met? Presumably, the prior 
probability of meeting the perfectly chosen 
milestone on time is distributed randomly 
and symmetrically about the predicted time. 
If the accomplishment is relatively simple, 
the distribution is narrow and this is called 
"low risk;" if the accomplishment is difficult, 
the distribution is wide and this is called 
"high risk." However, all development 
schedules assume success of each process. If 
we put trouble contingency time allowances 
into every task, the total contingency allow- 
ance would be unacceptably large and the de- 
velopment unacceptably long. This tends to 
bias the true risk distribution in such a way 
as to move the peak to the late side. Thus, 
there is a tendency for the "risk distribution" 
to peak after the milestone. The contingency 
allowance should be provided in an unpopu- 



A CLASSIC LOOK AT SYSTEMS ENGINEERING 



lar program element, "allowance for stupid- 
ity and the unforeseen." Even so, it probably 
would be eliminated by the efficient review 
process. 

All I am saying is that we only assess the 
risk of the predictable problems and that 
there is always a family of unpredictable 
problems that make things take longer; 
there are few ("oh, happy few!") cases of luck 
that make things take less time. We should 
not expect milestones to be reached, and they 
never (or hardly ever) are, although miles- 
tones are needed to assure adequate program 
pressure. 

This question and my trial answer sug- 
gest a signal-to-noise ratio approach to risk 
and error assessment in development 
models. I have not tried to carry this further; 
it is left as an exercise for the developer. 

Systems in Space vs. 
Systems in Space-Time 

My next antithesis I would label "systems in 
space" versus "systems in space-time." We 
talk about system design and system choice 
in terms of ten-year life-cycle costs, but the 
assumption we tend to make is that the sys- 
tem we are costing is a static object once it is 
designed and produced. In a way, this is 
forced upon us by the accountant's formalism 
of dividing costs into investment and recur- 
ring costs. Any system managers who say 
that they are designing their system in 
space-time, and that they propose to design 
it so as to facilitate their ability to change it 
during the course of the ten-year life cycle, 
will promptly have their project removed 
from under them because the doctrine says, 
"This is terribly uneconomical;" further- 
more, it says that it is bad system design. I 
would simply like to note here that real- 
world history tells us that all systems are 
changed frequently during their lifetime, if 
for no other reason than that the real 
requirements and environments and tech- 
nologies for them change, often in ways that 
make it stupid to leave them alone. In fact, it 



is almost true that no military system is ever 
used for the precise purpose for which it is 
designed. Consequently, it makes sense to 
think about the system as something that 
will have a history in time and that is likely 
to require change, and to include some 
thought of this in the design. Change, 
strangely, is the only truly predictable attri- 
bute of the system. Perhaps I am merely go- 
ing to be enshrined in the next generation of 
systems engineering doctrine with a special 
group in every project organization called 
"changeability management." I hope not. 

The question is not whether there will be 
changes or not, but whether the change 
process will be under conscious control. Do 
the developers know "what" and "why" when 
they allow or make a change? Pretending 
that no changes are allowable or desirable is 
merely a way of losing control of the change 
process. 

An example of the consequences of what I 
mean follows. It is systems engineering 
doctrine that the system should be matched 
throughout; that is to say, it is regarded as 
poor practice to have, for example, high- 
reliability components matched with low- 
reliability components since system reliabil- 
ity will really be set by the low-reliability 
components whereas system cost is likely to 
be set by the high-reliability components. 
This ignores the fact that since the system 
will have to change in time it may be very 
sensible to build in high-reliability compo- 
nents in some parts of the system, even 
though the technology does not provide them 
for other parts of the system. During the 
course of the lifetime of the system, there 
may be a high probability of bringing the 
low-reliability parts up to an equivalent reli- 
ability with the higher-reliability parts for a 
reasonable cost. Thus the system could be 
designed for great improvement in reliabil- 
ity from the very beginning, whereas if 
everything is matched to the lower reliabil- 
ity, the cost of improvement becomes gigan- 
tic, because the changes are extensive. In 
fact, the rule of thumb may not be good 



READINGS rN SYSTEMS ENGINEERING 



engineering at all if the system is designed 
considering change with time. We should de- 
sign for growth and a process of technological 
leapfrogging in the system. 

Optimization vs. Uncertainty 

One of the fundamental tenets of systems 
engineering is that the system should be 
optimized to its purpose. This is dandy if the 
purpose is very specifically definable and if it 
is very independent of scenario and enemy 
behavior. If these requirements are not true, 
and they almost never are for any military 
system of any great sophistication, then opti- 
mization may merely be the definition of 
which catastrophe you want to undergo. My 
analogy is the matching of a narrow-band 
filter to a specific signal. This is an elegant 
engineering procedure, provided you can de- 
pend on the signal to stay put. If the enemy, 
for example, has a slight adjustment in their 
frequency, then optimization in the normal 
sense rapidly becomes nonsense. There is no 
sense in optimizing the system beyond the 
accuracy of the definition of requirements, 
and I never, or almost never, see a definition 
of requirements with estimated error limits. 
This particular kind of catastrophe is 
most often generated by the portion of sys- 
tems engineering that the economists like to 
call systems analysis. That is to say, having 
chosen some scenario or problem defined in a 
very specific way, the system prescription 
follows optimization of this problem to the 
bitter and ridiculous end. There is a vast 
reluctance to look at the difficulties and the 
risks involved in assuming that the chosen 
problem is the correct problem. I will feel 
much better about the use of scenarios and 
prediction of warfare ten years ahead for 
system choice and optimization if ever I meet 
a person who can really predict a chess game, 
or what will happen in the stock market 
tomorrow. This is not to say the game should 
be ruled out just because the results cannot 
be predicted, but rather to reinforce the fact 



that it is a game and cannot be taken 
literally. 

There is a procedure called sensitivity 
analysis, but I have rarely seen it applied to 
the right parameters and variations. It is 
usually too difficult to do so. One rarely ever 
considers an error analysis, even when some- 
thing is known about the error distributions 
of the input parameters. 

A problem related to this is posed by the 
analysis of multipurpose objects. A tremen- 
dous difficulty is generated by the fact that 
the costs and characteristics must be allocat- 
ed to the appearance of the system in several 
different scenarios. Consequently, these 
systems must be single solutions to several 
systems engineering requirements. Our usu- 
al way of dealing with this problem is to bow 
three times in its direction and then ignore 
it, because it is just too hard to solve. Solving 
it requires solving the systems problems for 
all the situations in which the multipurpose 
system appears, then doing all the (non- 
linear) interaction cases. 

In addition, the cost allocation to the var- 
ious uses must be attacked. There is simply 
no methodology available for really trying 
this and hence the problem is generally 
ignored. This makes many of the analyses 
useless, but that is generally ignored too. 
There is no sense in pretending to solve 
problems by refusing to address them realis- 
tically because they are too difficult, but we 
go on playing that game. 

Objects vs. Objectives 

Finally, we do not distinguish sufficiently 
between objects and objectives. The working 
tools and most of the life of systems 
engineering are spent trying to reach an 
objective, the objective finally becoming an 
object. It is important to keep this distinction 
in mind. The trouble in procurement of a 
development is that procurement procedures 
are designed to buy objects, whereas in 
development there is no object until the end, 



A CLASSIC LOOK AT SYSTEMS ENGINEERING 



only an objective, and the two are not the 
same thing. 

For example, what is a specification? A 
specification is an abstract set intended to 
describe what is to be produced, but of course 
it is only a portion of a total description. It is 
a subset of points selected from a continuous 
portion of an infinite multidimensional 
space. The object itself and its total future 
history is the only complete specification. 
Consequently, the idea of a "complete" speci- 
fication is an absurdity; we can only produce 
a partial subset. In fact, it is possible (and we 
have all seen it happen) for an object that 
meets the subset of specification points to 
badly miss being a sensible solution to the 
problem, because it departs from the 
required reality between the specification 
subset points. I hasten to add that sometimes 
even the object itself, without regard to its 
future history, is not a sufficient specifica- 
tion, because it does not contain the details 
of the techniques used to produce it. Let the 
specifier beware! 

Having complained about all of this 
throughout this article, what do I propose? 
The only thing I know that works is to obtain 
a competent person and assistants, and 
make sure they understand the problem — 
not the specifications of the problem, not the 
particular written scenario, but what is real- 
ly in the minds of those who have a 
requirement to be solved. Then give them 
funds, a good choice of managerial and 
systems engineering tools, and let them 
work at the problem after reasonably 



frequent conferences with those who have 
the requirement. 

In this way, the end object may become 
the best that both parts of the system can 
produce and not merely the solution to a 
paper problem, said solution having the best 
paper properties to match the previous set of 
paper. (Some paper is water soluble.) 

It might do well to bear in mind the 
following closing thoughts: 

• As we are now behaving, we are using up 
our best people in filling out documenta- 
tion for their superiors to read, and most 
of the time no one is running the store. 

• We have lost sight of the fact that engi- 
neering is an art, not a technique; a tech- 
nique is a tool. From time to time I am 
briefed on the results of a systems analy- 
sis or systems engineering job in a way 
that prompts me to ask the questions: 
"That's fine, but is it a good system? Do 
you like it? Is it harmonious? Is it an 
elegant solution to a real problem?" For 
an answer I usually get a blank stare and 
a facial expression that suggests I have 
just said something really obscene. 

We must bring the sense of art and 
excitement back into engineering. Talent, 
competence, and enthusiasm are qualities of 
people who can use tools; the lack of these 
characteristics usually results in people who 
cannot even be helped by techniques and 
tools. We can all do better. 



SYSTEMS ENGINEERING OVERVIEW AND PROCESS 



N9 3-246 5 r3 / 
The Systems Engineering Overview and Process ';$367 1 

(FROM THE SYSTEMS ENGINEERING MANAGEMENT GUIDE U990]) 

Defense Systems Management College ' v f 



The past several decades have seen the rise 
of large, highly interactive systems that are 
on the forward edge of technology. As a re- 
sult of this growth and the increased usage of 
digital systems (computers and software), 
the concept of systems engineering has 
gained increasing attention. Some of this at- 
tention is no doubt due to large program fail- 
ures which possibly could have been avoided, 
or at least mitigated, through the use of sys- 
tems engineering principles. The complexity 
of modern day weapon systems requires con- 
scious application of systems engineering 
concepts to ensure producible, operable and 
supportable systems that satisfy mission 
requirements. 

Although many authors have traced the 
roots of systems engineering to earlier dates, 
the initial formalization of the systems engi- 
neering process for military development 
began to surface in the mid-1950s on the bal- 
listic missile programs. These early ballistic 
missile development programs marked the 
emergence of engineering discipline "special- 
ists" which has since continued to grow. 
Each of these specialties not only has a need 
to take data from the overall development 
process, but also to supply data, in the form 
of requirements and analysis results, to the 
process. 

A number of technical instructions, mili- 
tary standards and specifications, and man- 
uals were developed as a result of these 
development programs. In particular, MIL- 
STD-499 was issued in 1969 to assist both 
government and contractor personnel in 
defining the systems engineering effort in 
support of defense acquisition programs. 
This standard was updated to MIL-STD- 
499A in 1974, and formed the foundation for 
current application of systems engineering 
principles to military development pro- 
grams. 



In its simplest terms, systems engineer- 
ing is both a technical process and a manage- 
ment process. To successfully complete the 
development of a system, both aspects must 
be applied throughout the system life cycle. 
From a government's program management 
point of view, the Defense Systems Manage- 
ment College favors the management ap- 
proach and defines systems engineering as 
follows: 

Systems engineering is the manage- 
ment function which controls the total 
system development effort for the pur- 
pose of achieving an optimum balance 
of all system elements. It is a process 
which transforms an operational need 
into a description of system parameters 
and integrates those parameters to op- 
timize the overall system effectiveness. 
A system life cycle begins with the user's 
needs, expressed as constraints, and the 
capability requirements needed to satisfy 
mission objectives. Systems engineering is 
essential in the earliest planning period, in 
conceiving the system concept and defining 
system requirements. 

As the detailed design is being done, sys- 
tems engineers: 1) assure balanced influence 
of all required design specialties, 2) resolve 
interface problems, 3) conduct design re- 
views, 4) perform trade-off analyses, and 
5) assist in verifying system performance. 

During the production phase, systems en- 
gineering is concerned with: 1) verifying sys- 
tem capability, 2) maintaining the system 
baseline, and 3) forming an analytical 
framework for producibility analysis. 

During the operation and support (O/S) 
phase, systems engineering: 1) evaluates 
proposed changes to the systems, 2) estab- 
lishes their effectiveness, and 3) facilitates 
the effective incorporation of changes, modi- 
fications and updates. 



PRESIDING PAGE BLANK NOT FILMED 



***~^-_iAJiKiJUftwj mm 



READINGS IN SYSTEMS ENGINEERING 



Iterative Trade-Offs 




Functional 
Analysis 



Synthesis 



• What 

• Why 



How 



s~~\ Evaluation />. 
"K2y* and *(OR>* 



Description of 

System 
Elements 



Solutions 



Figure 1 The Systems Engineering Process 



The Systems Engineering Process 

Although programs differ in underlying 
requirements, there is a consistent, logical 
process for best accomplishing system design 
tasks. Figure 1 illustrates the activities of 
the basic systems engineering process. 

The systems engineering process is itera- 
tively applied. It consists primarily of four 
activities: functional analysis, synthesis, 
evaluation and decision, and a description of 
systems elements. The product element 
descriptions become more detailed with each 
application and support the subsequent 
systems engineering design cycle. The final 
product is production-ready documentation 
of all system elements. 

Since the requirement to implement a 
systems engineering process may cause 
major budgetary commitments and impact 
upfront development schedules, it is impor- 
tant to understand the inherent objectives: 

• Ensure that system definition and design 
reflect requirements for all system ele- 
ments: equipment, software, personnel, 
facilities and data. 

• Integrate technical efforts of the design 
team specialists to produce an optimally 
balanced design. 

• Provide a comprehensive indentured 
framework of system requirements for 



use as performance, design, interface, 
support, production and test criteria. 

• Provide source data for development of 
technical plans and contract work state- 
ments. 

• Provide a systems framework for logistic 
analysis, integrated logistic support 
(ILS), trade studies and logistic documen- 
tation. 

• Provide a systems framework for produc- 
tion engineering analysis, producibility 
trade studies, and production and manu- 
facturing documentation. 

• Ensure that life cycle cost considerations 
and requirements are fully considered in 
all phases of the design process. 

Successful application of systems engi- 
neering requires mutual understanding and 
support between the military and contractor 
program managers. They must be willing to 
make the systems engineering process the 
backbone of the overall development 
program. They must understand the need to 
define and communicate among the 
engineering specialty programs. They must 
recognize the role of formal technical reviews 
and audits, including the value, objectives 
and uniqueness of each formal review and 
audit. They must also know the objectives of 
the program and possess a thorough inter- 
pretation of the user's requirements. 



10 



SYSTEMS ENGINEERING OVERVIEW AND PROCESS 



The output of the systems engineering 
process is documentation. This is the means 
by which it controls the evolutionary devel- 
opment of the system. Systems engineering 
prepares a number of technical management 
and engineering specialty plans that define 
how each phase of the acquisition cycle will 
be conducted. Draft plans are usually sub- 
mitted with the proposal and final plans are 
delivered in accordance with the Contract 
Data Requirements List (CDRL). These 
plans are used by the government to ensure 
compliance with the contract and used by the 
contractor to develop detailed schedules and 
allocation of resources. Specifications are 
submitted that form the basis for the design 
and development effort. Top-level specifica- 
tions are incorporated into the statement of 
work (SOW) and provided to the developer. 
The developer will allocate these top-level 
requirements to lower level system compo- 
nents (hardware and software) and submit 
the associated specifications and design doc- 
uments to the government for approval. The 
status of system development progress is 
tracked and documented in the form of tech- 
nical review data packages, technical perfor- 
mance measurement (TPM) reports, analysis 
and simulation reports and other technical 
documentation pertinent to the program. In 
summary, this documentation may include: 



Systems Engineering Management Plan 
(SEMP) 

Specifications (system, segment, develop- 
ment, product, process, material) 
Design Documentation 
Interface Control Documents (ICDs) 
Risk Analysis Management Plan 
Survivability/Vulnerability (S/V) Hard- 
ness Plan 

Mission Analysis Report 
Reliability Plan 
Maintainability Plan 
Integrated Logistics Support Plan (ILSP) 
Software Development Plan (SDP) 
Test and Evaluation Master Plan 
(TEMP) 



• Producibility Plan 

• Functional Flow Block Diagrams (FFBD) 

• Requirements Allocation Sheets (RAS) 

• Audit Reports 

• EMI/EMC Control Plan 

• Human Engineering Plan 

• Trade Study Reports 

The systems engineering process is an 
iterative process applied throughout the ac- 
quisition life cycle. The process itself leads to 
a well defined, completely documented and 
optimally balanced system. It does not pro- 
duce the actual system itself, but rather, it 
produces the complete set of documentation, 
tailored to the needs of a specific program, 
which fully describes the system to be devel- 
oped and produced. Each program's systems 
engineering process, developed through 
tailoring and/or adding supplemental re- 
quirements, must meet certain general crite- 
ria. Although not complete, the following 
guidelines should be considered in approach- 
ing the basic process: 

• System and subsystem (configuration 
item) requirements shall be consistent, 
correlatable, and traceable both within 
data produced as basic documentation 
(e.g., Functional Flow Block Diagram, 
Requirements Allocation Sheet, and 
Time Line Sheet) and as related docu- 
mentation (e.g., work breakdown struc- 
ture and Logistic Support Analysis 
Record). 

• The concept of minimum documentation 
shall be evident. 

• Acquisition and ownership cost shall be 
an integral part of the evaluation and de- 
cision process. 

• Baselines shall be established progres- 
sively as an integral part of the systems 
engineering process. 

• The systems engineering process shall 
result in a design that is complete, at a 
given level of detail, from a total system 
element viewpoint. 



1 1 



READINGS IN SYSTEMS ENGINEERING 



The process shall provide for the timely 
and appropriate integration of main- 
stream engineering with engineering 
specialties such as reliability, maintain- 
ability, human factors engineering, 
safety, integrated logistic support, envi- 
ronmental assessments and producibility 
to ensure their influence on system 
design. 

The process shall provide for continuing 
prediction and demonstration of the an- 
ticipated or actual achievement of the 
primary technical objectives of the sys- 
tem. Problems and risk areas shall be 
identified in a timely manner. 
Formal technical reviews and audits 
shall be an integral part of the systems 
engineering process. 

The systems engineering process shall be 
responsive to change. The impact of 
changes to system and/or program re- 
quirements must be traceable to the low- 
est level of related documentation in a 
timely manner. 



• Significant engineering decisions shall be 
traceable to the systems engineering ac- 
tivities and associated documentation 
upon which they were based. 

Figure 2 is an overview of the four basic 
steps of the systems engineering process. 

Functional Analysis 

Every engineering effort must begin with a 
statement of a perceived need. At the 
beginning of a DOD acquisition effort, this 
statement will be in the form of a system 
requirement document, usually developed 
through a Mission Area Analysis of antici- 
pated threats. 

Once the purpose of the system is known, 
the functional analysis activity identifies 
what essential functions the system must 
perform. In order to accomplish this, func- 
tional analysis is composed of two primary 
process segments: functional identification 
and requirements identification and 



Input Requirements 

Mission Objectives 
Mission Environments 
Mission Constraints 
Measurements of 
Effectiveness 



Technology Selection Factors 



Hardware 

Software 

Reliability 

Maintainability 

Personnel/Human Factors 

Survivability 

Security 

Safety 

Standardization 

Integrated Logistic Support 

EMC 

System Mass Properties 

Producibility 

Transportability 

Electronic Warfare 

Computer Resources 




• Equipment 

• Personnel 

• Facilities 

• Computer Software 

• Technical Data 



Figure 2 The Systems Engineering Process 



12 



SYSTEMS ENGINEERING OVERVIEW AND PROCESS 



allocation (functional performance require- 
ments analysis). It answers the "what" and 
"why" questions relative to system design. 

The basic analytical tool for functional 
identification is the Functional Flow Block 
Diagram (FFBD), showing logical sequences 
and relationships of operational and support 
functions at the system level. Specific func- 
tions will vary from system to system and 
will be traceable to mission requirements 
and objectives. Maintenance flow diagrams 
depicting general maintenance and support 
concepts will lead to analysis of require- 
ments on an end item/equipment basis. At 
this level, since functions are more standard- 
ized, functional identification is often accom- 
plished using the End Item Maintenance 
Sheet (EIMS) or Logistic Support Analysis 
Record (LSAR). Similarly, detailed test 
requirements are identified using the Test 
Requirements Sheet (TRS), and productivity 
requirements are identified using the 
Production Sheet (PS). 

It should be kept in mind that the sys- 
tems engineering process is always iterative. 
Each acquisition phase will involve function- 
al analysis to progressively more detail. For 
example, during the Concept Explora- 
tion/Definition (C/E) phase, analysis of 
support functions will concentrate on Main- 
tenance FFBDs, which will support the 
establishment of gross maintenance con- 
cepts. During Full Scale Development (FSD), 
emphasis will shift to detailed analysis of the 
maintenance requirements of specific equip- 
ment using the EIMS or LSAR. 

The Requirements Allocation Sheet 
(RAS) is used as the primary analytical tool 
for requirements identification and alloca- 
tion, or functional performance require- 
ments analysis as it often is referred to, in 
conjunction with FFBDs and special purpose 
documents such as EIMSs, TRSs, and PSs. 
The RAS serves three purposes in document- 
ing the systems engineering process: 1) ini- 
tially, it is used to record the performance 
requirements established for each function; 
2) during synthesis, it is used to show the 



allocation of the functional performance 
requirements to individual system elements 
or a combination of elements; and 3) follow- 
ing evaluation and decision, the RAS 
provides the functionally oriented data re- 
quired in the description of the system 
elements. 

The Time Line Sheet (TLS) is used to 
perform and record the analysis of time- 
critical functions and functional sequences: 
In performing time requirements analysis 
for complex functional sequences, additional 
tools, such as mathematical models or 
computer simulations, may be needed. Time 
requirements analysis is performed in any or 
all of the functional cycles of the process to 
determine whether time is a critical factor. 
The TLS complements the FFBD in its 
ability to show a lower level of detail, as well 
as to illustrate the impact of concurrent 
functions within a given sequence. TLSs are 
used to support the development of design 
requirements for the operation, test and 
maintenance functions. They identify time- 
critical functions and depict the concurrency, 
overlap and sequential relationship of 
functions and related tasks. Time-critical 
functions are those that affect reaction time, 
downtime or availability. 

Synthesis 

Synthesis supplies the "how" answers to the 
"what" outputs of functional analysis. 

Two documentation tools accomplish and 
record the synthesis of design approaches or 
alternative approaches. The Concept 
Description Sheet (CDS) is used to collect the 
performance requirements and constraints, 
as delineated by functional analysis, that 
apply to an individual subsystem or end 
item. The CDS also describes at the gross 
level a design approach for meeting the 
requirements. The Schematic Block Dia- 
gram (SBD) is used to develop and portray 
the conceptual schematic arrangement of 
system elements to meet system and/or 
subsystem requirements. The CDS and SBD 



13 



READINGS IN SYSTEMS ENGINEERING 



are both applicable to all acquisition phases 
and provide the basis for development of the 
descriptions of system elements. 

Evaluation and Decision 

Since program risk and cost are dependent 
on practical trade-offs between stated oper- 
ating requirements and engineering design, 
continual evaluations and decisions must be 
made not only at the beginning of the 
program but throughout the design and 
development activity. 

The Trade Study Report (TSR) is used to 
summarize and correlate characteristics of 
alternative solutions to the requirements 



and constraints that establish the selection 
criteria for a specific trade study area. The 
report also documents the rationale used in 
the decision process and should present risk 
assessment and risk avoidance consider- 
ations. Other tools, such as analytical or 
mathematical models or computer simula- 
tions, may be needed and used in accomplish- 
ing the evaluation and decision process. 

Description of System Elements 

All systems can be defined by a set of inter- 
acting system elements which fall into five 
categories: equipment (hardware), software, 
facilities, personnel, and procedural data. 



Functional Analysis 



User 
Require- 
ments 



Function 
Identification 



Requirements 
Identification 
& Allocation 



Synthesis 



~*(85)r* 



Evaluation 
& Decision 




tOR 



Description of 

System 

Elements 



Basic 
Documen- 
tation 



Functional Flow 

Block Diagrams 

(FFBD) 

Identify and se- 
quence functions 
that must be accom- 
plished to achieve 
system or project ob- 
jectives. Develop the 
basis for establish- 
ing intersystem 
functional interfaces 
and identify system 
relationships. 



Requirements 

Allocation Sheets 

(RAS) 

Define the require- 
ments and constraints 
for each of the func- 
tions and relate each 
requirement to the sys- 
tem elements of 

a. Equipment 

b. Facilities 

c. Personnel 

d. Procedural data 

e. Computer software 

Time Line Sheets 

(TLS) 

Present critical func- 
tions against a time 
base in the required se- 
quence of accomplish- 
ment. 



Concept 

Description Sheets 

(CDS) 

Constrain the de- 
signer to stop at a 
point in the cycle and 
create at the gross 
level a design or syn- 
thesis meeting the 
FFBD, RAS, TLS 
requirements and 
constraints. 

Schematic 

Block Diagrams 

(SBD) 

Develop and portray 
schematic arrange- 
ment of system ele- 
ments to satisfy sys- 
tem requirements. 



Trade 

Study Reports 

(TSR) 

Select, evaluate and 
optimize promising 
or attractive con- 
cepts. Document the 
trade-off and sup- 
porting rationale. 
Consider all possible 
solutions within the 
framework of re- 
quirements. 



Design 

Sheets 
(DS) 

Define, describe and 
specify performance, 
design and test cri- 
teria for the system 
elements 

a. Equipment 

b. Facilities 

c. Personnel 

d. Procedural data 

e. Computer soft- 
ware 



Special 
Purpose 
Documen- 
tation 



End Item 
Maintenance Sheet 
(EIMS)/Te8t Reqmt 

Sheet (TRS)/ 
Production Sheets 
(PS)/Logistic Sup- 
port Analysis 
Record (LSAR) 
Identify mainten- 
ance, test and pro- 
duction functions on 
a specific end item, 
subassembly, and 
component oasis. 



Facility Interface 
Sheets 

(FIS) 

Identify environ- 
mental and physical 
interfaces between 
equipment and fa- 
cilities on an end 
item basis. 



Indenture is carried to the level required for the selected level of engineering to identify, describe and specify. 

Figure 3 Basic and Special Purpose Documentation for Systems Engineering 



14 



SYSTEMS ENGINEERING OVERVIEW AND PROCESS 



Two documentation forms are used to 
describe these system elements: the Design 
Sheet (DS) and the Facility Interface Sheet 
(FIS). The DS is used to establish and 
describe the performance, design and test 
requirements for equipment end items, criti- 
cal components and computer software 
programs. The FIS is used to identify the 
environmental requirements and interface 
design requirements imposed upon facilities 
by the functional and design characteristics 
of equipment end items. The DS and FIS 
provide the basis for the formal identifica- 
tion required for configuration management. 

The systems engineering process pro- 
duces the basic and special purpose docu- 
mentation that controls the evolutionary 
development of the system. Figure 3 
correlates the particular documentation 
associated with each step of the systems 
engineering process. 

The systems engineering process itself 
does not actually produce the system, but 
produces the documentation necessary to de- 
fine, design, develop and test the system. As 
such, a variety of engineering and planning 
documentation is required throughout the 
acquisition cycle, and systems engineering is 
the vehicle used to produce that documenta- 
tion. 

Numerous plans are prepared to define 
which technical activities will be conducted. 
They address the integration of engineering 
specialties requirements, "design-for" re- 
quirements and organizational resource 
requirements, and discuss how progress 
toward system-level goals will be measured. 
The Systems Engineering Management Plan 
is the key planning document that reflects 
these requirements. Contractor compliance 
with these plans is monitored by government 
organizations to ensure that standard poli- 
cies and procedures in the area of systems 
engineering are employed. Additionally, 



specifications are prepared as part of the- 
systems engineering process to form the 
basis for the design and development effort. 
The top-level specification (system or seg- 
ment) is normally approved and draft lower 
level specifications (configuration items) are 
developed reflecting allocated system re- 
quirements to lower level components or sub- 
systems, which designers and subcontractors 
translate into hardware and software pro- 
duction plans. 

In order to provide a continuing assess- 
ment of the system's capability to meet 
performance requirements, the systems 
engineering organization prepares technical 
review data packages, technical performance 
measurement (TPM) reports, analysis and 
simulation reports, and other documenta- 
tion. 

The systems engineering process is one 
approach to providing disciplined engineer- 
ing during all acquisition phases. Although 
current application of the process has focused 
on C/E, D/V, and FSD, systems engineering 
process techniques and principles are equal- 
ly applicable to the analysis and definition of 
production requirements. 

The systems engineering process also pro- 
vides the logic and timing for a disciplined 
approach, with certain internal assurances 
of technical integrity such as traceability. 
Technical integrity ensures that the design 
requirements for the system elements reflect 
the functional performance requirements, 
that all functional performance require- 
ments are satisfied by the combined system 
elements, and that such requirements are 
optimized with respect to system perfor- 
mance requirements and constraints. 

The DSMC Systems Engineering Man- 
agement Guide may be purchased from the 
U.S. Government Printing Office (1991-306- 
417-QL3). 



15 



SYSTEMS ENGINEERING FOR VERY LARGE SYSTEMS 



N9 3-24SBB/0 
Systems Engineering for Very Large Systems /sa e^ 7 ^ 

Recent efforts at Hughes Aircraft 
Company's Space & Communications Group 
have focused on sharpening the definition of 
systems engineering and defining standards 
for improving the implementation of the full 
systems engineering methodology on large 
spacecraft programs. Since these programs 
typically cost in the $100 million range, the 
pressure to deliver specified performance on 
time and on budget is enormous. A casual re- 
view of programs within the author's exper- 
ience has shown that the classical approach 
to systems engineering has been followed 
throughout, but with varying uniformity 
and overall success. The question to answer, 
in the context of even more advanced, more 
demanding projects, is: "How can it be done 
better?" 

The "classical" method of systems 
engineering alluded to above consists of 
requirements definition, technology assess- 
ment, solution synthesis and performance 
verification: four successive steps in the 
design of the mission solution. Typically, 
this is an iterative process, since require- 
ments and technology rarely remain static. 
The customer's mission can be altered by 
events or even by a better understanding of 
the technology, risks or costs involved. 
Synthesized solutions, too, depend on the 
technology available, as well as the question 
asked. Often, the proposed technology does 
not live up to expectations, resulting in a 
"new" solution and reverification: an embar- 
rassing situation at best, an extremely costly 
one at worst. 

When the verification (or testing) phase 
of the systems engineering process uncovers 
a fault, the cause can often be traced to in- 
complete or improperly stated requirements. 
An example of this fact is a problem uncov- 
ered on one particular series of satellites; an 
on-orbit failure resulted in the loss of some 
16 channels of telemetry data. The failure 
analysis, performed by the program's 



by Paul E. Lewkowicz 

Very large integrated systems have always 
posed special problems for engineers. Wheth- 
er they are power generation systems, com- 
puter networks or space vehicles, whenever 
there are multiple interfaces, complex tech- 
nologies or just demanding customers, the 
challenges are unique. "Systems engineer- 
ing" has evolved as a discipline in order to 
meet these challenges by providing a struc- 
tured, top-down design and development 
methodology for the engineer. This paper 
attempts to define the general class of 
problems requiring the complete systems 
engineering treatment and to show how 
systems engineering can be utilized to 
improve customer satisfaction and profit- 
ability. Specifically, this work will focus on a 
design methodology for the largest of 
systems, not necessarily in terms of physical 
size, but in terms of complexity and intercon- 
nectivity. 

The literature has generally defined 
"systems engineering" as in this quote from 
W.P. Chase in Management of System 
Engineering: 

[Systems Engineering is] the process of 
selecting and synthesizing the applica- 
tion of . . . knowledge in order to trans- 
late system requirements into a system 
design and ... to demonstrate that [it] 
can be effectively employed as a coher- 
ent whole to achieve some stated goal 
or purpose. 

This definition points out, in the most 
general terms, that systems engineering is a 
process for ensuring that the customer 
requirements are satisfied. What it also 
implies is that this satisfaction must be 
achieved on time and for the agreed-upon 
price. It is this implicit requirement that is 
most often unfulfilled in complex engineer- 
ing projects. 

° 1988 IEEE. Reprinted with permission of the author, from IEEE 
Aerospace Application Conference, Park City, Utah, February 1988 



PRE0EDINQ PAGE BLANK NOT FILMEI 



£»JNtt1UJ0MUI ttUN£ 



17 



Readings in systems engineering 



systems engineering staff, identified the 
cause as an open circuit in a particular unit. 
This fault produced an abnormally high 
telemetry output signal on one channel, 
which in turn resulted in the degradation of 
all 16 inputs to the telemetry multiplexer. 
Had systems engineering levied a require- 
ment to protect against failure-induced over- 
voltages (via a simple circuit redundancy 
technique at the unit), only the failed tele- 
metry channel would have been lost, instead 
of that of 15 other units as well. 

The point here is that it is a knowledge of 
the needs of the whole system that is re- 
quired, instead of only the needs of the parts. 
This knowledge exemplifies the principle of 
"engineering leverage" whereby a few engi- 
neers, representing a broad experience base, 
performing the logical, methodical systems 
design work, can save money over trial and 
error or crisis-oriented engineering. It is the 
concentration of systems knowledge, the "big 
picture" view, that allows for efficient 
designs all through the system. 

A common question is: "How much sys- 
tems engineering is required for a given pro- 
ject?" This can usually be interpreted as 
"How much will this cost?" Clearly a design 
team with unlimited funds can perform com- 
plete requirements analysis, all manner of 
failure analysis and simulations, and exten- 
sive part and unit environmental testing to 
fully optimize the design of some particular 
product. But if that product is, say, a ball- 
point pen, have they really made it better 
from the manufacturer's standpoint? Or 
have they succeeded in making the most 
expensive writing instrument the world has 
ever known? The application of systems 
engineering techniques to a project is a 
matter of appropriate degree; how much 
engineering is required to ensure the cus- 
tomer's satisfaction becomes the first ques- 
tion any organization must ask before they 
can set up a systems engineering program. 

This example emphasizes the fact that 
systems engineering costs are a direct charge 
to the effort, so the total cost of the engineer- 



ing must be distributed over the entire 
production run. Even if the run is large, as in 
the ballpoint pen case, when the product nor- 
mally sells for 39 cents, if the engineering 
costs run into the millions, then the manu- 
facturer could be in serious trouble. For 
smaller production runs, like a satellite or 
submarine contract, systems engineering 
costs can still drive the final sale price, but 
systems engineering can also reduce the 
price by preventing errors and rework. 

The Systems Engineering 
Methodology 

The procedure followed in systems engineer- 
ing consists of four distinct phases, described 
here in the simplest terms: requirements 
definition, technology assessment, solution 
synthesis and performance verification. 
These sobriquets are intended to be mne- 
monic; the details of what they really signify 
are presented below. 

Requirements Analysis. The initial step 
consists of defining the problem to be solved 
and the constraints on the solution set. This 
is perhaps the single most critical phase of 
the systems engineering process in that a 
misunderstanding of the problem to be 
solved, either in characterizing it or defining 
the context of the solution, can result in an 
erroneous conclusion. As in the satellite 
telemetry example, the customer can be 
somewhat less than satisfied when a partial 
solution is delivered. 

In large systems, the problem definition 
is usually described by the contractual docu- 
ments. The request for proposal (RFP) or the 
statement of work typically contains direc- 
tives as to the overall mission of the system, 
but these are not always completely specific; 
some interpretation of what the customer 
really meant is often required. 

Another aspect of requirements analysis 
often underappreciated is that of constrain- 
ing the solution. The RFP for a program may 
state that only a certain rocket booster or 



18 



SYSTEMS ENGINEERING FOR VERY LARGE SYSTEMS 



parts of a specific grade can be used, but the 
implications of such statements, and. espe- 
cially the implications of the "unstated" or 
"implied" requirements, can have serious 
consequences in the final design. These 
requirements, sometimes called derived or 
secondary requirements, determine the lim- 
its of the parametric trades that can be made 
in characterizing the problem's solution. 

Technology Assessment. Once the basic 
requirements, both primary and secondary, 
are in place and understood by the design 
team, the technology available to solve the 
problem can be examined for suitability. 
This step is intuitively obvious for small 
systems, but when complexity is high, 
making the appropriate choice is not always 
easy. Typical activities in this phase include 
comparative tradeoffs between different 
processes and materials, architectures and 
performance. The technology assessment 
phase may also consider the design and docu- 
mentation methods and the management 
organization to be employed on a specific 
project. Overall, this phase is concerned with 
selecting the best tools for performing the 
system design. 

Solution Synthesis. This is usually the 
most time-consuming step in engineering a 
system to perform complex tasks and meet 
stringent requirements simply because of 
the number of choices available. If the re- 
quirements are well understood and the 
available hardware and software appro- 
priate to the task are known, then trade 
studies can be carried out (on paper) that re- 
sult in myriad viable combinations. During 
this phase, compromises are often required 
in order to satisfy conflicting requirements. 
For example, in a communications system 
design, a large antenna may be desired to 
provide high gain, but this will reduce its 
coverage capability by reducing the beam- 
width. Out of this sea of alternatives must 
come a single "best fit" solution, meeting all 
of the original and derived requirements, es- 



pecially such items pertaining to cost and 
producibility. If it can't be built or bought, 
then it's not the right answer. 

Performance Verification. Last, but defi- 
nitely not least, is the performance verifica- 
tion or testing phase. The task here is to 
prove, with all the rigor possible, that the 
suggested solution does in fact meet all of the 
system requirements in a clearly docu- 
mented way. A standard approach is to 
utilize specification trees and a verification 
matrix to show where each requirement from 
the original customer's source documents is 
captured in lower level specifications. Addi- 
tionally, the verification matrix shows how 
compliance with the requirement is proven, 
either by inspection, test, demonstration or 
analysis. In general, the specification system 
is designed to show a clear, unambiguous 
flowdown of all system requirements into 
individual component designs. The verifica- 
tion phase is the test of this flowdown as well 
as a measure of system performance. 

requirements for successful 
Systems Engineering 

The foregoing text has all been a precursor to 
this: exactly what does an organization have 
to do to apply a full-scale systems engineer- 
ing approach to their work? And, perhaps 
more importantly, what does it cost that 
organization? As expected, in systems engi- 
neering, as in life, there are no free lunches. 
This section details the inputs to the process, 
or what is required by a systems engineering 
organization in order to function properly. 

Formality. First and foremost, a formal, 
planned approach to the systems engineer- 
ing process must be in place. Not only must 
the "generic" methodology for systems engi- 
neering be understood by all involved, the 
detailed program plans for the specific appli- 
cation of systems engineering must reflect 
this commitment. The major components in 
the formal system are review procedures, 



19 



READINGS IN SYSTEMS ENGINEERING 



specification generation and maintenance 
(or "configuration control") procedures, and 
planning. 

As can be deduced from the discussion of 
the phases of the systems engineering pro- 
cess, some degree of review and checking is 
inherent to all operations. The establish- 
ment of specification and design review 
teams to examine the documents (e.g., speci- 
fications, trade study reports, etc.) and help 
polish them into complete and correct inputs 
to the final design cannot be avoided. With- 
out concrete review milestones, the design 
will often wander and become unfocused 
with respect to its objectives, which results 
in inefficient time and money management. 

Since the specifications define the prob- 
lem to be solved and its constraints, it is 
clear that they must be reliable and well doc- 
umented. The configuration control function 
is to provide a routine for the introduction, 
validation and documentation of new re- 
quirements and the updating of old ones 
within the system. This is an important step 
in the review process, as well as the design 
process, in that all parties (customer and 
contractor alike) need a stable, well-defined 
basis of judgment for the validation of the 
system. 

Planning is mentioned last in this case 
only for emphasis: without complete plan- 
ning for the entire system design effort, from 
requirements definition through systems en- 
gineering, production, and final deployment, 
the project is doomed to failure. Every man- 
agement textbook in the world expounds this 
fact in detail, yet weak planning is still a 
major cause of cost overruns and poor perfor- 
mance in all types of industry. 

Information Exchange. While formality 
and procedure allow tight control of the 
requirements, informality and open commu- 
nications are the key to efficient design and 
problem resolution. Not only must the con- 
tractor communicate effectively with the 
customer, but the various elements of the 
contractor's organization (management, sys- 



tem engineers, unit designers, etc.) must all 
talk to each other in order to completely 
understand the requirements. In every pro- 
gram there are stated goals and hidden 
goals, real requirements and perceived 
requirements; it all depends on where the 
observer is looking from. Communications 
and open channels between all participants, 
regardless of title or rank, are absolutely 
essential to all phases of the job. 

Technology Base. "Technology" in this 
context means more than the hardware and 
software that can be employed in a design 
solution; it encompasses the organizations 
and information architectures as well. As a 
system becomes larger and more complex, so 
too does the technology or "knowledge base" 
required to fully define the implementation 
of system requirements. Such a base might 
include other contractors, national resources 
(e.g., the Space Transportation System), spe- 
cialized electronic devices, etc. In short, prac- 
tically any conceivable problems, and even a 
few inconceivable ones, can come up in sys- 
tems design. To deal effectively with them, 
the systems engineering team must have the 
knowledge and experience to recognize solu- 
tions from a wide selection of possibilities. 

Dedication and Staffing. Finally, the one 
factor that takes system engineering from an 
abstract concept to a practical reality is the 
dedication of the people involved. In order to 
even begin a design for a complex system, a 
design team is required. Not a single guru 
and a few part-time acolytes, but a team of 
committed managers and engineers with ex- 
perience in real-world problem solving, tech- 
nical breadth and clearly defined roles in the 
systems engineering process. Without this 
core team, the continuity and rigor required 
by the process to ensure a coherent, effective 
solution cannot possibly exist. 

Just as planning is the key to a successful 
project, leadership is the key to a successful 
team. The complexity of the designs under 
discussion are such that (typically) a wide 



20 



SYSTEMS ENGINEERING FOR VERY LARGE SYSTEMS 



range of talents are needed to arrive at a 
solution. This diversity can be dangerous 
without direction, because diversity is just a 
polite name for chaos waiting to happen. A 
group with a broad technical background, 
when presented a problem without leader- 
ship, will always seek to maximize its 
entropy. The project staff must be directed 
and focused at all times in order to move 
through the systems engineering process. 
After all, efficiency and minimal engineer- 
ing costs concern the entire group. The depth 
necessary to perform the detailed designs 
need not come from the systems staff, 
however; this is often not possible given the 
generalist nature required of them. Most 
companies employ a unit engineering staff to 
design the components of the complete 
solution, which simply reflects the top-down 
design approach of breaking each require- 
ment down into smaller and smaller 
functional blocks. 

An important factor to consider is time. It 
may take several months or even years to 
complete the design of a complex system, so 
continuity becomes a factor in the staffing of 
the design team. The deleterious effects of 
change on an organization are well known, 
and so are those of miscommunication. The 
training of systems engineers, whether 
through formal schooling or on-the-job edu- 
cation, is the first step toward building a 
self-perpetuating, self-replicating design 
methodology. Experienced staff members are 
able to produce more and overcome obstacles 
better than those less experienced; reinven- 
ting the wheel is avoided. Additionally, 
experienced people add synergy to the team 
by virtue of shared experiences. Synergism 
in the design process is how the engineering 
leverage of systems engineering is released, 
by the magnification of individual efforts. A 
fringe benefit of this magnification is growth 
in the individuals involved. The less 
experienced become more experienced and 
leadership skills are developed and honed. 
Not only does the design process (and 
product) continue to improve but, through 



continuity and growth, the staff benefits 
personally as well. 

What about the individual roles of the 
staff members? The need for a broad know- 
ledge base, for generalists, is clear, but what 
do they do? As in any team-building 
situation, all members need clearly commu- 
nicated job descriptions and management 
expectations; this applies to all members of 
the project team from the most senior man- 
ager to the last clerk. Once the work has 
started, they need tangible feedback on what 
is going correctly, according to expectations, 
and what is not. The immediate benefit to 
the organization is clear. Job satisfaction in- 
creases, and with it, a concomitant rise in 
overall productivity. Again, the process, 
when properly managed, feeds upon itself to 
work more efficiently. 

Cost vs. Benefits of Full-Scale 
Systems Engineering 

The requirements levied upon systems de- 
sign for very large projects are simple: pro- 
vide full customer satisfaction on time and 
on budget for a set of diverse and complex 
functional specifications and interconnec- 
tions. Likewise, the technology appropriate 
to this task is (hopefully) equally clear: 
employ a formal, full-scale systems engi- 
neering approach to meeting this challenge. 

Costs: 

- Management must be willing to allow 
group synergy to make decisions; the 
"group think" approach is mandatory. 

- Personnel must be dedicated and im- 
mersed in the systems engineering of a 
single system. Teamwork and continuity 
must be fostered and preserved. 

- The systems engineering organization 
can exhibit all the negative aspects of a 
bureaucracy if not managed precisely. 

- Careful, rigorous planning is required for 
all aspects of the program up-front, before 
the work begins, which often means extra 
bidding expense. 



21 



READINGS IN SYSTEMS ENGINEERING 



Benefits: 

+ Customer satisfaction is enhanced 
through demonstrated performance and 
the opportunity for full customer involve- 
ment in the design process. 

+ Manageability is improved by accurate, 
more complete planning and a well- 
defined staff structure. 

+ Contingencies are worked out in advance, 
resulting in fewer surprises during the 
design, test and production phases. 

+ Better cost performance is achieved due 
to reduced redesigns, reworks and "patch- 
es." 

After an analysis of the costs and benefits 
of implementing a systems engineering 
solution to a complex design problem, it 
becomes apparent that the benefits outweigh 
the costs, especially in terms of the potential 
for productivity and cost improvements. The 
chief drawback of this method is that it is 
difficult to implement in organizations that 
do not already practice some form of systems 
engineering, due to the cultural adjustments 
that are often necessary. Once the need for a 
rigorous design methodology is apparent, the 
systems engineering process of requirements 
analysis, technology assessment, solution 
synthesis and performance verification can 
be utilized to provide an efficient, cost- 
effective solution to the managerial and 
technical challenges. 



The author wishes to thank Dr. Thomas A. 
Brackey, W. Richard Brown, and Gdyien 
Miyata of the Hughes Aircraft Company for 
their support and mentorship in several com- 
plex design projects. 

References 

Chase, W.P. Management of System Engi- 
neering, as quoted in Hughes, Seminar. 

Defense Systems Management College. Sys- 
tems Engineering Management Guide, U.S. 
Air Force, 3 October 1983. 

Hughes Aircraft Company. Systems Engi- 
neering Seminar for General Motors, internal 
memorandum, 1987. 

"S&CG Practice 5-0-53," internal 

memorandum, 21 July 1987. 

. "Systems Engineering Division Mis- 
sion, Goals, and Objectives," internal memo- 
randum, 8 October 1987. 

IEEE, Standard Dictionary of Electrical and 
Electronics Terms, IEEE Press, Third Edi- 
tion, 1984 (ANSI/IEEE Std 100-1984). 

IEEE Spectrum special report, On Good De- 
sign, Volume 24, Number 5, May 1987. 

U.S. Government MIL-STD-499. 



22 



WHAT IS A SYSTEM? 



What is a System? NASA's Phased Project /6 -$ £ 73 
Description n j ^^ 

From the MSFC Systems Engineering Handbook (1991) fs ^ ( 



Systems engineering is defined in MIL-STD- 
499A as 

. . . the process(es) required to trans- 
form an operational need into a 
description of system performance 
parameters and a system configuration 
through the use of an iterative process 
of definition, synthesis, analysis, de- 
sign, test and evaluation. It includes 
the integration of related technical 
parameters and ensures compatibility 
of all physical, functional, and program 
interfaces in a manner that optimizes 
the total system definition and design. 
In addition, systems engineering 
integrates reliability, maintainability, 
safety, survivability, and other such 
efforts into the total engineering effort 
to meet cost, schedule and technical 
performance objectives. {Engineering 
Management, May 1, 1974) 
Systems engineering is a continuous, 
iterative process that has a built-in feedback 
mechanism. It is used throughout a project 
or program's life cycle to arrive at the best 
system architecture and design possible. 
Just when systems engineering began to be 
practiced as a separate discipline is open to 
debate, but there seems to be general agree- 
ment that formal recognition and definition 
of the process started after World War II. 
Large, complex post-war development 
projects such as the first U.S. ballistic 
missiles and NASA's Apollo program exhib- 
ited the characteristics which created the 
need for systems engineers. 

Among these project characteristics are: 

• Large design teams with many highly 
specialized designers 

• Many contractors involved, widely sepa- 
rated geographically, complicating com- 
munications 



• Many hardware and software systems in 
concurrent development 

• Complex operational and logistic support 
requirements 

• Constrained development time 

• High level of advanced technology 
(Systems Engineering Management 
Guide, U.S. Government Printing Office, 
1986). 

There are many definitions of a system. Two 
of these are listed below: 

• A system is a set of interrelated compo- 
nents working together toward some com- 
mon objective. (Blanchard, Benjamin S. 
and Fabrycky, Wolter J., Systems Engi- 
neering and Analysis, Prentice Hall, Inc., 
1990) 

• A system is a grouping of parts that 
operate together for a common purpose. 
For example, an automobile is a system of 
components that work together to provide 
transportation. An autopilot and an 
airplane form a system for flying at a 
specified altitude. (Forrester, Jay W., 
Principles of Systems, Wright-Allen Press 
Inc., 1968). 

Systems engineering is a cyclical process as 
depicted in Figure 1. The terms shown in 
this figure are explained in the following 
paragraphs. 

1. Project and Mission Requirements/ 
Need Definition can also be termed as "cus- 
tomer engineering." It is the process by 
which the needs of the customer (the princi- 
pal investigator or other significant parties, 
such as Congress or other budgetary author- 
ity) are determined. This allows the systems 
engineer to define requirements for a system 
that will meet the needs of the customer. 



2.< 



READINGS IN SYSTEMS ENGINEERING 



9. Verification and Validation 



1. Project and Mission Requirements/Need Definition 



2. Risk Analysis/Management 



8. Technical 
Oversight 



7. Configuration 
Management 



6. Implementation Planning and 
Systems Integration 




3. Systems Analysis 



4. Concept 
Development 



5. Derived Requirements Definition 



Figure 1 Systems Engineering Cycle 



2. Risk Analysis/Management is a 
continuing process to identify and assess the 
risks involved with the development and 
operation of the system. These include tech- 
nical, schedule, cost and organizational 
risks. Following the identification of the 
risks involved, the system engineer then de- 
velops an implementation plan to control 
and, if possible, reduce risks. 

3. Systems Analysis involves under- 
standing how the key mission and system 
functional elements interact. The mission 
analysis translates the users' needs into 
functional/performance requirements and 
design constraints. A functional analysis 
takes these requirements and breaks them 
down into specific tasks. 

4. Concept Development is the process of 
making informed trade-offs among the var- 
ious options to select the one that best meets 
the requirements and design constraints. 
Preliminary design and performance re- 
quirements and implementation architec- 
ture are the results. 



5. Derived Requirements Definition is 
the process of translating mission and func- 
tional analysis results, system operational 
concepts, and the selected system architec- 
ture into a set of system performance and 
interface requirements. At this level, the 
requirements must specify either functional 
or interface criteria only, without presenting 
design solutions. This gives the detail 
designers the flexibility needed to arrive at 
design solutions that meet the requirements. 

6. Implementation Planning and Sys- 
tems Integration is a complex activity 
resulting in a coherent, integrated set of 
implementation tasks and responsibilities 
for the design, development, fabrication, ver- 
ification and operation of the required 
system. It requires negotiation between the 
system requirements definition personnel 
and the system implementation (develop- 
ment) personnel. The plan must also consid- 
er the project constraints of schedule and 
budget while avoiding unnecessary risk. 



24 



WHAT IS A SYSTEM? 



7. Configuration Management activities 
ensure that controlled definition of all 
engieering documentation is maintained and 
correct information is distributed to all 
appropriate parties in a timely manner. This 
is one of the most important responsibilities 
of the systems engineering organization. On 
larger programs that have large numbers of 
people involved, this process becomes even 
more critical. This activity is also the mecha- 
nism by which the system development 
process is documented (i.e., design knowl- 
edge capture). 

Configuration Management establishes 
the system to control the requirements and 
configuration of hardware and software, 
evaluate changes, and maintain the defini- 
tion of the configuration via baselined docu- 
mentation and released drawings. 

8. Technical Oversight serves two func- 
tions. First, it ensures that all the subsys- 
tems work together. Second, it implements 
mechanisms to guarantee that the developed 
and documented architectural concept is not 
inadvertently changed during the develop- 
ment process. This allows the developer to 
certify that the system, which is ultimately 
tested, will meet the customer's require- 
ments. Technical oversight consists of the 
technical reviews and audits that gather 
consensus from all parties involved to ascer- 
tain that the effort at any given time is 
correct and adequately planned for the 
continuance of the work. 

A specific task for the systems engineer 
to perform is assuring that the systems re- 
quirements are understood and correctly 
implemented by the design organizations. 
This responsibility requires the systems 
engineer to work closely with the design 
organizations throughout the program. At 
the same time, the systems engineer must 
recognize that the initial set of systems 
requirements will not be perfect. During 
design evolution or because of the inability of 
a subsystem to meet its intended functional 
requirements, changes in the systems 
requirements will be necessary, and the 



systems engineer should view these changes 
as a normal part of the design process. Avoid 
the tendency to view the Systems Require- 
ments Specification as something, once base- 
lined, that is final and unchangeable. 

9. During the Verification and Valida- 
tion portion of the development activity, the 
characteristics and performance of the sys- 
tem are compared to the requirements and 
specifications. Tests, analyses and demon- 
strations are performed to verify that the 
hardware and software satisfactorily meet 
the performance requirements of the system 
specifications. 

NASA PHASED PROJECT DESCRIPTION 

In the planning of major projects, critical 
requirements must be well defined and the 
necessary technology must be available. If 
these criteria are met, there will be an ac- 
ceptable level of risk in meeting technical 
goals with reasonable cost and schedule. 

To ensure that the program is at a proper 
level of maturity when Congress approves 
major funding for design and development, 
projects go through various phases of analy- 
sis and definition. There are five phases in 
the life cycle of a typical successful project: 
pre-Phase A (concept study), Phase A 
(preliminary analysis), Phase B (definition), 
Phase C (design) and Phase D (development/ 
operations). Depending on the complexity of 
the system, funding availability and launch 
schedules, a project may combine phases or 
add intermediate phases. Common 
variations would include combining pre- 
Phase A and Phase A, adding an advanced 
development phase between Phase B and 
Phase C, combining Phase C and Phase D 
into Phase C/D, or moving operations out of 
Phase D into a separate phase. As a further 
example, the Space Shuttle program had 
both a Phase B' (B prime) and Phase B" (B 
Double-prime) in order to further refine the 
definition and requirements of the system 
before proceeding into Phase C. Figure 2 
depicts a typical phased project flow in which 



25 



READINGS rN SYSTEMS ENGINEERING 



I 


tf AJOR MANAGEMENT DECISK 


)NS 






lm 




1 


PRE-PHASE A/ 


Jjl) 




X(2) 






PHASED 


PHASE A 




PHASE B 




PHASE C 




PRELIMINARY 




DESIGN 




DESIGN 




DEVELOPMENT/ 


ANALYSIS 












OPERATIONS 


• Develop Project 


• Refine Selected 


• Develop Detail of 


• Develop and Test 


Objectives 




Alternative Concepts 




Selected Concept 




• Manufacture 


• Assess Feasibility 




• Conduct Systems 




• Develop Specific 




• Checkout 


• Identify Research and 




Analysis 




Requirements and 




• Operate 


Advanced Technology 




• Develop Preliminary 




Design Specifications 




• Evaluate 


Requirements 




Requirement and Design 




• Develop Plans for 




• Distribute Results 


• Identify Support 




Specifications 




Manufacturing, Testing, 




Requirements Areas 




• Define Support 




Operations, Supporting 






• Develop Gross Plans for 




Requirements 




Systems, Facilities, etc. 






Implementation 




• Assess Preliminary 




• Initiate Required 






• Perform Trade-Off 




Manufacturing and Test 


— ► 


Long Lead Advance 


^ 




Analysis 




Requirements 




Development and Define 






• Identify Favorable and 




• Identify Advanced 




Plan for Supporting 
Development 






Unfavorable Factors 




Technology and 








• Define Relationships to 
Programs 




Advanced Development 
Requirements 




• Develop Schedules and 
Estimates of Costs 






• Perform Cost Analysis 




• Assess Costs and 
Schedules 

• Define Management 
and Procurement 
Approaches 

• Perform Trade-off 
Analysis 

• Perform Operation 




• Refine Management and 
Procurement Plans 






\ f ♦ l 

• Feasible Project Concepts for • Preliminary Design and • Project Design and • Completed Project 


Detailed Study Specifications Specification including 


• Preliminary Schedule, Manufacture Teat and 


Resource and Management Operation Plans 


Plans • Schedule Resources 


• WBS Management and 










Procurement Plans 







(1) Mission need statement approved 

(2) Mission need statement reaffirmed 



Source: MM7120.2, Project Management Handbook 



Figure 2 NASA Program Phases 



pre-Phase A has been combined with 
Phase A. 

Safety is a critical systems engineering 
function that must be considered during all 
program phases and in all studies and analy- 
ses. In short, although safety is organization- 
ally the responsibility of S&MA, it is a 
responsibility of all program participants 
and should be a primary consideration 
throughout the systems engineering process. 

Figure 2 shows the major activities in 
each phase, as well as the outputs and major 



decision points. Note that this description 
pertains to the typical program, in which 
NASA contracts with industry to do the 
Phase C/D activity. Other types of programs 
include small, contracted efforts, as well as 
both large and small in-house programs 
where NASA may retain all or part of the 
design and development responsibility. 

The typical program review phasing 
includes many more activities and formal 
reviews than are shown in Figure 2. For 
completeness, these are introduced here and 



26 



WHAT IS A SYSTEM? 



Preliminary 
Analysis 
Phase A 



Concept 
Definition 



PRR 



Definition 
Phase 6 



Requirements 
Generation 



PDR 

T 

Design 
Phase C 



CDR 

V 



Preliminary 
\ Design 



Final 
Design 



AR 



T 



Development/Operation 
Phase D 



Fabrication 



Verification 



Integration 



Operation 



Post 

Flight 

Analysis 




Launch/Vehicle/Payloads 



ATP 



IPL 
RR 
V7 



IPL 
PDR 

\7 



IPL 
CDR 



Mission 
Definition 



Interface 
Definition 



Final 
Design 



Space System Carrier 

Notes: PRR - Preliminary Requirements Review 
PDR - Preliminary Design Review 
CDR - Critical Design Review 
AR - Acceptance Review 
ATP - Authority to Proceed 
D?L - Integrated Payload 



IPL IPL 
GOR FOR 

\7 \7 



IPL 
IRR 

\7 



FRR Launch 
\7 T7 



Verification & 
Integration 



Ground & 

Flight 
Operations 




RR - Requirements Review 
GOR - Ground Operations Review 
FOR - Flight Operations Review 
IRR - Integrated Readiness Review 
FRR - Flight Readiness Review 



Figure 3 Typical Program Review Phasing 



shown in Figure 3. This figure also serves to 
relate the major reviews to the project 
phases and to show the more detailed inte- 
gration activities associated with attached 
payloads and Spacelab-kinds of experiments. 
At MSFC, the Program Development 
(PD) Directorate is responsible for nurturing 
new projects from idea conception through 
concept definition supporting preliminary 
design. Systems engineering is emphasized 
and utilized throughout this process, hoth in- 
house and during contracted studies. Typi- 
cally, concepts that have matured through 
this process and gained Congressional new 
start approval to become official projects are 
then moved into project offices. The new 
start review and approval process begins ap- 
proximately two years in advance of Phase 
C/D authority to proceed (ATP) at which 
point funds are applied to begin a major 
design and development effort. That two- 



year period is used to execute the definition 
phase (Phase B) and prepare the request for 
proposal (RFP) for Phase C/D. The new start 
approval process includes a definition review 
or non-advocate review (NAR) generally con- 
ducted during the Phase B activity at a time 
when the project manager, Center manage- 
ment, and Headquarters program office 
deem appropriate. Results of the NAR are 
factored into the Phase C/D RFP, as well as 
the budget approval process. Note that this 
timeline pertains principally to large pro- 
grams which include in-house and contract- 
ed efforts. The timeframe could be much 
shorter for smaller projects such as experi- 
ments. Figure 4 shows the overall systems 
engineering process flow in Program Devel- 
opment (PD). 

In the course of developing the pre- 
liminary systems requirements and the 
conceptual design, PD uses many of the same 



READINGS IN SYSTEMS ENGINEERING 



Program 
Planning 



Program 
Planning 



MisRion Planning 
and Analysis 



Acquisition 
Planning 



Operations Planning 
and Analysis 



Advanced Mission and 
Systems Analysis 



Space Technologies 
Applications 



Project Planning 



Budget Planning 
and Implementations 



Feasibility and Definition 
Studies 



Manpower Planning 
and Analysis 



Progra m/Sci ence 
Requirements 



Program Control 



'"' 



Concept Definition & 
Design 




Preliminary SyBte ma 
Requirements 



Advanced Development 
Requirements 



Supporting/ Advanced Research 
and Technology 



Preliminary 
Design 



Systems/Subsystems 
Analysis &Trades 



Cost Modeling 8 
Estimating 



Headquarters Approval Lead to 
Program Initiation Agreement 



Figure 4 Systems Engineering Process Flow in Program Development 



analysis tools and techniques that are em- 
ployed by Science & Engineering (S&E) in 
later program phases. The principal differ- 
ences in the outputs of the two organizations 
are the quantity, format and maturity of the 
documentation and the level of detail in the 
analyses. In summary, the analyses and 
trade studies by S&E are to refine, not re- 
peat, the concepts developed by PD in sup- 
port of design implementation. PD develops 
the conceptual approach and S&E develops 
the design implementation. 

Pre-Phase A (Concept Study) 

A pre-Phase A study may be accomplished 
within the engineering capability of Pro- 
gram Development or contracted with 
funding from one of the major NASA Head- 
quarters offices. Successful results from this 
study would provide justification to initiate a 
Phase A study or additional pre-Phase A 
studies. The genesis of new ideas requiring 



further study can come from a variety of 
sources: industry, the scientific community, 
university and research centers, MSFC con- 
tractors and associates, or even from within 
MSFC itself. Typically, such ideas receive a 
top-level examination by cognizant 
MSFC/PD personnel. A quick assessment of 
objectives, requirements and the total mis- 
sion concept is performed. Often, new ideas 
are shared with colleagues through propos- 
als (either in response to an RFP or unsolicit- 
ed), technical papers at professional society 
meetings, or "white papers" propounding the 
new idea/concept. From an MSFC in-house 
weeding out process, concepts are identified 
for further (Phase A) study. 

System functional concept trades are per- 
formed during the pre-Phase A period, 
generally at a fairly cursory level of detail. 
This process eliminates architectures that 
are too costly or time-consuming to develop. 
They are conducted at a level sufficient to 
support the definition of the top-level system 



28 



WHAT IS A SYSTEM? 



requirements. Architectural options are the 
result. Some of the primary sources for this 
identification of concepts include brain- 
storming, past experience, examination of 
other systems and intuition. 

Cost estimates are developed in pre- 
Phase A and are usually at a very prelimi- 
nary level due to the lack of detailed systems 
definition. These estimates are based pri- 
marily on parametrics adjusted for the new 
program, taking into account differences in 
mission, size, complexity and other factors. 

Phase A (Preliminary Analysis) 

A Phase A study is the preliminary analysis 
of a space concept. These concepts could have 
come from a pre-Phase A study or from other 
sources within or external to NASA. The ma- 
jority of concepts that are studied at MSFC 
are assigned by NASA Headquarters and 
funded accordingly. Documentation in this 
Phase usually consists of study reports and 
briefing charts. 

Schedules are developed during Phase A 
studies by Program Development in conjunc- 
tion with the organization performing the 
study (contractor, PD, S&E). The schedules 
include an overall program schedule pro- 
vided by MSFC and a detailed technical 
schedule developed by the contractor. 

The overall program schedule depicts im- 
portant milestones that establish the start 
and finish dates of each study phase, includ- 
ing design, development, launch, and oper- 
ations. Programmatic milestones are also 
shown. These are dependent on the federal 
budget cycle plus proposal preparation and 
evaluation time. The contractor schedule 
depicts the major activities and phasing 
required to develop the hardware in time to 
meet the scheduled launch date. Since this is 
a concept study, the detail schedule is still at 
a relatively high level and would not show 
activity below the system level. 

Cost estimates developed during Phase A 
are generated using a parametric cost 
analysis system in conjunction with the cost 



database discussed above. The has access to 
several cost estimating systems, both 
government and commercial. One example is 
the GE/RCA Price Model. Each model is 
unique with special capabilities and limita- 
tions. Complexity factors and Cost Estimat- 
ing Relationships are applied to the 
estimating software using system weight as 
the independent variable. A factor is applied 
to the hardware/software costs to account for 
wraparounds such as project management, 
test and verification, percent new design, 
operational complexity, hardware complex- 
ity, similarity to other projects or develop- 
ment activities and others. As each system is 
defined in more detail and the system weight 
is further refined, the cost estimates become 
more realistic and provide a higher confi- 
dence level in the results. 

A cost/risk analysis and assessment is 
usually completed near the end of each 
Phase A study. The analysis is accomplished 
with special software that uses statistical 
techniques, including a Monte Carlo simula- 
tion. The results predict the probability of 
completing the program within the estimat- 
ed cost. A risk assessment, which follows the 
analysis, should identify areas of high risk 
that require further cost analysis or possibly 
further trade studies to look at alternate sys- 
tems that would lower the potential costs 
without sacrificing technical capability. 

As part of the study activity, the contrac- 
tor provides a detailed risk analysis and 
assessment to establish a high level of confi- 
dence for the program cost. The cost estimate 
established during this phase will provide 
NASA Headquarters with the funding 
requirements to be approved by Congress 
before the development program can begin. 

The processes occurring during Phase A 
include: 

• Development of project objectives 

• Assessment of project feasibility 

• Identification of research and advanced 
technology requirements 



29 



READINGS IN SYSTEMS ENGINEERING 



• Identification of support requirements 
areas 

• Performance of trade-off analyses 

• Identification of favorable and unfavor- 
able factors 

• Definition of relationships to other 
programs 

• Selection of systems concepts 

• Identification of maintenance, technology 
insertion, and disposal concepts of 
payload and orbital debris 

• Environmental Impact Analysis. 

The outputs from Phase A, which become the 
inputs to Phase B, are in the form of reports 
or annotated briefing charts and include in- 
formation on: 

• Concept definition 

• Preliminary system requirements 

• Preliminary configuration layouts 

• Point designs 

• Preliminary implementation plans 

• Preliminary schedules 

• Preliminary cost estimates 

• Environmental impact. 

Phase b (Definition and 
Preliminary Design) 

This phase of the project consists of the re- 
finement of preliminary requirements, cost 
estimates, schedules and risk assessments 
prior to starting final design and develop- 
ment. 

Once the feasibility of an idea is estab- 
lished, the concept definition phase is begun 
to explore alternatives to meet the docu- 
mented mission need. Competition and inno- 
vation should be employed to ensure that a 
wide variety of alternatives are identified 
and examined. Modeling and computer ana- 
lysis are required to assess the best concepts. 

The goal of a concept definition activity is 
to determine the best and most feasible 
concept(s) that will satisfy the mission and 
science requirements. Generally, the re- 
quirements available at this point in time 



are Level I (NASA Headquarters) require- 
ments from preliminary activities. 

Level I requirements are broad mission 
needs and objectives. Occasionally, there 
may be some Level II (project office level) re- 
quirements at this time. 

The mission need determination is the 
first step in a multifaceted preliminary con- 
cept definition activity. This is the step that 
is first performed at a NASA Headquarters 
or Center level (or industry, university, etc.) 
and is the precursor to concept development. 
The mission need determination is that part 
of early mission planning that identifies a 
scientific knowledge need or gap that could 
be met with some kind of NASA sponsored 
activity. A set of Level I requirements is gen- 
erally developed during or just prior to the 
activities described in the following para- 
graphs. 

A feasibility analysis is conducted to de- 
termine the viability of the project. The 
study report usually includes requirements, 
objectives, problems, opportunities and costs. 

A utility analysis is then conducted to de- 
termine the value of a project. The following 
criteria may be considered during this study: 
the needs met, the scientific knowledge ac- 
quired, the political benefits, or potential 
spinoffs and applications. 

Certain satellites and/or instruments are 
selected for a more detailed level of design. 
The Preliminary Design Office of Program 
Development performs these studies. This 
office is a miniature replication of the capa- 
bilities of the laboratories at MSFC: Propul- 
sion, Guidance, Navigation and Control, 
Electrical Power, Avionics, Structures, 
Operations, etc. One difference is the empha- 
sis by Program Development in developing 
credible cost estimates. Cost is an important 
differential, but often other factors, such as 
mission risk or incompatibility with other 
instruments that may be grouped on a com- 
mon satellite, may predominate. 

Throughout the Phase B period the con- 
cepts that were developed during Phase A 
are iteratively reviewed and analyzed. Using 



30 



WHAT IS A SYSTEM? 



trade study techniques, the concepts' capa- 
bilities are compared to the system require- 
ments. Those concepts that consistently 
satisfy the requirements are identified and 
refined. Any concepts that do not meet 
performance and other requirements are 
scrutinized very closely for possible elimina- 
tion. Following the examination of those 
that do not perform well, assessments are 
made regarding their augmentation to dis- 
cover the degree of change necessary to bring 
their performance into scope. The concepts 
that have to change too much or would 
experience severe budgetary and/or schedule 
impacts are deleted from the concept defini- 
tion and analysis cycle. This allows the ana- 
lysts' energies to be focused on those concepts 
that are valid and workable. 

These trade studies provide a more de- 
tailed look at the architectural concepts and 
result in a narrowing of the field of candi- 
dates. Trades performed during this time 
consider such things as cost, schedule, life- 
time and safety. The evaluation criteria used 
to assess alternative concepts are developed 
to a finer level of detail than for earlier sys- 
tem trades. 

Cost estimates from Phase A are refined 
as further detailed requirements are identi- 
fied during Phase B. The cost estimating 
process is still dependent on parametric ana- 
lysis. The Program Development cost office 
works closely with the study contractor in 
evaluating costing methodology and continu- 
ously compares government cost estimates 
with those of the study contractor. Should a 
large discrepancy occur, the assumptions 
and schedule inputs of the study contractor 
are examined. If this examination yields val- 
id assumptions and schedules, the NASA 
estimates are adjusted. The cost estimation 
process goes through continuous iterations 
during the study to reflect the evolution of 
detail resulting from trade studies. 

Schedules are developed during Phase B 
by the task team program control personnel 
and by the study contractors. Schedules de- 
veloped by the task team are expanded from 



the Phase A overall program schedules. In 
addition, other schedules are developed that 
include Phase C and D procurement strate- 
gies, cost phasing and project manning 
requirements. The study contractor sched- 
ules are expanded to lower levels of the work 
breakdown structure (WBS) to include 
subsystem development, program manage- 
ment, manufacturing, verification, logistics 
planning, operations planning and other 
technical areas. The schedule detail would 
show the phasing of all major activities 
through launch and the follow-on operations. 

As in Phase A, the typical documentation 
of this phase consists of reports and briefing 
charts. 

The processes occurring during Phase B 

include: 

• Refinement of selected alternative 
concepts 

• Performance of trade-off analyses 

• Performance of system analyses and 
simulations 

• Definition of preliminary system and 
support requirements 

• Definition and assessment of preliminary 
manufacturing and test requirements 

• Identification of advanced technology and 
advanced development requirements for 
focused funding 

• Refinement of preliminary schedules 

• Refinement of preliminary cost estimate 
and trade study results which support 
selection of baseline for cost estimate 

• Assessment of technical , cost, and sched- 
ule risks 

• Assessment and refinement of the Mis- 
sion Need Statement. 

The outputs from Phase B, which become the 
inputs to Phase C, may include (in the form 
of study reports and annotated briefing 
charts) information related to: 

• Preliminary WBS 

• System requirements 

• Preliminary interface requirements 



31 



READINGS IN SYSTEMS ENGINEERING 



PHASE A 

Preliminary 

Analysis 



PHASE B 
Definition 



PROGRAM 
DEVELOPMENT 



PDO 



PHASE C 
Design 



TASK TEAM 




PHASED 

Development/ 
Operations 



PROGRAM/PROJECT OFFICES 




SCIENCE & ENGINEERING In-depth Technical Support 





INSTITUTIONAL & PROGRAM SUPPORT Support & Services 



I 



I 



I 



Source: PD Lead Engineer's Guide 
Figure 5 MSFC Support Relationships in Project Phases 



• Management and procurement ap- 
proaches 

• Program Implementation Plans 

• Request for Proposal (RFP) inputs, where 
applicable. 

Phase B is normally the final phase of 
activity within Program Development. A 
separate core of people is selected to form a 
task team to manage the Phase B contract. 
At the beginning of Phase B, a chief engineer 
is appointed to the task team (or project 
office) to provide consultation to the task 
team manager on all related engineering 
matters. The chief engineer also helps 
ensure that the study contractor uses accept- 
able engineering practices and sound 
judgment during the course of the study. The 



chief engineer is often the deputy to the task 
team manager and is usually the first Sci- 
ence and Engineering representative sub- 
stantially involved in the process. The chief 
engineer's office has personnel resources 
available to support the project as needed 
during the study. Additional engineering 
support from S&E may be used at the discre- 
tion of the chief engineer. The chief engineer 
plays a key role in determining the state of 
technical maturity of the project for starting 
the design and development phase. 

At the conclusion of Phase B, the task 
team is converted to a project office, and it is 
no longer under the direction of program 
development. On large projects, such as 
Space Station, a project office might be 
created prior to Phase B; in that case, 



32 



WHAT IS A SYSTEM? 



Program Development (PD) support becomes 
minimal (such as cost estimating and limited 
programmatics) and S&E plays a major role 
in the Phase B engineering activities. 

At MSFC, it is not uncommon to have 
more than one directorate providing 
engineering or technical support to a project 
throughout its life cycle. The transition of 
engineering support is depicted in Figure 5. 

Figure 5 shows that Program Develop- 
ment typically performs most, if not all, of 
the technical support during Phase A. As the 
project life cycle evolves, the S&E Director- 
ate takes on a larger and larger role as PD's 
involvement tapers off. The exact point at 
which S&E gets involved varies depending 
on the size and priority of the project at 
MSFC, as well as the availability of S&E 
manpower resources. In every case, however, 
Phase C and D activities are exclusively the 
domain of S&E. 

The extent of information and the level of 
detail available at the end of Phase B to 
begin the Phase C design are variable and 
become a function of the time and money 
made available to the PD organization for 
the conduct of Phase B studies. As a result, 
significant efforts may be needed at the 
beginning of Phase C to refine many of the 
Phase B analyses. 

The hand-over of technical responsibility 
from PD to S&E is an interface which 
requires a great deal of attention to mini- 
mize transition problems and project 
disruptions. A key issue to be addressed is 
the type and content of documentation 
produced in Phases A and B. Since these 
early phases typically have limited funding 
and PD's manpower resources are limited, 
requirements and specifications resulting 
from Phase B may require substantial 
refinement and rework by S&E at the 
beginning of Phase C. It is important that 
Phase C planning and schedules account for 
this activity. 



PHASE C (DESIGN) 

This phase requires Congressional budget 
approval for projects large enough to be 
separate line items in the NASA budget 
submission. Funding must be approved and 
available at the start of Phase C. Detailed 
design is accomplished and plans are refined 
for final development, fabrication, test and 
operations. 

The processes occurring during Phase C in- 
clude: 

• Refinement of work breakdown structure 

• Development of Systems Requirements 
Specification 

• Development of design and contract end 
item specifications 

• Development of interface requirements 
documents 

• Completion of preliminary and detail 

design 

• Development of preliminary interface 
control documents (ICDs) 

• Performance of detailed system analyses 

• Development of manufacturing, testing 
verification, integration, operations, sup- 
porting systems and facilities plans 

• Definition of a development plan 

• Refinement of schedules and cost esti- 
mates 

• Refinement of management and procure- 
ment plans. 

The outputs from Phase C, which become the 
inputs to Phase D, include: 

• Updated system requirements documen- 
tation 

• Updated detail design and CEI specifica- 
tions 

• Baseline. 



33 



READINGS IN SYSTEMS ENGINEERING 



It is typically at the beginning of Phase C, 
when industry is heavily involved in design 
and project funding is increased dramatical- 
ly, that many formal documentation require- 
ments are contractually imposed. This can 
contribute to large cost increases over 
previous estimates in Phases A and B, and 
dictates the need for early inputs from the 
S&E engineering organization to assure that 
design and performance requirement specifi- 
cations and data requirements are incorpo- 
rated into initial cost estimates. 

Phase D (Development/Operations) 

During this phase of a project, flight hard- 
ware and software are developed, manufac- 
tured/coded, tested and qualified for flight. 
In addition, support is provided for the 
follow-on flight operations. 

The processes occurring during Phase D in- 
clude: 

• Development and test of prototype and 
protoflight hardware 

• Verification/Validation - qualification of 
hardware and software for flight 

• Manufacture and integration of flight 
hardware 

• Checkout of flight systems 

• Launch operations 

• Flight operations 



• Retrieval or disposal of payload and orbit- 
al debris. 

The outputs from Phase D include: 

• A successful mission, 

• Documentation and evaluation of the re- 
sults and anomalies 

• Documentation of lessons learned. 

In the early days of spaceflight, MSFC 
provided expendable propulsion systems, so 
most project activity terminated when 
launch operations were complete. As the 
mission of MSFC evolved into payloads and 
experiments, its role in the area of mission 
operations and maintenance greatly expand- 
ed and now provides an important function 
in present projects such as Spacelab, the Na- 
tional Space Transportation System, Hubble 
Space Telescope, the Advanced X-Ray Astro- 
physics Facility, and Space Station Freedom. 
These programs involve 15 to 30 years of 
technology insertion, operations and main- 
tenance activities that would justify a sepa- 
rate independent phase in their life cycles. 

At MSFC, the design phase is normally 
combined with the development and oper- 
ations phase to form a Phase C/D. The result- 
ing contract takes the Phase B data, refines 
it into a final design, develops and fabricates 
the hardware, tests and flight qualifies it, 
and supports the flight and mission 
operations. 



34 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



Management Issues in Systems Engineering ^-^ B 7^ - 

by Robert Shishko and Robert G. Chamberlain /? ./^ 

with contributions by ( ' 7 

Robert Aster, Vincent Bilardo, Kevin Forsberg, Hal Mooz, Lou Polaski and Ron Wade 



When applied to a system, the doctrine of 
successive refinement is a divide-and- 
conquer strategy. Complex systems are suc- 
cessively divided into pieces that are less 
complex, until they are simple enough to be 
conquered. This decomposition results in 
several structures for describing the product 
system and the producing system ("the 
system that produces the system"). These 
structures play important roles in systems 
engineering and project management. Many 
of the remaining sections in this chapter are 
devoted to describing some of these key 
structures. 

Structures that describe the product sys- 
tem include, but are not limited to, the re- 
quirements tree, system architecture and 
certain symbolic information such as system 
drawings, schematics, and data bases. The 
structures that describe the producing sys- 
tem include the project's work breakdown, 
schedules, cost accounts and organization. 
These structures provide different perspec- 
tives on their common raison d'etre: the 
desired product system. Creating a funda- 
mental harmony among these structures is 
essential for successful systems engineering 
and project management; this harmony 
needs to be established in some cases by one- 
to-one correspondence between two struc- 
tures, and in other cases, by traceable links 
across several structures. It is useful, at this 
point, to give some illustrations of this key 
principle. 

System requirements serve two purposes 
in the systems engineering process. First, 
they represent a hierarchical description of 
the buyer's desired product system as under- 
stood by the systems engineer. The interac- 
tion between the buyer and systems engineer 
to develop these requirements is one way the 



"voice of the buyer" is heard. Determining 
the right requirements — that is, only those 
that the informed buyer is willing to pay for 
— is an important part of the systems engi- 
neer's job. Second, system requirements also 
communicate to the design engineers what to 
design and build (or code). As these require- 
ments are allocated, they become inexorably 
linked to the system architecture and prod- 
uct breakdown, which consists of the hierar- 
chy of project, systems, segments, elements, 
subsystems, etc. 

The work breakdown structure (WBS) is 
also a hierarchical structure that contains 
the pieces of work necessary to complete the 
project. Each task in the WBS should be 
traceable to one or more of the system re- 
quirements. Schedules, which are structured 
as networks, describe the time-phased activi- 
ties that result in the product system in the 
WBS The cost account structure needs to be 
directly linked to the work in WBS and the 
schedules by which that work is done. 

The project's organizational structure 
describes clusters of personnel assigned to 
perform the work. These organizational 
structures are usually trees. Sometimes they 
are represented as a matrix of two interlaced 
trees; one for line responsibilities, the other 
for project responsibilities. In any case, the 
structure should allow identification of re- 
sponsibility for each WBS task. 

Project documentation is the product of 
particular WBS tasks. There are two funda- 
mental categories of project documentation: 
baselines and archives. Each category con- 
tains information about both the product 
system and the producing system. The base- 
line, once established, contains information 
describing the current state of the product 
system and producing system resulting from 



35 



READINGS IN SYSTEMS ENGINEERING 



all decisions that have been made. It is usu- 
ally organized as a collection of hierarchical 
tree structures, and should exhibit a signifi- 
cant amount of cross-linking. The archives 
should contain all of the rest of the project's 
information that is worth keeping, even if 
only temporarily. The archives should con- 
tain all assumptions, data and supporting 
analyses that are relevant to past, present 
and future decisions. Inevitably, the struc- 
ture (and control) of the archives is much 
looser than that of the baseline, though cross 
references should be maintained where feasi- 
ble. 

The structure of reviews (and their asso- 
ciated control gates) reflect the time-phased 
activities associated with the realization of 
the product system from its product break- 
down. The status reporting and assessment 
structure provides information on the 
progress of those same activities. On the fi- 
nancial side, the status reporting and assess- 
ment structure should be directly linked to 
the WBS, schedules and cost accounts. On 
the technical side, it should be linked to the 
product breakdown and/or the requirements 
tree. 

Managing the Systems Engineering 
Process: the Systems 
Engineering Management Plan 

Systems engineering management is a tech- 
nical function and discipline that ensures 
that systems engineering and all other tech- 
nical functions are properly applied. 

Each project should be managed in accor- 
dance with a project cycle that is carefully 
tailored to the project's risks. While the pro- 
ject manager concentrates on managing the 
overall project cycle, the project-level or lead 
systems engineer concentrates on managing 
its technical aspect. This requires that the 
systems engineer perform (or cause to be per- 
formed) the necessary multiple layers of 
decomposition, definition, integration, ver- 
ification and validation of the system, while 
orchestrating and incorporating the appro- 



priate concurrent engineering. Each one of 
these systems engineering functions re- 
quires application of technical analysis skills 
and tools to achieve the optimum system 
solution. 

The techniques used in systems engineer- 
ing management include baseline manage- 
ment, requirements traceability, change 
control, design reviews, audits, document 
control, failure review boards, control gates 
and performance certification. 

The Project Plan defines how the overall 
project will be managed to achieve the pre- 
established requirements within defined pro- 
grammatic constraints. The Systems Engi- 
neering Management Plan (SEMP) is the 
subordinate document that defines to all 
project participants how the project will be 
technically managed within the constraints 
established by the Project Plan. The SEMP 
communicates to all participants how they 
must respond to pre-established manage- 
ment practices. For instance, the SEMP 
should describe the means for both internal 
and external (to the project) interface con- 
trol. 

Role of the SEMP 

The SEMP is the rule book that describes to 
all participants how the project will be tech- 
nically managed. The responsible NASA 
Center should have a SEMP to describe how 
it will conduct its technical management, 
and each contractor should have a SEMP to 
describe how it will manage in accordance 
with both its contract and NASA's technical 
management practices. Since the SEMP is 
project- and contract-unique, it must be up- 
dated for each significant programmatic 
change or it will become outmoded and un- 
used, and the project could slide into an un- 
controlled state. The NASA Center should 
have its SEMP developed before attempting 
to prepare a "should-cost" estimate, since ac- 
tivities that incur cost, such as technical risk 
reduction, need to be identified and described 
first. The contractor should have its SEMP 



36 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



developed during the proposal process (prior 
to costing and pricing) because the SEMP de- 
scribes the technical content of the project, 
the potentially costly risk management ac- 
tivities, and the verification and validation 
techniques to be used, all of which must be 
included in the preparation of project cost 
estimates. 

The project SEMP is the senior technical 
management document for the project; all 
other technical control documents, such as 
the Interface Control Plan, Change Control 
Plan, Make-or-Buy Control Plan, Design 
Review Plan, Technical Audit Plan, etc., de- 
pend on the SEMP and must comply with it. 
The SEMP should be comprehensive and 
describe how a fully integrated engineering 
effort will be managed and conducted. 

Contents of the SEMP 

Since the SEMP describes the project's tech- 
nical management approach, which is driven 
by the type of project, the phase in the project 
cycle, and the technical development risks, it 
must be specifically written for each project 
to address these situations and issues. While 
the specific content of the SEMP is tailored 
to the project, the recommended content is 
listed below. 

Part I — Technical Program Planning 
and Control. This section should identify 
organizational responsibilities and authority 
for systems engineering management, in- 
clude control of contracted engineering; lev- 
els of control established for performance 
and design requirements, and the control 
method used; technical progress assurance 
methods; plans and schedules for design and 
technical program reviews; and control of 
documentation. 

This section should describe: 

• The role of the project office 

• The role of the user 

• The role of the Contracting Office Techni- 
cal Representative (COTR) 



The role of systems engineering 

The role of design engineering 

The role of specialty engineering 

Applicable standards 

Applicable procedures and training 

Baseline control process 

Change control process 

Interface control process 

Control of contracted (or subcontracted) 

engineering 

Data control process 

Make-or-buy control process 

Parts, materials and process control 

Quality control 

Safety control 

Contamination control 

EMI/EMC 

Technical performance measurement 

Control gates 

Internal technical reviews 

Integration control 

Verification control 

Validation control. 



Part II — Systems Engineering Process. 

This section should contain a detailed de- 
scription of the process to be used, including 
the specific tailoring of the process to the re- 
quirements of the system and project; the 
procedures to be used in implementing the 
process; in-house documentation; the trade 
study methodology; the types of mathemat- 
ical and/or simulation models to be used for 
system cost-effectiveness evaluations; and 
the generation of specifications. 
This section should describe the: 



System decomposition process 
System decomposition format 
System definition process 
System analysis and design process 
Trade study process 
System integration process 
System verification process 
System qualification process 
System acceptance process 
System validation process 
Risk management process 



37 



READINGS IN SYSTEMS ENGINEERING 



• Life-cycle cost management process 

• Use of mathematical models 

• Use of simulations 

• Specification and drawing structure 

• Baseline management process 

• Baseline communication process 

• Change control process 

• Tools to be used. 

Part III — Engineering Specialty Inte- 
gration. This section of the SEMP should de- 
scribe the integration and coordination of the 
efforts of the specialty engineering disci- 
plines into the systems engineering process 
during each iteration of that process. Where 
there is potential for overlap of specialty ef- 
forts, the SEMP should define the relative 
responsibilities and authorities of each. 

This section should contain the project's 
approach to: 



Concurrent engineering 
The activity phasing of specialty disci- 
plines 

The participation of specialty disciplines 
The involvement of specialty disciplines 
The role and responsibility of specialty 
disciplines 

The participation of specialty disciplines 
in system decomposition and definition 
The role of specialty disciplines in verifi- 
cation and validation 
Reliability 
Producibility 
Human engineering 
Maintainability 
Safety 

Survivability/vulnerability 
Integrated logistics 
Quality assurance. 



Development of the SEMP 

The SEMP must be developed concurrently 
with the Project Plan. In developing the- 
SEMP, the technical approach to the project, 
and hence the technical aspect of the project 
cycle, are developed. This becomes the keel of 



the project that ultimately determines the 
length and cost of the project. The develop- 
ment of the programmatic and technical 
management approaches of the project re- 
quires that the key project personnel develop 
an understanding of the work to be per- 
formed and the relationships among the var- 
ious parts of that work. (See sections on work 
breakdown structures and network sched- 
ules.) 



SEMP Lessons Learned from DoD Experience 

• A well-managed project requires a 
coordinated SEMP that is used through 
the project cycle. 

• A SEMP is a living document that must be 
updated as the project changes and kept 
consistent with the Project Plan. 

• A meaningful SEMP must be the product 
of experts from all areas of the project. 

• Projects with little or insufficient systems 
engineering discipline generally have 
major problems. 

• Weak systems engineering, or systems 
engineering placed too low in the 
organization, cannot perform the functions 
as required. 

• The systems engineering effort must be 
skillfully managed and well 
communicated to all the individuals 

• The systems engineering effort must be 
responsive to both the customer and the 
contractor interests. 



The SEMP's development requires contri- 
butions from knowledgeable programmatic 
and technical experts from all areas of the 
project that can significantly influence the 
project's outcome. The involvement of recog- 
nized experts is needed to establish a SEMP 
that is credible to the project manager and to 
secure the full commitment of the project 
team. 

Managing the Systems Engineering 
Process: Summary 

Systems engineering organizations, and spe- 
cifically project-level systems engineers, are 



38 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



responsible for managing projects through 
the technical aspect of the project cycle. This 
responsibility includes managing the decom- 
position and definition sequence, managing 
the integration, verification and validation 
sequence and controlling the technical 
baselines of the project. Typically, these 
baselines are the functional, "design-to," 
"build-to" (or "code-to"), "as-built" (or "as- 
coded"), and "as-deployed." Systems engi- 
neering must ensure efficient and logical 
progression through these baselines. 

Systems engineering is responsible for 
system decomposition and design until the 
design -to specifications of all lower level con- 
figuration items have been produced. Design 
engineering is then responsible for develop- 
ing the build-to and code-to documentation 
that complies with the approved design -to 
baseline. Systems engineering audits the 
design and coding process and the design en- 
gineering solutions for compliance to all 
higher level baselines. In performing this 
responsibility, systems engineering must 
ensure requirements traceability and docu- 
ment the results in a requirements traceabil- 
ity/verification matrix. 

Systems engineering is also responsible 
for the overall management of the integra- 
tion, verification and validation process. In 
this role, systems engineering conducts Test 
Readiness Reviews and ensures that only 
verified configuration items are integrated 
into the next higher assembly for further 
verification. Verification is continued to the 
system level, after which system validation 
is conducted to prove compliance with user 
requirements. 

Systems engineering also ensures that 
concurrent engineering is properly applied 
through the project cycle by involving the 
required specialty engineering. The SEMP is 
the guiding document for these activities. 

The Work breakdown Structure 

A WBS is a hierarchical breakdown of the 
work necessary to complete a project. The 



WBS should be a product-based, hierarchical 
division of deliverable items and associated 
services. As such, it should contain the pro- 
ject's product breakdown structure (PBS), 
with the specified prime product(s) at the 
top, and the systems, segments, subsystems, 
etc. at successive lower levels. At the lowest 
level are products such as hardware items, 
software items and information items (e.g., 
documents, databases, etc.) for which there 
is a cognizant engineer or manager. Branch 
points in the hierarchy should show how the 
PBS elements are to be integrated. The WBS 
is built from the PBS by adding, at each 
branch point of the PBS, any necessary ser- 
vice elements such as management, systems 
engineering, integration and verification 
(I&V), and integrated logistics support (ILS). 
If several WBS elements require similar 
equipment or software, then a higher level 
WBS element might be defined to perform a 
block buy or a development activity (e.g., 
"System Support Equipment"). Figure 1 
shows the relationship between a system, a 
PBS and a WBS. 

A project WBS should be carried down to 
the cost account level appropriate to the 
risks to be managed. The appropriate level of 
detail for a cost account is determined by 
management's desire to have visibility into 
costs, balanced against the cost of planning 
and reporting. Contractors may have a Con- 
tract WBS (CWBS), which is appropriate to 
the contractor's needs to control costs. A 
summary CWBS, consisting of the upper lev- 
els of the full CWBS, is usually included in 
the project WBS to report costs to the con- 
tracting agency. 

WBS elements should be identified by ti- 
tle and by a numbering system that performs 
the following functions: 

• Identifies the level of the WBS element 

• Identifies the higher level element into 
which the WBS element will be integrat- 
ed 

• Shows the cost account number of the 
element. 



39 



READINGS IN SYSTEMS ENGINEERING 



Sub 

system 

A 



Sub- 
system 
A 



System Components (subsystems) 
held together by "glue" (integration) 



The whole does 
more than the 
sum of ita parts 



Subsystem 
A 


Sub 
system 

b 


Subsystem 
C 


Subsystem 
D 



System 



Product 

Breakdown 

Structure Shows 

the components 

from which the 

system was 

formed 



Sub- 
system 
B 



Sub- 
system 



1 



The individual system 
components 



System 



Work 

Breakdown 

Structure (WBS) 

All work 

components 

necessary to 

produce a 

complete system 



Sub- 
system 
B 



Sub- 
system 
C 



Work to produce the 

individual system 

components 



mi 



Manage- Syetenu {&y 
ment Engin- 
eering 



Work to integrate the 

components into a 

system 



The whole takes 

more work than the 

sum of its parts 



Figure 1 The Relationship between a System, 

a Product Breakdown Structure, and 

a Work Breakdown Structure 



A WBS should also have a companion WBS 
dictionary that contains each element's title, 
identification number, objective, description, 
and any dependencies (e.g., receivables) on 
other WBS elements. This dictionary pro- 
vides a structured project description that is 
valuable for orienting project members and 



other interested parties. It fully describes 
the products and/or services expected from 
each WBS element. 

This section provides some techniques for 
developing a WBS, and points out some mis- 
takes to avoid. 

Role of the WBS 

A product-based WBS is the organizing 
structure for: 

• Project and technical planning and sched- 
uling 

• Cost estimation and budget formulation 
(In particular, costs collected in a 
product-based WBS can be compared to 
historical data. This is identified as a 
primary objective by DoD standards for 
WBSs.) 

• Defining the scope of statements of work 
and specifications for contract efforts 

• Project status reporting, including sched- 
ule, cost and work force, technical perfor- 
mance, integrated cost/schedule data 
(such as earned value and estimated cost 
at completion) 

• Plans, such as the SEMP, and other docu- 
mentation products, such as specifica- 
tions and drawings. 

It provides a logical outline and vocabulary 
that describes the entire project and inte- 
grates information in a consistent way. If 
there is a schedule slip in one element of a 
WBS, an observer can determine which other 
WBS elements are most likely to be affected. 
Cost impacts are more accurately estimated. 
If there is a design change in one element of 
the WBS, an observer can determine which 
other WBS elements will most likely be af- 
fected, and these elements can be consulted 
for potential adverse impacts. 

Techniques for Developing the WBS 

Developing a successful project WBS is likely 
to require several iterations through the 
project cycle since it is not always obvious at 



40 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



the outset what the full extent of the work 
may be. Prior to developing a preliminary 
WBS, there should be some development of 
the system architecture to the point where a 
preliminary PBS can be created. 

The PBS and associated WBS can then be 
developed level by level from the top down. 
In this approach, a project-level systems en- 
gineer finalizes the PBS at the project level, 
and provides a draft PBS for the next lower 
level. The WBS is then derived by adding ap- 
propriate services such as management and 
systems engineering to that lower level. This 
recursive process is repeated until a WBS ex- 
ists down to the desired cost account level. 

An alternative approach is to define all 
levels of a complete PBS in one design activ- 
ity, and then develop the complete WBS. 
When this approach is taken, it is necessary 
to take great care to develop the PBS so that 
all products are included, and all assembly/ 
integration and verification branches are 
correct. The involvement of people who will 
be responsible for the lower level WBS ele- 
ments is recommended. 

A WBS for a Multiple Delivery Project. 

Some of the terms for projects that provide 
multiple deliveries, are "rapid develop- 
ment," "rapid prototyping" and "incremental 
delivery." Such projects should also have a 
product-based WBS, but there will be one ex- 
tra level in the WBS hierarchy immediately 
under the final prime product(s) that identi- 
fies each delivery. At any point in time there 
will be both active and inactive elements in 
the WBS. 

A WBS for an Operational Facility. A 

WBS for managing an operational facility 
such as a flight operations center is analo- 
gous to a WBS for developing a system. The 
difference is that the products in the PBS are 
not necessarily completed once and then 
integrated, but are all produced on a routine 
basis. A PBS for an operational facility 
might consist of information products or 



service products provided to external cus- 
tomers. However, the general concept of a 
hierarchical breakdown of products and/or 
services would still apply. 

The rules that apply to a development 
WBS also apply to a WBS for an operational 
facility. The techniques for developing a 
WBS for an operational facility are the same, 
except that services such as maintenance 
and user support are added to the PBS, and 
services such as systems engineering, inte- 
gration and verification may not be needed. 

Common Errors in Developing a WBS 

There are three common errors found in 
WBSs: 

Error 1: The WBS describes functions, 
not products. This makes the project man- 
ager the only one formally responsible for 
products. 

Error 2: The WBS has branch points that 
are not consistent with how the WBS ele- 
ments will be integrated. For instance, in a 
flight operations system with a distributed 
architecture, there is typically software asso- 
ciated with hardware items that will be inte- 
grated and verified at lower levels of a WBS. 
It would then be inappropriate to separate 
hardware and software as if they were sepa- 
rate systems to be integrated at the system 
level. This would make it difficult to assign 
accountability for integration and to identify 
the costs of integrating and testing compo- 
nents of a system. 

Error 3: The WBS is inconsistent with 
the PBS. This makes it possible that the PBS 
will not be fully implemented, and generally 
complicates the management process. 

Some examples of these errors are shown 
in Figure 2. Each one prevents the WBS from 
successfully performing its roles in project 
planning and organizing. These errors are 
avoided by using the WBS development tech- 
niques described above. 



41 



READINGS IN SYSTEMS ENGINEERING 



Error 1 



Functions without Products 

This WBS describes only 
functions, not the products 






Project 



Management 



i 






^-5 : 






Engineering 



Fabrication 






Verification j 







Inappropriate Branches 

This WBS has branch points that are 

not consistent with the way the WBS 

elements will be integrated 






> -Y" '•flftfttfi tfn. 



Software 



Distributed 

Information 

System 



IJ I JJ II J IIII L^ I JJ^ I J 



Hardware 




B 



Subsystem 



,. , ,„^„^^v,, f itnliitMffli!- in hi 



■■ S* * r " f-tf ■^"O -" 




Inconsistency with PBS 

This WBS is inconsistent with the 
Product Breakdown Structure 



TWT Amplifier 




I TWT Amplifier f 



The Work Breakdown Structure The Product Breakdown Structure 

Figure 2 Examples of WBS Development Errors 



Network Scheduling 

Products described in the WBS are the result 
of activities that take time to complete. An 
orderly and efficient systems engineering 
process requires that these activities take 
place in a way that respects the underlying 
time-precedence relationships among them. 
This is accomplished by creating a network 
schedule, which explicitly takes into account 
the dependencies of each activity on other ac- 
tivities and receivables from outside sources. 
This section discusses the role of scheduling 
and the techniques for building a complete 
network schedule. 

Scheduling is an essential component of 
planning and managing the activities of a 
project. The process of creating a network 
schedule can lead to a much better under- 
standing of what needs to be done, how long 



it will take, and how each element of the pro- 
ject WBS might affect other elements. A 
complete network schedule can be used to 
calculate how long it will take to complete a 
project, which activities determine that du- 
ration (i.e., critical path activities), and how 
much spare time (i.e., float) exists for all the 
other activities of the project. An under- 
standing of the project's schedule is a 
prerequisite for accurate project budgeting. 

Keeping track of schedule progress is an 
essential part of controlling the project, be- 
cause cost and technical problems often show 
up first as schedule problems. Because net- 
work schedules show how each activity af- 
fects other activities, they are essential for 
predicting the consequences of schedule slips 
or accelerations of an activity on the entire 
project. Network scheduling systems also 
help managers accurately assess the impact 



42 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



Critical Path and Float Calculation 

The critical path is the sequence of activities 
that will take the longest to accomplish. Activi- 
ties that are not on the critical path have a cer- 
tain amount of time that they can be delayed un- 
til they, too are on a critical path. This time is 
called float. There are two types of float, path 
float and free float. Path float is where a se- 
quence of activities collectively have float. If 
there is a delay in an activity in this sequence, 
then the path float for all subsequent activities 
is reduced by that amount. Free float exists 
when a delay in an activity will have no effect on 
any other activity. For example, if activity A can 
be finished in 2 days, and activity B requires 5 
days, and activity C requires completion of both 
A and B, then A would have 3 days of free float. 

Float is valuable. Path float should be con- 
served where possible, so that a reserve exists 
for future activities. Conservation is much less 
important for free float. 

To determine the critical path, there is first 
a "forward pass" where the earliest start time of 
each activity is calculated. The time when the 
last activity can be completed becomes the end 
point for that schedule. Then there is a "back- 
ward pass," where the latest possible start point 
of each activity is calculated, assuming that the 
last activity ends at the end point previously cal- 
culated. Float is the time difference between the 
earliest start time and the latest start time of an 
activity. Whenever this is zero, that activity is 
on a critical path. 



of both technical and resource changes on the 
cost and schedule of a project. 

Network Schedule Data and Graphical 
Formats 

Network schedule data consist of: 

• Activities 

• Dependencies between activities (e.g., 
where an activity depends upon another 
activity for a receivable) 

• Products or milestones that occur as a re- 
sult of one or more activities 

• Duration of each activity. 



A work flow diagram (WFD) is a graphi- 
cal display of the first three data items 
above. A network schedule contains all four 
data items. When creating a network sched- 
ule, graphical formats of these data are very 
useful. Two general types of graphical for- 
mats, shown in Figure 3, are used. One has 
activities-on-arrows, with products and de- 
pendencies at the beginning and end of the 
arrow. This is the typical format of the Pro- 
gram Evaluation and Review Technique 
(PERT) chart. The second called precedence 
diagrams, has boxes that represent activi- 
ties; dependencies are then shown by arrows. 
Due to its simpler visual format and reduced 
requirements on computer resources, the 
precedence diagram has become more com- 
mon in recent years. 



Activity-on-Arrow Diagram 
A," 




Activity A has 
been "artificially" 
broken into two 
separate activities. 



Activity Description 



Activity Duration 
(e.g., days) 



Precedence Diagram 



Activity Description 



Activity Duration 
(e.g., days) 



SS5 



This means that Activity B 
can start 5 days after 
Activity A starts. 



Note: 

Each activity's 

description 

should contain 

an action and 

the object of 

that action. 



Figure 3 Activity-on-Arrow and Precedence 
Diagrams for Network Schedules 

The precedence diagram format allows 
for simple depiction of the following logical 
relationships: 

• Activity B begins when Activity A begins 
(Start-Start, or SS) 

• Activity B begins only after Activity A 
ends (Finish-Start, or FS) 



43 



Readings in systems engineering 



• Activity B ends when Activity A ends 
(Finish-Finish, or FF). 

Each of these three activity relationships 
may be modified by attaching a lag ( + or - ) 
to the relationship, as shown in Figure 3. 

It is possible to summarize a number of 
low-level activities in a precedence diagram 
with a single activity. This is commonly 
referred to as hammocking. One takes the 
initial low-level activity and attaches a 
summary activity to it using the first re- 
lationship described above. The summary 
activity is then attached to the final low- 
level activity using the third relationship 
described above. Unless one is hammocking, 
the most common relationship used in prece- 
dence diagrams is the second one mentioned 
above. The activity-on-arrow format can 
represent the identical time-precedence logic 
as a precedence diagram by creating artifi- 
cial events and activities as needed. 

Establishing a Network Schedule 

Scheduling begins with project-level sched- 
ule objectives for delivering the products de- 
scribed in the upper levels of the WBS. To 
develop network schedules that are consis- 
tent with the project's objectives, the follow- 
ing six steps are applied to each cost account 
at the lowest available level of the WBS. 

Step 1: Identify activities and dependen- 
cies needed to complete each WBS element. 
Enough activities should be identified to 
show exact schedule dependencies between 
activities and other WBS elements. It is not 
uncommon to have about 100 activities iden- 
tified for the first year of a WBS element 
that will require 10 work-years per year. 
Typically, there is more schedule detail for 
the current year, and much less detail for 
subsequent years. Each year, schedules are 
updated with additional detail for the cur- 
rent year. This first step is most easily ac- 
complished by: 



• Ensuring that the cost account WBS is 
extended downward to describe all sig- 
nificant products, including documents, 
reports, hardware and software items. 

• For each product, listing the steps re- 
quired for its generation and drawing the 
process as a work flow diagram. 

• Indicating the dependencies among the 
products, and any integration and verifi- 
cation steps within the work package. 

Step 2: Identify and negotiate external 
dependencies. External dependencies are 
any receivables from outside of the cost ac- 
count, and any deliverables that go outside 
of the cost account. Informal negotiations 
should occur to ensure that there is agree- 
ment with respect to the content, format and 
labeling of products that move across cost 
account boundaries. This step is designed to 
ensure that lower level schedules can be 
integrated. 

Step 3: Estimate durations of all activi- 
ties. Assumptions behind these estimates 
(work force, availability of facilities, etc.) 
should be written down for future reference. 

Step 4: Enter the schedule data for the 
WBS element into a suitable computer pro- 
gram to obtain a network schedule and an 
estimate of the critical path for that element. 
(There are many commercially available 
software packages for this function.) This 
step enables the cognizant engineer, team 
leader, and/or systems engineer to review 
the schedule logic. It is not unusual at this 
point for some iteration of steps one to four to 
be required in order to obtain a satisfactory 
schedule. Reserve will also be added to criti- 
cal path activities, often in the form of a 
dummy activity, to ensure that schedule 
commitments can be met for this WBS ele- 
ment. 

Step 5: Integrate schedules of lower level 
WBS elements, using suitable software, so 
that all dependencies between WBS ele- 
ments are correctly included in a project 



44 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



network. It is important to include the im- 
pacts of holidays, weekends, etc., at this 
point. The critical path for the project is dis- 
covered at this step in the process. 

Step 6: Review the work force level and 
funding profile over time, and make final ad- 
justments to logic and durations so that work 
force levels and funding levels are reason- 
able. Adjustments to the logic and the dura- 
tions of activities may be needed to conform 
to the schedule targets established at the 
project-level. This may include adding more 
activities to some WBS element, deleting re- 
dundant activities, increasing the work force 
for some activities that are on the critical 
path, or finding ways to do more activities in 
parallel, rather than in series. If necessary, 
the project-level targets may need to be ad- 
justed, or the scope of the project may need to 
be reviewed. Again, it is good practice to 
have some schedule reserve, or float, as part 
of a risk mitigation strategy. 

The product of these last steps is a feasi- 
ble baseline schedule for each WBS element 
that is consistent with the activities of all 
other WBS elements, and the sum of all 
these schedules is consistent with both the 
technical scope and the schedule goals for the 
project. There should be enough float in this 
integrated master schedule so that schedule 
and associated cost risk are acceptable to the 
project and to the project's customer. Even 
when this is done, time estimates for many 
WBS elements will have been underestimat- 
ed, or work on some WBS elements will not 
start as early as had been originally as- 
sumed due to late arrival of receivables. Con- 
sequently, replanning is almost always 
needed to meet the project's goals. 

Reporting Techniques 

Summary data about a schedule is usually 
described in Gantt charts, a good example of 
which is shown in Figure 4. Another type of 
output format is a table that shows the float 
and recent changes in float of key activities. 
For example, a project manager may wish to 



Desirable Features in Gantt Charts 

The Gantt chart shown in Figure 4 illustrates 
the following desirable features: 

• A heading that describes the WBS element, 
the responsible manager, the date of the 
baseline used, and the date that status was 
reported. 

• A milestone section in the main body (lines 1 
and 2). 

• An activity section in the main body. 
Activity data: 

a. WBS elements (lines 3, 5, 8, 12, 16 and 
20) 

b. Activities (indented from WBS elements) 

c. C urrent plan (shown as thick bars) 

d. Baseline plan (same as current plan, or if 
different, represented by thin bars under 
the thick bars) 

e. Status line at the appropriate date 

f. Slack for each activity (dashed lines 
above the current plan bars) 

g. Schedule slips from the baseline (dashed 
lines below the milestone on line 12) 

• A note section, where the symbols in the 
main body can be explained. 

This Gantt chart shows only 23 lines, which is a 
summary of the activities currently being 
worked for this WBS element. It is appropriate 
to tailor the amount of detail to those items most 
pertinent at the time of status reporting. 



know precisely how much schedule reserve 
has been consumed by critical path activi- 
ties, and whether reserves are being 
consumed or are being preserved in the 
latest reporting period. This table provides 
information on the rate of change of schedule 
reserve. 

Good scheduling systems provide 
capabilities to show resource requirements 
over time, and to make adjustments so that 
the schedule is feasible with respect to 
resource constraints over time. Resources 
may include work force level, funding 
profiles, important facilities, etc. Figure 5 
shows an example of an unleveled resource 
profile. The objective is to move the start 
dates of tasks that have float to points where 



45 



READINGS IN SYSTEMS ENGINEERING 



Space Science & Instruments 
Approval 



Achievement 



Level 3 Manager 



Level 4 Manager 



System (Level 2) 

Subsystem (Level 3) 

Assembly (Level 4) 




STIKSCAT PROJECT 

Status as of: Jan 20, 1991 
Revision Date: Dec 23,1990 



ACTIVITY 



Milestones - Subsystem 
- Assembly 



Management 

Quarterly Assessments 




System Engineering 
Assembly Design 
Subassembly rqmt. . 



Subassembly #1 
Design 
Fabricate 
Test 



Subassembly #2 
Design 
Fabricate 
Test 



Subassembly #3 
Design 
Fabricate 
Test 



Integration & Test 
Plans 
Procedures 
Integrate & Test 



NOTES: 

FLOAT - Positive or Negative - is 

shown above the activity bars and 

event symbols. 
The BASELINE plan is shown below 

the current plan, if they differ. 



This assembly is for the PFM (WBS 49801) 
Assemblies for FM1 (WBS 49802) and 
FM2 (WBS 49803) are on Pg 2/2. 



Figure 4 An Example of aGantt Chart 



the resource profile is feasible. If that is 
not sufficient, then the assumed task dura- 
tions for resource-intensive activities should 
be re-examined and, accordingly, the re- 
source levels changed. 

Budgeting and Resource Planning 

Budgeting and resource planning involves 
the establishment of a reasonable project 
baseline budget and the capability to ana- 



lyze changes to that baseline resulting from 
technical and/or schedule changes. The proj- 
ect's WBS, baseline schedule and budget 
should be viewed by the systems engineer as 
mutually dependent, reflecting the technical 
content, time, and cost of meeting the proj- 
ect's goals and objectives. 

The budgeting process needs to take into 
account whether a fixed cost cap or cost 
profile exists. When no such cap or profile 
exists, a baseline budget is developed from 



46 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



Unita 


Note: Activities 
.resulting in 
/violations of 


\ 








15 

10 

5 




















































V 


- rescheduled. 


c 




























































































































































leaource Limit 
















































■:: 


& 


















£V 


, :V±': 1 ' 




h ** 


"W 
























:■:■:■ 




















































w 
































































>:;*:■:: 
























































xif ; : : 












- 


































i& 










■-ilr 




ir 














































:-: f : 










































#: 










ix*; : ■ 












































jS: 








MM 


:;vl>": 
























































;?i: : :: : : 















































Time 10 20 








JO 





Figure 5 An Example of an Unleveled Resource 
Profile 

the WBS and network schedule. This specifi- 
cally involves combining the project's work 
force and other resource needs with the 
appropriate work force rates and other finan- 
cial and programmatic factors to obtain cost 
element estimates. These elements of cost 
include: 

• Direct labor costs 

• Overhead costs 

• Other direct costs (travel, data process- 
ing, etc.) 

• Subcontract costs 

• Material costs 

• General and administrative costs 

• Cost of money (i.e., interest payments, 
if applicable) 

• Fee (if applicable) 

• Contingency 

When there is a cost cap or a fixed cost 
profile, there are additional logic gates that 
must be satisfied before the systems engi- 
neer can complete the budgeting and plan- 
ning process. A determination needs to be 
made whether the WBS and network sched- 
ule are feasible with respect to mandated 
cost caps and/or cost profiles. If not, the sys- 
tems engineer needs to recommend the best 
approaches for either stretching out a project 
(usually at an increase in the total cost) or 



descoping the project's goals and objectives, 
requirements, design, and/or implementa- 
tion approach. 

Whether a cost cap or fixed cost profile 
exists, it is important to control costs after 
they have been baselined. An important 
aspect of cost control is project cost and 
schedule status reporting and assessment. 
Another is cost and schedule risk planning, 
such as developing risk avoidance and work- 
around strategies. At the project level, 
budgeting and resource planning must also 
ensure that an adequate level of contingency 
funds are included to deal with unforeseen 
events. 



Assessing the Effect of Schedule Slippage 

Certain elements of cost, called fixed costs, are 
mainly time related, while others, called vari- 
able costs, are mainly product related. If a pro- 
ject's schedule is slipped, then the fixed costs of 
completing it increase. The variable costs re- 
main the same in total (excluding inflation 
adjustments), but are deferred downstream, as 
in the figure below. 




r NOW 



To quickly assess the effect of a simple schedule 
slippage: 

• Convert baseline budget plan from nominal 
(real-year) dollars to constant dollars 

• Divide baseline budget plan into fixed and 
variable costs 

• Enter schedule slip implementation 

• Compute new variable costs including any 
work force disruption costs 

• Repeat last two steps until an acceptable 
implementation is achieved 

• Compute new fixed costs 

• Sum new fixed and variable costs 

• Convert from constant dollars to nominal 
(real-years) dollars. 



47 



READINGS IN SYSTEMS ENGINEERING 



Risk Management 

Risk management comprises purposeful 
thought to the sources, magnitude and 
mitigation of risk, and actions directed to- 
ward its balanced reduction. As such, risk 
management is an integral part of project 
management, and contributes directly to the 
objectives of systems engineering. 



Risk 

The term risk has different meanings depending 
on the context. Sometimes it simply indicates the 
degree of variability in the outcome or result of a 
particular action. In the context of risk 
management during the systems engineering 
process, the term denotes a combination of both 
the likelihood of various outcomes and their 
distinct consequences. The focus, moreover, is 
generally on undesired or unfavorable outcomes 
such as the risk of a technical failure, or the risk 
of exceeding a cost target. 



NASA policy objectives with regard to 
project risks are expressed in NMI 8070. 4A, 
Risk Management Policy. These are to: 

• Provide a disciplined and documented ap- 
proach to risk management throughout 
the project cycle 

• Support management decision making by 
providing integrated risk assessments 
(i.e., taking into account cost, schedule, 
performance and safety concerns) 

• Communicate to NASA management the 
significance of assessed risk levels and 
the decisions made with respect to them. 



There are a number of actions the systems 
engineer can take to effect these objectives. 
Principal among them is planning and com- 
pleting a well-conceived risk management 
program. Such a program encompasses 
several related activities during the systems 
engineering process. The structure of these 
activities is shown in Figure 6. 

The first is the process of identifying and 
characterizing the project's risks. The objec- 
tive of this step is to understand what uncer- 
tainties the project faces, and which among 
them should be given greater attention. This 
is accomplished by categorizing (in a consis- 
tent manner) uncertainties by the likelihood 
of occurrence (e.g., high, medium, or low), 
and separately, according to severity of 
consequences. This categorization forms the 
basis for ranking uncertainties by their rela- 
tive riskiness. Uncertainties with both high 
likelihood and severely adverse conse- 
quences are ranked higher than those 
without these characteristics. The primary 
methods used in this process are qualitative; 
hence, in systems engineering literature, 
this step is sometimes called qualitative risk 
assessment. The output of this step is a list of 
significant risks (by phase) to be given 
specific management attention. 

In some projects, qualitative methods are 
adequate for making risk management 
decisions; in others, these methods are not 
precise enough to elucidate the magnitude of 
the problem, or to allocate scarce risk reduc- 
tion resources. Risk analysis is the process of 
quantifying both the likelihood of occurrence 
and consequences of potential future events 
(or "states of nature" in some texts). The 



Risk Identification 
and Characterization 



1 



Risk Management 



i 



Risk Analysis 



i 



Risk Mitigation 
and Tracking 



1 



Figure 6 Risk Management Structure 



48 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



systems engineer needs to decide whether 
risk identification and characterization are 
adequate, or whether the increased precision 
of risk analysis is needed for some uncertain- 
ties. In making that determination, the sys- 
tems engineer needs to balance the (usually) 
higher cost of risk analysis against the value 
of the additional information. 

Risk mitigation is the formulation, selec- 
tion and execution of strategies designed to 
economically reduce risk. Tracking the effec- 
tivity of these strategies is also considered 
part of risk mitigation. Risk mitigation is 
often a challenge because efforts and expen- 
ditures to reduce one type of risk may 
increase another type. (Some have called this 
the systems engineering equivalent of the 
Heisenberg Uncertainty Principle in quan- 
tum mechanics). The ability (or necessity) to 
trade one type of risk for another means that 
the project manager and the systems engi- 
neer need to understand the system-wide 
effects of various strategies in order to make 
a rational allocation of resources. 

Several techniques have been developed 
for each of these risk management activities. 
The principal ones are shown in Table 1. The 
systems engineer needs to choose the tech- 
niques that best fit the unique requirements 
of each project. 

A risk management program is needed 
throughout the project cycle. In keeping with 
the doctrine of successive refinement, its 
focus, however, moves from the "big picture" 
in the early phases of the project cycle 
(Phases A and B) to more specific issues dur- 
ing product design and development (Phases 
C and D). During pre -operations and oper- 
ations (Phases E and F), the focus changes 
again. A good risk management program is 
always forward-looking. In other words, a 
risk management program should address 
the project's ongoing risk issues and future 
uncertainties. As such, it is a natural part of 
concurrent engineering. 

Risk management activities for a project 
should be documented in a risk management 
program plan. That plan, which elaborates 



Risk 

Identification 
and 

Characteriza- 
tion 


Risk Analysis 


Risk 

Mitigation 

and Tracking 


Expert 
interviews 


Decision 
analysis 


Watchlists/ 
milestones 


Independent 
assessment 
(cost, schedule 
and technical) 


Probabilistic 
Risk 

Assessment 
(PRA) 


Contingency 
planning 


Risk templates 
(e.g.,DoD 

4245.7-M) 


Probabilistic 
network 
schedules (e.g., 
PERT) 


Critical 

items/issues 
lists 


Lessons 
learned files 
from previous 
projects 


Probabilistic 
cost and 
effectiveness 
models (e.g., 
Monte Carlo 
models) 


Cost/schedule 

control 

systems and 

Technical 

Performance 

Measure 

(TPM) 

tracking 


FMECAs/ 

FMEAs/ 

Digraphs 



Table 1 Techniques of Risk Management 

on the SEMP and should be updated at each 
phase of the project cycle, contains: 

• The project's overall risk policy and objec- 
tives 

• The programmatic aspects of the risk 
management activities (i.e., responsibil- 
ities, resources, schedules and miles- 
tones, etc.) 

• A description of the tools and techniques 
to be used for risk identification and 
characterization, risk analysis, and risk 
mitigation 

• A description of the role of risk manage- 
ment with respect to systems analysis, 
baseline change control, formal reviews, 
and status reporting and assessment 

• Documentation requirements for each 
risk management product and action. 

The level of risk management activities 
should be consistent with the project's 
overall risk policy established in conjunction 
with its NASA Headquarters program office. 
At present, formal guidelines for the 



49 



READINGS IN SYSTEMS ENGINEERING 



classification of projects with respect to over- 
all risk policy do not exist; such guidelines 
exist only for NASA payloads. These are pro- 
mulgated in NMI 8010.1 A, Classification of 
NASA Payloads, Attachment A. 

Types of Risks 

There are several ways to describe the var- 
ious types of risk a project manager/systems 
engineer faces. Traditionally, project manag- 
ers and systems engineers have attempted to 
divide risks into three or four broad categor- 
ies namely, cost, schedule, technical, and 
sometimes, safety (and/or hazard) risks. 
More recently, others have entered the lexi- 
con, including the categories of organization- 
al, management, acquisition, supportability, 
political and programmatic risks. These 
newer categories reflect the expanded set of 
concerns of project managers and systems 
engineers who must operate in the current 
NASA environment. Some of these newer 
categories also represent supersets of other 
categories. For example, the Defense Sys- 
tems Management College (DSMC) Systems 
Engineering Management Guide wraps 
"funding, schedule, contract relations, and 
political risks" into the broader category of 
programmatic risks. While these terms are 
useful in informal discussions, there appears 
to be no formal taxonomy free of ambiguities. 
One reason, mentioned above, is that often 
one type of risk can be exchanged for an- 
other. A second reason is that some of these 
categories move together, as for example, 
cost risk and political risk (e.g., the risk of 
project cancellation). 

Another way some have categorized risk 
is by the degree of mathematical pre- 
dictability in its underlying uncertainty. 
The distinction has been made between an 
uncertainty that has a known probability 
distribution, with known or estimated 
parameters, and one in which the underlying 
probability distribution is either not known, 
or its parameters cannot be objectively 
quantified. 



An example of the first kind of uncertain- 
ty occurs in the unpredictability of the 
spares upmass requirement for alternative 
Space Station Freedom designs. While the 
requirement is stochastic in any particular 
logistics cycle, the probability distribution 
can be estimated for each design from reli- 
ability theory and empirical data. Examples 
of the second kind of uncertainty occur in 
trying to predict whether a Shuttle accident 
will make resupply of Freedom impossible 
for a period of time greater than x months, or 
whether life on Mars exists. 

Modern subjectivist (also known as 
Bayesian) probability theory holds that the 
probability of an event is the degree of belief 
that a person has that it will occur, given 
his/her state of information. As that infor- 
mation improves (e.g., through the acquisi- 
tion of data or experience), the subjectivist's 
estimate of a probability should converge to 
that estimated as if the probability distribu- 
tion were known. In the examples of the 
previous paragraph, the only difference, 
then, is the probability estimator's perceived 
state of information. Consequently, subjec- 
tivists find the distinction between the two 
kinds of uncertainty of little or no practical 
significance. The implication of the subjec- 
tivist's view for risk management is that, 
even with little or no data, the systems 
engineer's subjective probability estimates 
form a valid basis for risk decision making. 

Risk Identification and 
Characterization Techniques 

A variety of techniques is available for risk 
identification and characterization. The 
thoroughness with which this step is accom- 
plished is an important determinant of the 
risk management program's success. 

Expert Interviews. When properly con- 
ducted, expert interviews can be a major 
source of insight and information on the pro- 
ject's risks in the expert's area of knowledge. 
One key to a successful interview is in 



50 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



identifying an expert who is close enough to 
a risk issue to understand it thoroughly, and 
at the same time, able (and willing) to step 
back and take an objective view of the prob- 
abilities and consequences. A second key to 
success is advanced preparation on the part 
of the interviewer. This means having a list 
of risk issues to be covered in the interview, 
developing a working knowledge of these 
issues as they apply to the project, and devel- 
oping methods for capturing the information 
acquired during the interview. 

Initial interviews may yield only qualita- 
tive information, which should be verified in 
follow-up rounds. Expert interviews are also 
used to solicit quantitative data and infor- 
mation for those risk issues that qualitative- 
ly rank high. These interviews are often the 
major source of inputs to risk analysis 
models built using the techniques described 
later. 

Independent Assessment. This technique 
can take several forms. In one form, it can be 
a review of project documentation, such as 
statements of work, acquisition plans, verifi- 
cation plans, manufacturing plans and the 
SEMP. In another form, it can be an evalua- 
tion of the WBS for completeness and consis- 
tency with the project's schedules. In a third 
form, an independent assessment can be an 
independent cost (and/or schedule) estimate 
from an outside agency and/or group. 

Risk Templates. This technique consists of 
examining and then applying a series of pre- 
viously developed risk templates to a current 
project. Each template generally covers a 
particular risk issue, and then describes 
methods for avoiding or reducing that risk. 
The most widely recognized series of tem- 
plates appears in DoD 4245. 7M, Transition 
from Development to Production . . . Solving 
the Risk Equation. Many of the risks and risk 
responses described are based on lessons 
learned from DoD programs, but are general 
enough to be useful to NASA projects. Asa 



general caution, risk templates cannot 
provide an exhaustive list of risk issues for 
every project, but they are a useful input to 
risk identification. 

Lessons Learned. A review of the lessons 
learned files, data and reports from previous 
similar projects can produce insights and in- 
formation for risk identification on a new 
project. For technical risk identification, as 
an example, it makes sense to examine pre- 
vious projects of similar function, architec- 
ture or technological approach. The lessons 
learned from the Infrared Astronomical Sat- 
ellite (IRAS) project might be useful to the 
Space Infrared Telescope Facility (SIRTF) 
project, even though the latter's degree of 
complexity is significantly greater. The key 
to applying this technique is in recognizing 
what aspects are analogous in two projects, 
and what data are relevant to the new 
project. Even if the the documented lessons 
learned from previous projects are not appli- 
cable at the system level, there may be 
valuable data applicable at the subsystem or 
component level. 

FMECAs, FMEAs and Digraphs. Failure 
Modes, Effects, and Criticality Analysis 
(FMECA), Failure Modes and Effects Analy- 
sis (FMEA) and digraphs are specialized 
techniques for safety (and/or hazard) risk 
identification and characterization. These 
techniques focus on the hardware compo- 
nents that make up the system. According to 
MIL-STD-1629A, FMECA is "an ongoing 
procedure by which each potential failure in 
a system is analyzed to determine the results 
or effects thereof on the system, and to classi- 
fy each potential failure mode according to 
its severity." Failures are generally classi- 
fied into four severity categories: 

• Category I - Catastrophic Failure (possi- 
ble death or system loss) 

• Category II - Critical Failure (possible 
major injury or system damage) 



51 



Readings in systems engineering 



• Category III - Major Failure (possible 
minor injury or mission effectiveness deg- 
radation) 

• Category IV - Minor Failure (requires 
system maintenance, but does not pose a 
hazard to personnel or mission effective- 
ness). 

A complete FMECA also includes an esti- 
mate of the probability of each potential fail- 
ure. These probabilities are usually based, at 
first, on subjective judgment or experience 
factors from similar kinds of hardware com- 
ponents, but may be refined from reliability 
data as the system development progresses. 
An FMEA is similar to an FMECA, but typi- 
cally excludes the severity classification 
category. 

Digraph analysis is an aid in determining 
fault tolerance, propagation and reliability 
in large, interconnected systems. Digraphs 
exhibit a network structure and resemble a 
schematic diagram. The digraph technique 
permits the integration of data from a num- 
ber of individual FMECAs/FMEAs, and can 
be translated into fault trees, described be- 
low, if quantitative probability estimates are 
needed. 

Risk Analysis Techniques 

The tools and techniques of risk analysis rely 
heavily on the concept and "laws" (actually, 
axioms and theorems) of probability. The 
systems engineer needs to be familiar with 
these in order to appreciate the full power 
and limitations of these techniques. The 
products of risk analyses are generally quan- 
titative probability and consequence esti- 
mates for various outcomes, more detailed 
understanding of the dominant risks, and 
improved capability for allocating risk re- 
duction resources. 

Decision Analysis. Decision analysis is one 
technique to help the individual decision 
maker deal with a complex set of uncertain- 
ties. Using the divide-and-conquer approach 



common to much of systems engineering, a 
complex uncertainty is decomposed into sim- 
pler ones, which are then treated separately. 
The decomposition continues until it reaches 
a level at which either hard information can 
be brought to bear, or intuition can function 
effectively. The decomposition can be graphi- 
cally represented as a decision tree. The 
branch points, called nodes, in a decision tree 
represent either decision points or chance 
events. Endpoints of the tree are the poten- 
tial outcomes. 

In most applications of decision analysis, 
these outcomes are generally assigned dollar 
values. From the probabilities assigned at 
each chance node, and the dollar value of 
each outcome, the distribution of dollar val- 
ues (i.e., consequences) can be derived for 
each set of decisions. Even large, complex de- 
cision trees can be represented in currently 
available decision analysis software. This 
software can also calculate a variety of risk 
measures. 

In brief, decision analysis is a technique 
that allows: 

• A systematic enumeration of uncertain- 
ties and encoding of their probabilities 
and outcomes 

• An explicit characterization of the deci- 
sion maker's attitude toward risk, ex- 
pressed in terms of his/her risk aversion 

• A calculation of the value of "perfect 
information," thus setting a normative 
upper bound on information-gathering 
expenditures 

• Sensitivity testing on probability esti- 
mates and outcome dollar values. 

Probabilistic Risk Assessment (PRA). A 

PRA seeks to measure the risk inherent in a 
system's design and operation by quantify- 
ing both the likelihood of various possible 
accident sequences and their consequences. 
A typical PRA application is to determine 
the risk associated with a specific nuclear 
power plant. Within NASA, PRAs are used 
to demonstrate, for example, the relative 



52 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



An Example of a Decision Tree for Robotic Precursor Missions to Mars 

In 1990, the Lunar/Mars Exploration Program Office (LMEPO) at JSC wanted to know how robotic precur- 
sor missions might reduce the risk of a manned Mars mission. Structuring the problem as a decision tree al- 
lows the effects of different missions and chance events to be systematically and quantitatively evaluated. 
The portion of the decision tree shown here illustrates the calculation of the probabilities for three distinct 
outcomes: (A) a successful Mars landing, (B) a safe return without a landing, or (C) a disaster resulting in 
mission and crew loss, when no atmospheric or site reconnaissance robotic precursor missions were made 
and aerocapture at Mars was selected. As new information becomes available, the decision tree's data can be 
reviewed and updated. 



Probability of Each Outcome 



/a±^ = .8635^ 

Z£v = 0600 >-= 1.000 
AZ± = .0765 J 




No Atmospheric 
Mission 



Decision Node 



Chance Node 



Z\ 



Outcome 



0.00 Probability 



Making the same calculations for every branch in the decision tree allows a determination of the best mix of 
robotic precursor missions as an explicit function of: (a) the contribution of each robotic precursor mission to 
manned mission risk reduction; (b) the cost, schedule and riskiness of each robotic mission; (c) the value of 
the manned mission; and (d) the science value of each robotic mission in the absence of a subsequent manned 
mission. Another benefit of this quantitative approach is that robotic precursors can be traded against other 
risk mitigation strategies in the manned mission architecture. 

For more information on decision analysis, see de Neufville and Stafford, Systems Analysis for Engineers 
and Managers, 1971, and Barclay, et al., Handbook for Decision Analysis, 1977. 



J 



safety of launching spacecraft containing 
RTGs (Radioisotope Thermoelectric Gener- 
ators). 

The search for accident sequences is 
facilitated by event trees, which depict 
initiating events and combinations of system 
successes and failures, and fault trees, which 
depict ways in which the system failures 
represented in an event tree can occur. When 
integrated, an event tree and its associated 
fault tree(s) can be used to calculate the 
probability of each accident sequence. The 
structure and mathematics of these trees is 
similar to that for decision trees. The 



consequences of each accident sequence are 
generally measured both in terms of direct 
economic losses and in public health effects. 

Doing a PRA is itself a major effort, 
requiring a number of specialized skills 
other than those provided by reliability 
engineers and human factors engineers. 
PRAs also require large amounts of system 
design data at the component level and 
operational procedures data. [For additional 
information on PRAs, refer to the PRA 
Procedures Guide (1983) by the American 
Nuclear Society and Institute of Electrical 
and Electronic Engineers (IEEE).] 



;Vi 



READINGS IN SYSTEMS ENGINEERING 



Probabilistic Risk Assessment Pitfalls 

Risk is generally defined in a probabilistic risk 
assessment (PRA) as the expected value of a con- 
sequence function — that is: 

K = Z a r a C 9 

where P 3 is the probability of outcome s, and C„ is 
the consequence of outcomes. To attach probabil- 
ities to outcomes, event trees and fault trees are 
developed. These techniques have been used 
since 1953, but by the late 1970s, they were 
under attack by PRA practitioners. The reasons 
include the following: 

• Favlt trees are limiting because a complete 
set of failures is not definable 

• Common cause failures could not be captured 
properly. An example of a common cause fail- 
ure is one where all the valves in a system 
have a defect so that their failures are not 
truly independent 

• PRA results are sometimes sensitive to sim- 
ple changes in event tree assumptions 

• Stated criteria for accepting different kinds of 
risks are often inconsistent, and therefore not 
appropriate for allocating risk reduction re- 
sources 

• Many risk-related decisions are driven by 
perceptions, not necessarily objective risk as 
defined by the above equation. Perceptions of 
consequences tend to grow faster than the 
consequences themselves — that is, several 
small accidents are not perceived as strongly 
as one large one, even it fatalities are identi- 
cal 

• There are difficulties in dealing with incom- 
mensurables, as for example, lives vs. dollars. 



Probabilistic Network Schedules. Proba- 
bilistic network schedules, such as PERT 
(Program Evaluation and Review Tech- 
nique), permit the duration of each activity 
to be treated as a random variable. By 
supplying PERT with the minimum, 
maximum and most likely duration for each 
activity, a probability distribution can be 
computed for project completion time. This 
can then be used to determine, for example, 
the chances that a project (or any set of tasks 
in the network) will be completed by a given 
date. In this probabilistic setting, however, a 
unique critical path may not exist. Some 
practitioners have also cited difficulties in 
obtaining meaningful input data for 
probabilistic network schedules. 



Probabilistic Cost and Effectiveness 
Models. These models offer a probabilistic 
view of a project's cost and effectiveness out- 
comes. This approach explicitly recognizes 
that single point values for these variables 
do not adequately represent the risk condi- 
tions inherent in a project. 

Risk Mitigation and Tracking 
Techniques 

Risk identification and characterization and 
risk analysis provide a list of significant 
project risks that require further manage- 
ment attention and/or action. Because risk 
mitigation actions are generally not costless, 
the systems engineer, in making recommen- 
dations to the project manager, must balance 
the cost (in resources and time) of such 
actions against their value to the project. 
Four responses to a specific risk are usually 
available: (1) deliberately do nothing, and 
accept the risk, (2) share the risk with a co- 
participant, (3) take preventive action to 
avoid or reduce the risk, and (4) plan for con- 
tingent action. 

The first response is to accept a specific 
risk consciously. Sometimes, a risk can be 
shared with a co-participant, that is, with a 
foreign partner or a contractor. In this 
situation, the goal is to reduce NASA's risk 
independent of what happens to total risk, 
which may go up or down. There are many 
ways to share risks, particularly cost risks, 
with contractors. These include various 
incentive contracts and warranties. The 
third and fourth responses require that 
additional specific planning and actions be 
undertaken. 

Typical technical risk mitigation actions 
include additional (and usually costly) 
testing of subsystems and systems, design- 
ing in redundancy, and building a full 
engineering model. Typical cost risk mitiga- 
tion actions include using off-the-shelf 
hardware and providing sufficient funding 
during Phases A and B. Major supportability 



54 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



risk mitigation actions include providing 
sufficient initial spares to meet the system's 
availability goal and a robust resupply 
capability (when transportation is a signifi- 
cant factor). For those risks that cannot be 
mitigated by a design or management 
approach, the systems engineer should re- 
commend the establishment of reasonable 
financial and schedule contingencies and 
technical margins. 

The strategy and underlying rationale 
selected for a specific risk should be docu- 
mented in a risk mitigation plan and its ef- 
fectivity should be tracked through the pro- 
ject cycle, as required by NMI 8070. 4A. The 
techniques for choosing a (preferred) risk 
mitigation strategy deal with the larger role 
of trade studies and system modeling in gen- 
eral. Some techniques for planning and 
tracking are briefly mentioned here. 

Watchlists and Milestones. A watchlist is a 
compilation of specific risks, their projected 
consequences and early indicators of the 
start of the problem. The risks on the watch- 
list are those that were selected for manage- 
ment attention as a result of completed risk 
management activities. A typical watchlist 
also shows for each specific risk a triggering 
event or missed milestone (for example, a 
delay in the delivery of long lead items), the 
related area of impact (production schedule), 
and the risk mitigation strategy to be used in 
response. The watchlist is periodically 
reevaluated and items are added, modified or 
deleted as appropriate. Should the triggering 
event occur, the projected consequences 
should be updated and the risk mitigation 
strategy revised as needed. 

Contingency Planning. This technique is 
generally used in conjunction with a watch- 
list. The focus in contingency planning is on 
developing credible hedges and work 
arounds, which are activated upon a trigger- 
ing event. To be credible, hedges often re- 
quire that additional resources be expended, 
which provide a return only if the triggering 



event occurs. In this sense, contingency 
planning and resources act as a form of 
project insurance. (The term contingency 
here should not be confused with use of the 
same term for project reserves.) 

Critical Items/Issues Lists. A critical 
items/issues list (CIL) is similar to a watch- 
list, and has been used extensively on the 
Shuttle program to track items with signifi- 
cant system safety consequences. 

C/SCS and TPM Tracking. Two very 
important risk tracking techniques — cost 
and schedule control systems (C/SCS) and 
Technical Performance Measure (TPM) 
tracking — are discussed later. 

Risk Management: Summary 

Uncertainty is a fact of life in systems engi- 
neering. To deal with it effectively, the risk 
manager needs a disciplined approach. In a 
project setting, a good-practice approach 
includes efforts to: 

• Plan, document and complete a risk man- 
agement program. 

• Identify and characterize risks for each 
phase of the project. High risks, those for 
which the combined effects of likelihood 
and consequences are significant, should 
be given specific management attention. 
Reviews conducted throughout the 
project cycle should help to force out risk 
issues. 

• Apply qualitative and quantitative 
techniques to understand the dominant 
risks and to improve the allocation of risk 
reduction resources. This may include the 
development of project-specific risk ana- 
lysis models such as decision trees and 
PRAs. 

• Formulate and execute a strategy to 
handle each risk, including establish- 
ment, where appropriate, of reasonable 
financial and schedule contingencies and 
technical margins. 



55 



READINGS IN SYSTEMS ENGINEERING 



• Track the effectivity of each risk mitiga- 
tion strategy. 

Good risk management requires a team 
effort — that is, managers and systems engi- 
neers at all levels of the project need to be 
involved. However, risk management re- 
sponsibilities must be assigned to specific 
individuals. Successful risk management 
practices often evolve into institutional 
policy. 

Baseline Management 

The baseline for a project contains all of the 
technical requirements and related cost and 
schedule requirements that are sufficiently 
mature to be accepted and placed under 
change control by the NASA project man- 
ager. The project baseline consists of two 
parts: the technical baseline and the 
business baseline. The systems engineer is 
responsible for managing the technical base- 
line and ensuring that the technical baseline 
is consistent with the costs and schedules in 
the business baseline. Typically, the project 
control office manages the business baseline. 

Baseline management requires the for- 
mal agreement of both the buyer and the 
seller to proceed according to the up-to-date, 
documented project requirements (as they 
exist at that phase in the project cycle), and 
to change the baseline requirements only by 
a formal change control process. The buyer 
might be an external funding agency. For 
example, the buyer for the GOES project is 
NOAA and the seller is the NASA GOES 
project office. Baseline management must be 
enforced at all levels. In the next level for 
this same example, the NASA GOES project 
office is the buyer and the seller is the 
contractor, the Loral GOES project office. 

The project-level systems engineer is 
responsible for ensuring the completeness 
and technical integrity of the technical base- 
line. The content of the technical baseline 
includes: 



• Definition (or specification) of the func- 
tional and performance requirements for 
hardware, software and operations 

• Interface definitions 

• Specialty engineering requirements 

• Verification plans 

• Documentation trees. 

Baseline management includes the following 
techniques: 

• Baseline definition and approval 

• Configuration control (and version con- 
trol, if needed) 

• Change control 

• Traceability 

• Data management 

• Baseline communication. 

Baseline Evolution 

The project baseline evolves in discrete steps 
through the project life cycle. An initial 
baseline may be established when the top- 
level user requirements expressed in the 
Mission Needs Statement are placed under 
configuration control. At each interphase 
control gate, increased technical detail is 
added to the maturing baseline. For a typical 
project, there are five sequential technical 
baselines: 

• Functional baseline at Program/Project 
Requirements Review (PRR, sometimes 
called development baseline) 

• Design-to baseline at Preliminary Design 
Review (PDR) 

• Build-to (or code-to) baseline at the Criti- 
cal Design Review (CDR) 

• Production (or as-built or as-coded) base- 
line at the System Acceptance Review 
(SAR) 

• Operational (or as-deployed) baseline at 
Operational Acceptance Review (OAR). 

Risk management activity must begin 
early and continue throughout the 



56 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



decomposition process of the project cycle to 
prove that the core-level decisions are sound. 
These early detailed studies and tests must 
be documented and retained in the project 
archives, but they are not part of the techni- 
cal baseline. 

Configuration Management 

Configuration management is the discipline 
of identifying and formalizing the physical 
and functional characteristics of a configura- 
tion item at discrete points in the product 
evolution for the purpose of maintaining the 
integrity of the product and controlling 
changes to the baseline. As a functional 
discipline, configuration management man- 
ages the documentation of the approved 
evolution of a product's configuration. Con- 
figuration management includes configura- 
tion or baseline identification, configuration 
control and configuration communication. 
(See Figure 7.) 

Configuration management is essential to 
the execution of an orderly development 
process, to enable the modification of an 
existing design, and to provide for later rep- 
lication of an existing design. Configuration 
management often provides the information 
needed to track the technical progress of the 
project. 

Configuration identification of a baseline 
is evidenced by documentation such as 
requirements documents, specifications, 
drawings, code listings, process specifica- 
tions and material specifications. Configura- 
tion documentation is not considered part of 



the technical baseline until approved by 
control gate action of the buyer. 

Configuration control is the process of 
controlling changes to any approved baseline 
by formal action of a change board that is 
controlled by the same authority that pre- 
viously approved the baseline. Typically, the 
change control board meets to consider 
change requests to the business or technical 
baselines of the project. The project manager 
is usually the board chair, and the configura- 
tion manager the secretary, who skillfully 
guides the process and records the official 
events of the process. 

In a change control board forum, a num- 
ber of issues should be addressed: 

• What is the proposed change? 

• What is the reason for the change? 

• What is the design impact? 

• What is the effectiveness or performance 
impact? 

• What is the schedule impact? 

• What is the project life-cycle cost impact? 

• What is the impact of not making the 
change? 

• What is the risk of making the change? 

• What is the impact on operations? 

• What is the impact to support equipment 
and services? 

• What is the impact on spares require- 
ments? 

• What is the effectivity of the change? 

• What documentation is affected by the 
change? 

• Is the buyer supportive of the change? 




Figure 7 Configuration Management Structure 



57 



READINGS IN SYSTEMS ENGINEERING 



A review of this information should lead to a 
well-informed decision. When this informa- 
tion is not available to the change control 
board, unfounded decisions are made, often 
with negative consequences to the project. 



Change Control Board Conduct 

Objective: To review evaluations and then ap- 
prove or disapprove proposed changes to the pro- 
ject's technical, operations or business baseline. 
Participants: Project manager (chair), project- 
level systems engineer, managers of each affected 
organization, configuration manager (secretary), 
presenters. 

Format: Presenter covers recommended change 
and " cusses related system impact. The presen- 
tatii is reviewed by the systems engineer for 
completeness prior to presentation. 
Decision: The CCB members discuss the Change 
Request (CR) and formulate a decision. Project 
manager agrees or overrides. 



Configuration control always includes 
the management of approved baseline 
documentation, so configuration control is 
required on a no-change project as well as a 
frequently changing one. Configuration 
management and configuration control em- 
brace the function of data management, 
which ensures that only up-to-date baseline 
information is available to the project staff. 
The data management function also encom- 
passes managing and archiving supporting 
analyses and trade study data, and keeping 
it convenient for project use. 

Configuration verification is part of con- 
figuration control. It ensures that the result- 
ing products conform to the intentions of the 
designers and to the standards established 
by preceding approved baselines. Each con- 
trol gate serves to review and challenge the 
data presented for conformance to the pre- 
viously established baseline constraints. The 
Physical Configuration Audit control gate 
verifies that the physical configuration of the 
product corresponds to the build-to (or code- 
to) documentation previously approved at 
the CDR. The Functional Configuration 



Audit control gate verifies that the accep- 
tance test results are consistent with the test 
requirements previously approved at the 
PDR and CDR. The Formal Qualification 
Review control gate verifies that the as-built 
product is consistent with the as-built or as- 
coded documentation and describes the ulti- 
mate configuration of the product. This 
review follows all modifications needed to 
implement qualification-caused corrective 
actions. 

For disciplined software development, ad- 
ditional configuration control methods are 
recommended: 

• Computer Resources Working Group 
(CRWG) — ensures the development envi- 
ronment is adequate for the job 

• Software Configuration Review Board — 
change board for software baseline 
changes 

• Software Development Library — man- 
agement controlled repository for soft- 
ware development documentation and 
tools 

• Software Development Folder (SDF)— 
developer-controlled repository for devel- 
opment documentation and tools. 

The configuration manager performs the 
following functions: 

• Conceives, documents and manages the 
configuration management system 

• Acts as secretary of the change control 
board (controls the change approval 
process) 

• Controls changes to baseline documenta- 
tion 

• Controls release of baseline documenta- 
tion 

• Initiates configuration verification au- 
dits. 

Configuration communication is the process 
of conveying to all involved parties the 
approved baseline progression in a timely 
manner. This is essential to ensure that 



58 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



developers only pursue options that are com- 
patible with the approved baseline. 

Communication also keeps developers 
knowledgeable of the approved baseline and 
the necessity of approaching the change con- 
trol board for approval of any deviations 
considered necessary to further develop the 
system. 

The project's approach to configuration 
management should be documented in the 
project's Configuration Management Plan. 

Change Control and Version Control 

Once a baseline is placed under change con- 
trol, any change requires the approval of the 
change control board. The project manager 
chairs the change control board, while the 
systems engineer or configuration manager 
is responsible for reviewing all material for 
completeness before it is presented to the 
board, and for ensuring that all affected or- 
ganizations are represented in the change 
control board forum. 

Change control is essential at both the 
contractor and NASA Center levels. 
Changes determined to be Class 1 to the 
contractor must be referred to the NASA 
project manager for resolution. This process 
is described in Figure 8. The use of a prelimi- 
nary Engineering Change Proposal (ECP) to 



forewarn of an impending change provides 
the project manager with sufficient prelimi- 
nary information to determine whether the 
contractor should spend NASA contract 
funds on a formal ECP. This technique is 
designed to save significant contract dollars. 

Class 1 changes affect the approved base- 
line and hence the product version identifica- 
tion. Class 2 changes are editorial changes or 
internal changes not "visible" to the external 
interfaces. 

Overly formalized systems can become so 
burdensome that members of the project 
team may try to circumvent the process. It is 
essential that the formality of the change 
process be appropriately tailored to the 
needs of each project. However, there must 
always be an effective change control process 
on every project. 

For software projects, it is routine to use 
version control for both pre-release and post- 
release deliverable systems. It is equally 
important to maintain version control for 
hardware-only systems. 

Approved changes on a development 
project that has only one deliverable ob- 
viously are only applicable to that one deliv- 
erable item. However, for projects that have 
multiple deliverables of "identical" design, 
changes may become effective on the second 
or subsequent production articles. In such a 



r — 

i 
* 




r 

Disapprove 

■ 
i 








r 

Disapprove 

j Request 






* 
Disapprove 

i 

i 




Change 
Request 


—*■ 


Seller 
CCB 


Approve 
Class I 


Prepare 

Prelim 

ECP 


^- 


Buyer 
CCB 


■ Formal ECP 


Prepare 
ECP 


— *■ 


Buyer 
Decision 


App 














App 
Clai 


rove 

sn 




i 


No 






Approve 














Buyer 1 
Concurrence | 






^- 




1 >- 


with 1 
















Record 
Change 
Status 




Implement 




| | Indicates Buyer Action 








-« 


CI 


lange 


«*■ ' 



Figure 8 Contract Change Control Process 



59 



READINGS IN SYSTEMS ENGINEERING 



situation, the change control board must 
decide the effectivity of the change, and the 
configuration control system must maintain 
version control and identification of the 
as-built configuration for each article. Incre- 
mental implementation of changes is 
common in projects that have a deliberate 
policy of introducing product or process 
improvements. As an example, the original 
1972 plan held that each of the Space Shuttle 
orbiters would be identical. In reality, each 
of the orbiters is different, driven primarily 
by the desire to achieve the original payload 
requirement of 65,000 pounds. Proper 
version control documentation has been 
essential to the sparing, fielding and main- 
tenance of the operational fleet. 

Data Management and Requirements 
Traceability 

Data management is an essential and associ- 
ated function to configuration management. 
Data management ensures that official 
baseline data is retained, available and 
controlled for all official project use. Data 
management is essentially the official 
project library and reference desk. 

The data manager performs the following 
functions: 

• Conceives, documents and manages the 
documentation management system 

• Manages changes to baseline documenta- 
tion 

• Manages the release of baseline docu- 
mentation 

• Manages the project library. 

Before the project team can produce a 
tangible product, engineering must produce 
descriptions of the system using words, icons 
(drawings) and numbers (i.e., symbolic in- 
formation). The project team must have a 
common understanding of the words and 
icons in order to be able to go from an idea to 
a properly functioning system. 



Since the systems engineer spends time 
working with information about the system 
rather than the system itself, there are 
several vital characteristics the symbolic in- 
formation must have. First, the information 
must be shareable. Whether it is in electron- 
ic or paper form, the data must be readily 
available in the most recently approved 
version to all members of the team. 

Second, symbolic information must be 
durable. This means that it must be recalled 
accurately every time and represent the 
most current version of the baseline. The 
baseline information cannot change or de- 
grade with repeated access of the database or 
paper files, and cannot degrade with time. 
This is not a trivial requirement, poor data 
management practices (e.g., allowing some- 
one to borrow the only copy of a document or 
drawing) can allow controlled information to 
become lost. Also, material must be retained 
for the life of the program (and possibly be- 
yond), and a complete set of documentation 
for each baseline change must be retained. 

Third, the symbolic information must be 
traceable upward and downward. A data 
base must be developed and maintained to 
show the parentage of any requirement. The 
data base must also be able to display all 
children derived from a given requirement. 
Finally, traceability must be provided to 
engineering reports that document trade 
study results and other decisions that played 
a key role in the flowdown of requirements. 

It is the responsibility of the systems 
engineer to ensure the active, approved base- 
line is communicated to all those relying on 
it. This technique keeps all participants ap- 
prised as to the distinction between what is 
frozen under formal change control and what 
can still be decided without change control 
board approval. 

Reviews, Audits and Control Gates 

The intent and policy for reviews, audits and 
control gates should be developed during 



60 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



Phase A and defined in the Project Imple- 
mentation Plan. The specific implementa- 
tion of these activities should be consistent 
with, though not limited to, the types of 
reviews and audits described in this section. 
The same tailoring applies to the timing of 
reviews, audits and control gates. 

The purpose of a review is to furnish the 
forum and process to provide NASA manage- 
ment and their contractors assurance that 
the most satisfactory approach, plan or 
design has been selected, that a configura- 
tion item has been produced to meet the 
specified requirements, or that a configura- 
tion item is ready. Reviews (technical or 
management) are scheduled to communicate 
an approach, demonstrate an ability to meet 
requirements or establish status. Reviews 
help to develop a better understanding 
among task or project participants, open 
communication channels, alert participants 
and management of problems and open ave- 
nues for solutions. 



Project Termination 

It should be noted that project termination, 
while usually disappointing to project personnel, 
may be a proper reaction to changes in external 
conditions or to an improved understanding of 
the system's projected cost-effectiveness. 



The purpose of an audit is to provide 
NASA management and its contractors a 
thorough examination of adherence to pro- 
gram or project policies, plans, requirements 
and specifications. Audits are the systematic 
examination of tangible evidence to deter- 
mine adequacy, validity and effectiveness of 
the activity or documentation under review. 
An audit may examine documentation of 
policies and procedures as well as verify 
adherence to them. 

The purpose of a control gate is to provide 
a scheduled event (either a review or an 
audit) that NASA management will use to 
make program or project go/no-go decisions. 
A control gate is a management event in the 



project cycle that is of sufficient importance 
to be identified, defined and included in the 
project schedule. It requires formal examina- 
tion to evaluate project status and to obtain 
approval to proceed to the next management 
event according to the Project Implementa- 
tion Plan. 

GENERAL PRINCIPLES FOR REVIEWS 

Review Boards. The convening authority, 
who supervises the manager of the activity 
being reviewed, normally appoints the 
review board chair. Unless there are compel- 
ling technical reasons to the contrary, the 
chair should not be directly associated with 
the project or task under review. The conven- 
ing authority also names the review board 
members. The majority of the members 
should not be directly associated with the 
program or project under review. 

Internal Reviews. During the course of a 
project or task, it is necessary to conduct 
internal reviews that present technical 
approaches, trade studies, analyses and 
problem areas to a peer group for evaluation 
and comment. The timing, participants and 
content of these reviews are normally de- 
fined by the project manager or the manager 
of the performing organization. Internal 
reviews are also held prior to participation in 
a formal, control gate review. 

The internal reviews provide an excellent 
means for controlling the technical progress 
of the project. They also should be used to en- 
sure that all interested parties are involved 
in the design/development process early on, 
and throughout the process. Thus, represen- 
tatives from areas such as manufacturing 
and quality assurance should attend the 
internal reviews as active participants. They 
can then, for example, ensure that the design 
is producible and that quality is managed 
through the project cycle . 

In addition, some organizations utilize a 
Red Team. This is an internal, independent, 
peer-level review conducted to identify any 



READINGS IN SYSTEMS ENGINEERING 



deficiencies in requests for proposals, propos- 
al responses, documentation or presentation 
material prior to its release. The project or 
task manager is responsible for establishing 
the Red Team membership and for deciding 
which of their recommendations are to be 
implemented. 

Review Presentation Material. Presenta- 
tions using existing documentation such as 
specifications, drawings, analyses and re- 
ports may be adequate. Copies of any pre- 
pared materials (such as viewgraphs) should 
be provided to the review board and meeting 
attendees. Background information and re- 
view presentation material of use to board 
members should be distributed to the mem- 
bers early enough to enable them to examine 
it prior to the review. For major reviews, this 
time may be as long as 30 calendar days. 

Review Conduct. All reviews should con- 
sist of oral presentations of the applicable 
project requirements and the approaches, 
plans or designs that satisfy those require- 
ments. These presentations normally are 
given by the cognizant design engineer or 
his/her immediate supervisor. 

It is highly recommended that in addition 
to the review board, the review audience in- 
clude project personnel (NASA and contrac- 
tor) not directly associated with the design 
being reviewed. This is required to utilize 
their cross-disciplinary expertise to identify 
any design shortfalls or recommend design 
improvements. The review audience should 
also include non-project specialists in the 
area under review, and specialists in manu- 
facturing and fabrication, testing, quality 
assurance, reliability and safety. Some 
reviews may also require the presence of 
both the contractor's and NASA's contract- 
ing officers. 

Prior to and during the review, board 
members and review attendees may submit 
requests for action or engineering change 
requests (ECR) that document a concern, 
deficiency or recommended improvement in 



the presented approach, plan or design. 
Following the review, these are screened by 
the review board to consolidate them and to 
ensure that the chair and cognizant man- 
agers) understand the intent of the re- 
quests. It is the responsibility of the review 
board to ensure that adequate closure 
responses for each of the action requests are 
obtained. 

Post Review Report. The review board 
chair has the responsibility to develop, 
where necessary, a consensus of the findings 
of the board, including an assessment of the 
risks associated with problem areas, and de- 
velop recommendations for action. The chair 
will submit, on a timely basis, a written 
report, including recommendations for ac- 
tion, to the convening authority with copies 
to the cognizant managers. 

Standing Review Boards. Standing review 
boards are selected for projects or tasks that 
have a high level of activity, visibility and/or 
resource requirements. Selection of board 
members by the convening authority is gen- 
erally made from senior Center technical 
and management staff. Supporting members 
or advisors may be added to the board as 
required by circumstances. If the review 
board is to function over the lifetime of a pro- 
ject, it is advisable to select extra board 
members and rotate active assignments to 
cover needs. 

Specific Types of Reviews 

This section describes the types, purpose, 
timing and content of most of the reviews 
that may occur during the conduct of projects 
or tasks. Review material should be keyed to 
project documentation when available to 
minimize separate efforts. 

Program/Project Requirements Review. 
Purpose. The Program/Project Require- 
ments Review (PRR) establishes the project 



62 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



development (i.e., functional) baseline. It 
ensures that: 

• The project objectives (particularly the 
research and/or science objectives) have 
been properly translated into definite and 
unambiguous statements of require- 
ments. 

• The impact of these requirements on the 
design of the major project elements and 
systems is sufficiently well understood 
that trades between requirements and 
constraints can be properly made. 

• The management techniques, procedures, 
agreements and resources to be utilized 
by all project participants are evaluated. 

Timing. At the completion of the Concept 
Definition Phase (Phase B) activities, just 
prior to issuing the Source Selection Request 
for Proposal. 

Agenda. The appropriate items from the 
following review items/data checklist should 
be addressed: 

• Status of action items from the Conceptu- 
al Design Review (CoDR) 
Project Plan 
Mission objectives 
Research objectives 
Science objectives 
Design criteria and approach 
System trade analyses 
Design analyses and trade studies 
Final system specification 
Preliminary interface specifications 
Software system requirements 
Work breakdown structure 
Preliminary manufacturing plan 
Preliminary ground operations plan 
Preliminary payload integration plan 
Preliminary flight operations plan 
Preliminary data management plan 
Configuration management plan 
Reliability requirements and plan 
Quality assurance requirements and plan 
System safety requirements and plan 
Project policy and requirements 



• Management structure 

• Budget constraints 

• Schedule 

• Risk management activities. 

Preliminary Design Review. The Prelimi- 
nary Design Review (PDR) is not a single re- 
view but a number of reviews starting with 
the system PDR, followed by reviews con- 
ducted on specific configuration items (CIs). 

Purpose. The PDR establishes the 
design-to baseline and ensures that it meets 
the program, project, system, subsystem or 
specific CI baseline requirements. The PDR 
process should: 

• Establish the ability of the selected de- 
sign approach to meet the technical 
requirements. 

• Establish the compatibility of the inter- 
face relationships between the specific 
configuration item and other interfacing 
items. 

• Establish the integrity of the selected 
design approach. 

• Establish the oper ability of the selected 
design. 

• Assess compliance with quality assur- 
ance, reliability and system safety re- 
quirements. 

• Address status, schedule and cost rela- 
tionships. 

• Establish the feasibility of the approach. 

Timing. After design-to specifications 
are developed and after risk reduction analy- 
ses are available. 

Agenda. The appropriate items from the 
following review items/data checklist should 
be addressed: 

• Status of action items from the applicable 
Hardware or Software Specification 
Review(s) 

• Final functional requirements and speci- 
fications 

• Technical justification for the perfor- 
mance specified 



63 



READINGS IN SYSTEMS ENGINEERING 



• Experiment performance analysis, in- 
cluding an analysis of instrument accura- 
cy requirements 

Design parameters and constraints 
Environmental design requirements 
Interface design requirements 
Requirements traceability results 
Software standards to be applied 
Design and safety codes and standards to 
be applied 

Results of technical feasibility modeling 
and testing 

Design optimization analyses 
Discussion of block diagrams 
Compliance with functional require- 
ments and specifications 
Suitability of inherited designs and hard- 
ware 

Lists of preliminary parts, materials and 
processes 

Spares requirements philosophy 
Preliminary data management flow and 
reduction plans 

Preliminary pay load integration plan 
Preliminary ground operations plan 
Preliminary flight operations plan 
Requirements and plans for support 
equipment, including ground support 
equipment (GSE) 

Preliminary reliability analyses, includ- 
ing single-point failure mode policy 
Preliminary system safety analyses 
Quality Assurance Plan 
Hardware and/or software verification 
plans 

Hardware and software development 
plans and schedules (including verifica- 
tion tests or analyses to be performed) 
Present status of item under review, in- 
cluding cost and technical developments 
Risk management activities. 



Critical Design Review. The Critical De- 
sign Review (CDR) is not a single review but 
a number of reviews starting with specific 
CIs and ending with the system CDR. 

Purpose. The CDR verifies the suitabil- 
ity of a CI design in meeting the specified 



requirements and establishes its build-to 
and/or code-to baseline. The CDR determines 
whether the design is compatible with the 
specified requirements, and verifies that the 
design conforms to the requirements estab- 
lished at the PDR and updated to the time of 
the CDR. During the CDR, the integrity of 
the design is verified through review of ana- 
lytical and test data. 

Following the CDR, the CI specifications 
and drawings are updated and placed under 
configuration control, and may be then re- 
leased for fabrication and/or coding. 

Timing. When the design of a CI is com- 
plete and after the completion of producibil- 
ity demonstration. It should be held early 
enough to allow for corrective action and 
before total design freeze, the purchase of 
significant equipment or fabrication of final 
hardware. 

Agenda. The appropriate items from the 
following review items/data checklist should 
be addressed: 

• Status of PDR action items 

• Design requirements and specifications 

• Interface requirements and specifications 

• Design approach 

• Assessment of hardware and software 
inheritance 

• Test procedures 

• Producibility demonstration results 

• Scale model test results 

• Design trades and alternatives consid- 
ered 

• Reliability, maintainability and opera- 
bility considerations 

• Spares list 

• Conformance of the design to functional 
and user requirements 

• Conformance to environmental design 
requirements 

• Differences between the configuration 
item, system and subsystem perfor- 
mances in relation to the performances 
estimated at the PDR 

• Final hardware and software design ver- 
ification plans 



64 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



Detailed mechanical (including electronic 
packaging, thermal, hydraulic and pneu- 
matic) design 

Detailed electronic and electrical circuit 
design 

Detailed software design 
Interface details and agreements 
Mechanical and electronic parts stress 
analysis results 

Final reliability analyses, including 
single-point failure analyses against the 
reliability policy 
System safety analyses 
Electronic parts classifications and 
screening specifications 
Nonelectric parts, materials and process- 
ing list 

Materials and processing specifications 
Purchased devices list 
Manufacturing and fabrication plans 
Quality assurance plans and procedures 
Configuration control plans 
Qualification and acceptance test plans 
Calibration plan 

Data management flow and data reduc- 
tion plan 

Support equipment and GSE require- 
ments and plans 
Spares provisioning plan 
Ground operations plan 
Payload integration plan 
Flight operations plan 
Present status of item under review, in- 
cluding cost and technical developments 
Risk management activities. 



Test Readiness Review. The Test Readi- 
ness Review (TRR) is not a single review but 
a series of reviews conducted prior to the 
start of verification testing of each test arti- 
cle, CI, subsystem and/or system. 

Purpose. The TRR establishes the deci- 
sion point to proceed with planned verifica- 
tion (qualification and/or acceptance) testing 
of test articles, CIs, subsystems and/or sys- 
tems to acquire official sell-off verification 
data. The TRR assesses the adequacy of the 



test planning and compatibility with the ver- 
ification requirements and specifications. 

Timing. After completion of preliminary 
testing and prior to the start of official verifi- 
cation testing. 

Agenda. The appropriate items from the 
following review items/data checklist should 
be addressed: 

• Description of test article 

• Test objectives 

• Verification requirements and specifica- 
tions 

• Applicable test plans 

• Applicable test procedures 

• Test configuration and functional block 
diagrams 

• Test equipment and circuitry 

• Test equipment calibration 

• Data to be collected, and collection and 
preservation methods 

• Quality assurance plan 

• Safety plan 

• Test failure procedures 

• Personnel responsibilities and qualifica- 
tions 

• Present status of item under review in- 
cluding cost and technical developments 

• Risk management activities. 

System Formal Qualification Review. 

Purpose. The System Formal Qualifica- 
tion Review (SFQR) establishes the system 
production baseline by verifying that the 
system performance meets the system 
qualification specifications. The qualifica- 
tion testing demonstrates that the system 
meets its performance and operational 
requirements within the specified margins. 
The SFQR is the decision point for customer 
approval of the qualification certification of 
the design. 

Timing. After the completion of all 
lower-level qualification testing. 

Agenda. The appropriate items from the 
following review items/data checklist should 
be addressed: 



65 



READINGS IN SYSTEMS ENGINEERING 



• Status of action items from the applicable 
CDRs and TRRs 

• Description of system tested, including 
all subsystems and functional block dia- 
grams 

• Qualification test objectives 

• Qualification test requirements and 
specifications 

• Description of test facilities 

• Description of test configurations 

• Subsystem qualification test results 

• System qualification test results 

• Qualification by similarity analysis 

• Nonconformance reports/status 

• Waivers and deviations 

• Open work list 

• Environmental retest following correc- 
tive action of any failures 

• Strength and fracture mechanics for as- 
built hardware 

• Software development documentation 

• Summary of qualification status of all 
end items subjected to separate qualifica- 
tion tests 

• Operational manuals 

• Maintenance manuals 

• Present status of system under review, 
including cost and technical develop- 
ments 

• Risk management activities. 

Functional and Physical Configuration 
Audit. 

Purpose. A Functional Configuration 
Audit (FCA) verifies that each as-built con- 
figuration item, test article, subsystem 
and/or system satisfies the functional and 
performance requirements specified in their 
respective design-to specifications. 

A Physical Configuration Audit (PCA) 
verifies that each as-built test article, CI, 
subsystem and/or system: 

• Satisfies the physical requirements 
(weight, center of gravity, moments of in- 
ertia, surface finish, cleanliness, etc.) 
specified in their respective design speci- 
fications 



• Is correctly documented in as-built draw- 
ings, code listings, user manuals, etc. 

Timing. Following the completion of the 
SFQR. Usually held in conjunction with the 
System Acceptance Review (SAR). For single 
unit projects, the FCA/PCA may be held pri- 
or to qualification testing. 

Agenda. The appropriate items from the 
following project documentation should be 
addressed: 

• CI, subsystem and system specifications 

• Design drawings and engineering orders 

• Subsystem and system schematics and 
block diagrams 

• Design verification matrices for each con- 
figuration item, subsystem and system 

• Inspection results 

• Material and electronic parts certifica- 
tions 

• Materials process certifications 

• Material Utilization List (MUL) 

• Installed non-flight hardware list 

• Test results 

• Demonstration results 

• Nonconformance reports/status 

• Results of each Configuration Item Ac- 
ceptance Review (CIAR) 

• Results of the SFQR. 

System Acceptance Review. 

Purpose. The System Acceptance Review 
(SAR) provides the decision point to confirm 
that the design is ready for either integra- 
tion, acceptance or replication. 

Timing. Following the completion of 
the SFQR and prior to the Multi-Unit 
Procurement Phase and/or the Pre- 
Operations Phase (Phase E). 

Agenda. The appropriate items from the 
following project documentation should be 
addressed: 

• Brief description of system under review 

• Verification requirements 

• Results of the system FCA and PCA 

• Results of the SFQR 



66 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



• System verification report (qualification 
and operation) 

• System acceptance report 

• Final systems operations and mainten- 
ance methods 

• System development lessons learned 
document 

• Safety analyses status 

• Present status of system under review, 
including cost and technical develop- 
ments 

• Risk management activities. 

Safety Reviews. System safety is the appli- 
cation of engineering and management prin- 
ciples, criteria and techniques to optimize 
safety within the constraints of operational 
effectiveness, time and cost through all 
phases of the project cycle. A series of system 
and occupational safety reviews are held 
during the project cycle, many of which are 
held concurrently with other project reviews. 
Following are descriptions of these reviews 
and their relationship to the other project 
reviews. 

Occupational Safety Reviews. The re- 
quirements for these reviews are not covered 
here. However, the systems engineer should 
be aware that many occupational safety re- 
quirements can impose requirements on 
flight and/or ground equipment, such as the 
shipping and handling of pressure vessels or 
toxic or explosive materials. Early reviews 
with Center occupational safety personnel 
should be held to identify and understand 
any problem areas and specify the require- 
ments to control them. 

Conceptual Design Safety Review. 

Purpose. The Conceptual Design Safety 
Review (CoDSR) ensures that safety require- 
ments have been included in the conceptual 
design and that a preliminary assessment of 
the potential hazards has been made. At 
several NASA Centers, the CoDSR is called 
the Phase Safety Review. 



Timing. At the completion of the Mission 
Needs and Conceptual Studies Phase (Phase 
A). It should be held concurrently with the 
Conceptual Design Review (CoDR). 

Agenda. The appropriate items from the 
following list should be addressed: 

• Purpose of the project, facility or equip- 
ment 

• Design requirements 

• Safety requirements 

• Preliminary project safety plan 

• Preliminary hazard analysis 

• Safety staffing and management struc- 
ture 

• Safety budget 

• Schedule 

• Risk management activities. 

Project Requirements Safety Review. 

Purpose. The Project Requirements 
Safety Review (PRSR) establishes the project 
safety requirements baseline and ensures 
that: 

• The project safety objectives have been 
properly translated into definite and un- 
ambiguous statements of requirements. 

• The impact of these requirements on the 
design of the major project elements and 
systems is sufficiently well understood 
that trades between requirements and 
constraints can be properly made. 

• The management techniques, procedures, 
agreements and resources to implement 
the safety program by all project partici- 
pants are evaluated. 

Timing. At the completion of the Concept 
Definition Phase (Phase B) activities just 
prior to issuing the Source Selection Request 
for Proposal. It should be held concurrently 
with the PRR. 

Agenda. The appropriate subjects from 
the following list should be addressed: 

• Purpose of the project, facility or equip- 
ment 



67 



READINGS IN SYSTEMS ENGINEERING 



• Status of action items from the CoDSR 

• Design requirements 

• Safety requirements 

• Updated preliminary project safety plan 

• Updated preliminary hazard analysis 

• Safety staffing and management struc- 
ture 

• Safety budget 

• Schedule 

• Risk management activities. 

Preliminary Design Safety Review. The 

Preliminary Design Safety Review (PDSR) is 
not a single review but a series of reviews 
conducted on specific configuration items, 
subsystems and the system. 

Purpose. The PDSR ensures that the 
proposed CI, subsystem and/or system de- 
signs satisfy the project and Center safety re- 
quirements. At several NASA Centers, the 
PDSR is called the Phase I Safety Review. 

Timing. At the completion of prelimi- 
nary design and prior to the start of major 
detail design activities. It should be held con- 
currently with the PDRs. 

Agenda. The appropriate subjects from 
the following list should be addressed: 

• Description of design under review 

• Status of safety -related action items from 
applicable hardware or software specifi- 
cation reviews 

• Updated project safety plan 

• Updated safety analysis reports 

• Updated preliminary hazard analyses 
(sometimes called the Phase I Hazard 
Analyses) 

• Preliminary Failure Modes and Effects 
Analysis (FMEA) 

• Preliminary Critical Items List (CIL). 

• List of limited-life items 

• Accident or mishap investigation reports 

• Waiver and deviation request disposi- 
tions 

• Present status of safety activities, includ- 
ing cost and technical developments 

• Risk management activities. 



Critical Design Safety Review. The Criti- 
cal Design Safety Review (CDSR) is not a 
single review but a series of reviews conduct- 
ed on specific configuration items, subsys- 
tems and the system. 

Purpose. The CDSR establishes the 
baseline for safety requirements, safety haz- 
ard controls and verification methods to be 
implemented in verifying those controls. At 
several NASA Centers, the CDSR is called 
the Phase II Safety Review. 

Timing. When the design of a configura- 
tion item is essentially complete and prior to 
total design freeze, the purchase of signifi- 
cant equipment, or fabrication of final hard- 
ware. It should be held concurrently with the 
CDRs. 

Agenda. The appropriate subjects from 
the following list should be addressed: 

• Description of design under review 

• Status of safety -related action items from 
applicable hardware or software PDSRs 

• Final project safety plan 

• Updated safety analysis reports 

• Updated preliminary hazard analyses 
(sometimes called the Phase II Hazard 
Analyses) 

• Final Failure Modes and Effects Analysis 

• Final Critical Items List 

• List of limited-life items 

• Accident or mishap investigation reports 

• Waiver and deviation request disposi- 
tions 

• Present status of safety activities includ- 
ing cost and technical developments 

• Risk management activities. 

System Acceptance Safety Review. 

Purpose. The System Acceptance Safety 
Review (SASR) provides the decision point to 
confirm that all project safety requirements 
have been satisfied and confirms the satis- 
factory completion of all hazard control 
verification items and open safety items. At 
several NASA Centers, the SASR is called 
the Phase III Safety Review. 



68 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



Timing. Following the completion of the 
SFQR and prior to the Multi-Unit Procure- 
ment Phase and the Pre-Operation Phase 
(Phase E). It should be held concurrently 
with the SAR. 

Agenda. The appropriate subjects from 
the following list should be addressed: 

• Description of design under review 

• Status of safety-related action items from 
applicable hardware or software CDRs 

• Updated safety analysis reports 

• Updated preliminary hazard analyses 
(sometimes called the Phase III Hazard 
Analyses) 

• Accident or mishap investigation reports 

• Waiver and deviation request disposi- 
tions 

• Present status of safety activities, includ- 
ing cost and technical developments 

• Risk management activities. 

Launch or Operational Safety Readiness 
Reviews. 

Purpose. These reviews ensure the flight 
and/or ground operational safety of the item 
under review by certifying that: 

• A CI, subsystem or system complies with 
all program and/or project safety require- 
ments. 

• Approved controls for all identified safety 
hazards have been implemented. 

• All personnel involved in the handling 
and/or operation of the item under review 
have received the required training. 

Timing. Following installation and inte- 
gration and prior to flight and/or start of 
ground operations. 

Agenda. The appropriate subjects from 
the following list should be addressed: 

• Brief description of item under review 

• Safety requirements and specifications 

• Safety compliance data package 

• Hazard analyses/reports with supporting 
data 



• Critical items list 

• Limited-life item list 

• Accident or mishap investigation reports 

• Nonconformance reports/status 

• Personnel training requirements 

• Personnel training status 

• Present status of safety activities, includ- 
ing cost and technical developments 

• Risk management activities. 

Status reporting and assessment 

An important part of systems engineering 
planning is determining what is needed in 
time, resources and people to realize the 
system that meets the desired goals and 
objectives. Planning functions such as WBS 
preparation, scheduling and fiscal resource 
requirements planning, were discussed earli- 
er. Project management, however, does not 
end with planning; project managers need 
visibility into the progress of those plans in 
order to exercise proper management con- 
trol. This is the purpose of the status report- 
ing and assessing processes. Status reporting 
is the process of determining where the 
project stands in dimensions of interest such 
as cost, schedule and technical performance. 
Assessing is the analytical process that con- 
verts the output of the reporting process into 
a more useful form for the project manager; 
namely, what are the future implications of 
current trends? Lastly, the manager must 
decide whether that future is acceptable, and 
what changes, if any, in current plans are 
needed. Planning, status reporting, and 
assessing are systems engineering and/or 
program control functions; decision making 
is a management one. 

These processes together form the feed- 
back loop depicted in Figure 9. This loop 
takes place on a continual basis throughout 
the project cycle. 

This loop is applicable at each level of the 
project hierarchy. Planning data, status re- 
porting data and assessments flow up the 
hierarchy with appropriate aggregation at 
each level; decisions cause actions to be 



69 



readings in systems engineering 



(Re) 
Planning 



Status 
Reporting 



Assessing 



Status Not OK 



Decision 
Making 



Status 



OK 



Figure 9 Planning and Status Reporting 
Feedback Loop 



taken down the hierarchy. Managers at each 
level determine (consistent with policies 
established at the next higher level of the 
project hierarchy) how often, and in what 
form, reporting data and assessments should 
be made. In establishing these status report- 
ing and assessment requirements, some 
principles of good practice are: 

• Use an agreed-upon set of well-defined 
status reporting variables 

• Report these core variables in a consis- 
tent format at all project levels 

• Maintain historical data for both trend 
identification and cross-project analyses 

• Encourage a logical process of rolling up 
status reporting variables, (e.g., use the 
WBS for obligations/costs status report- 
ing and PBS for mass status reporting) 

• Support assessments with quantitative 
risk measures 

• Summarize the condition of the project by 
using color-coded (red, yellow, and green) 
alert zones for all core reporting vari- 
ables. 

Regular, periodic (e.g., monthly) tracking of 
the core status reporting variables is recom- 
mended, through some status reporting vari- 
ables should be tracked more often when 
there is rapid change or cause for concern. 
Key reviews, such as PDRs and CDRs, are 
points at which status reporting measures 
and their trends should be carefully scru- 
tinized for early warning signs of potential 
problems. Should there be indications that 
existing trends, if allowed to continue, will 
yield an unfavorable outcome, replanning 
should begin as soon as practical. 



This section provides additional infor- 
mation on status reporting and assessment 
techniques for costs and schedules, technical 
performance, and systems engineering pro- 
cess metrics. 

Cost and Schedule Control Measures 

Status reporting and assessment on costs 
and schedules provides the project manager 
and systems engineer visibility into how 
well the project is tracking against its 
planned cost and schedule targets. From a 
management point of view, achieving these 
targets is on a par with meeting the techni- 
cal performance requirements of the system. 
It is useful to think of cost and schedule 
status reporting and assessment as measur- 
ing the performance of the "system that 
produces the system." 

NHB 9501.2B, Procedures for Contractor 
Reporting of Correlated Cost and Perfor- 
mance Data, provides specific requirements 
for cost and schedule status reporting and 
assessment based on a project's dollar value 
and period of performance. Generally, the 
NASA Form 533 series of reports is applica- 
ble to NASA cost-type (i.e., cost reimburse- 
ment and fixed-price incentive) contracts. 
However, on larger contracts (>$25M) 
which require Form 533P, NHB 9501. 2B al- 
lows contractors to use their own reporting 
systems in lieu of 533P reporting. The pro- 
ject manager/systems engineer may choose 
to evaluate the completeness and quality of 
these reporting systems against criteria 
established by the project manager/systems 
engineer's own Center, or against the DoD's 
Cost/Schedule Cost System Criteria 
(C/SCSC). The latter are widely accepted by 
industry and government, and a variety of 
tools exist for their implementation. 

Assessment Methods. The traditional 
method of cost and schedule control is by 
comparing baselined cost and schedule plans 
against their actual values. In program con- 
trol terminology, a difference between actual 



70 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



performance and planned costs or schedule 
status is called a variance. 

Figure 10 illustrates two kinds of vari- 
ances and some related concepts. A properly 
constructed work breakdown structure 
(WBS) divides the project work into discrete 
tasks and products. Associated with each 
task and product (at any level in the WBS) is 
a schedule and a budgeted (i.e., planned) 
cost. The Budgeted Cost of Work Scheduled 
(BCWSt) for any set of WBS elements is the 
budgeted cost of all work on tasks and pro- 
ducts in those elements scheduled to be com- 
pleted by time t. The Budgeted Cost of Work 
Performed (BCWPt) is a statistic represent- 
ing actual performance. BCWPt, also called 
Earned Value (EVt), is the budgeted cost for 
tasks and products that have actually been 
produced (completed or in progress) at time t 
in the schedule for those WBS elements. The 
difference, BCWP t -BCWS t) is called the 
schedule variance at time t . 







BCWS, 


1 


^ A Forecaat of 

X Coat Variance 

T at Completion 

Budget 


c 
u 

M 

u 

L 
A 
T 
I 


''■'■'•I'-:: 

/// (w EV) 

j^y^ Current 
£r Date j 


f ,' ACWP 

/ / 
1 ' 




1 
t 
1 
1 
/ 
1 


i 
P) , 


i 

Schedule 
Variance 
to Date 
IBCWP 
BCWS) 


V 
E 

$ 


i 


Coet Variance 
to Date 
,<BCWP ACW 


n 


a 


BCWS 

ACWP 

BCWP 

EV 
EAC 


= Budgeted Cost of 
Work Scheduled 

= Actual Cost of 
Work Performed 

= Budgeted Cost of 
Work Performed 




u 


TIME 






= 


Estimate at 
Completion 





Figure 10 Cost and Schedule Variances 

The Actual Cost of Work Performed 
(ACWPt) is a third statistic representing the 
funds that have been expended up to time t 
on those WBS elements. The difference be- 
tween the budgeted and actual costs, 



BCWPt -ACWPt, is called the cost variance 
at time t. Such variances may indicate that 
the cost Estimate at Completion (EACt) of the 
project is different from the budgeted cost. 
These types of variances enable a program 
analyst to estimate the EAC at any point in 
the project cycle. 

If the cost and schedule baselines and the 
technical scope of the work are not fully inte- 
grated, then cost and schedule variances can 
still be calculated, but the incomplete link- 
age between cost data and schedule data 
makes it very difficult (or impossible) to esti- 
mate the current cost EAC of the project. 

Control of Variances and the Role of the 
Systems Engineer. When negative vari- 
ances are large enough to represent a signifi- 
cant erosion of reserves, then management 
attention is needed to either correct the vari- 
ance, or to replan the project. It is important 
to establish levels of variance at which 
action is to be taken. These levels are gener- 
ally lower when cost and schedule baselines 
do not support Earned Value calculations. 

The first action taken to control an 
excessive negative variance is to have the 
cognizant manager or systems engineer in- 
vestigate the problem, determine its cause 
and recommend a solution. There are a 
number of possible reasons why variance 
problems occur: 

• A receivable was late or was unsatisfac- 
tory for some reason. 

• A task is technically very difficult and 
requires more resources than originally 
planned. 

• Unforeseeable (and unlikely to repeat) 
events occurred, such as illness, a labor 
strike, a fire or some other calamity. 

Although the identification of variances is 
largely a program control function, there is 
an important systems engineering role in 
their control. That role arises because the 
correct assessment of why a negative vari- 
ance is occurring greatly increases the 



71 



READINGS IN SYSTEMS ENGINEERING 



chances of successful control actions. This 
assessment often requires an understanding 
of the cost, schedule and technical situation 
that can only be provided by the systems 
engineer. 



Computing the Estimate at Completion 

EAC can be estimated at any point in the project. 
The appropriate formula depends upon the the 
reasons associated for any variances that may 
exist. If a variance exists due to a one-time 
event, such as an accident, then EAC = BUD- 
GET + ACEP - BCWP where BUDGET is the 
original planned cost at completion. If a variance 
exists for systemic reasons, such as a general un- 
derestimate of schedule durations, or a steady 
redefinition of requirements, then the variance 
is assumed to continue to grow over time, and 
the equation is: EAC = BUDGET X (ACWP/ 
BCWP). 

It is also possible that EAC will grow at a 
greater rate than estimated by the above equa- 
tion if there are a growing number of liens, ac- 
tion items or significant problems that will 
increase the difficulty of future work. Such fac- 
tors could be addressed using risk management 
methods . 

In a large project, a good EAC is the result of 
a variance analysis that may use a combination 
of these estimation methods on different parts of 
the WBS. A rote formula should not be used as a 
substitute for understanding the underlying 
causes of variances. 



Technical Performance Measures 

Status reporting and assessment of the 
system's technical performance measures 
(TPMs) complements cost and schedule con- 
trol. By tracking the system's TPMs, the 
project manager gains visibility into wheth- 
er the delivered system will actually meet its 
performance specifications (requirements). 
Beyond that, tracking TPMs ties together a 
number of basic systems engineering 
activities — that is, a TPM tracking program 
forges a relationship among systems analy- 
sis, functional and performance require- 
ments definition and verification and valida- 
tion activities. 



• Systems analysis activities identify the 
key performance or technical attributes 
that determine system effectiveness; 
trade studies performed in systems ana- 
lysis help quantify the system's perfor- 
mance requirements. 

• Functional and performance require- 
ments definition activities help identify 
verification and validation requirements. 

• Verification and validation activities re- 
sult in quantitative evaluation of TPMs. 

• "Out-of-bounds" TPMs are signals to re- 
plan fiscal, schedule and people re- 
sources; sometimes new systems analysis 
activities need to be initiated. 

Tracking TPMs can begin as soon as a base- 
line design has been established, which can 
occur as early as Phase B. A TPM tracking 
program should begin not later than the 
start of Phase C. Data to support the full set 
of selected TPMs may, however, not be avail- 
able until later in the project cycle. 

Selecting TPMs. In general, TPMs can be 
generic (attributes that are meaningful to 
each Product Breakdown Structure [PBS] 
element, like mass or reliability) or unique 
(attributes that are meaningful only to spe- 
cific PBS elements). The systems engineer 
needs to decide which generic and unique 
TPMs are worth tracking at each level of the 
PBS. The systems engineer should track the 
measure of system effectiveness (when the 
project maintains such a measure) and the 
principal performance or technical attri- 
butes that determine it, as top-level TPMs. 
At lower levels of the PBS, TPMs worth 
tracking can be identified through the func- 
tional and performance requirements levied 
on each individual system, segment, etc. 

In selecting TPMs, the systems engineer 
should focus on those that can be objectively 
measured during the project cycle. This mea- 
surement can be done directly by testing or 
indirectly by a combination of testing and 
analysis. Analyses are often the only means 
available to determine some high-level 



72 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



TPMs such as system reliability, but the 
data used in such analyses should be based 
on demonstrated values to the maximum 
practical extent. These analyses can be 
performed using the same measurement 
methods or models used during trade stud- 
ies. In TPM tracking, however, instead of 
using estimated (or desired) performance or 
technical attributes, the models are exer- 
cised using demonstrated values. As the 
project cycle proceeds through Phases C and 
D, the measurement of TPMs should become 
increasingly more accurate because of the 
availability of more "actual" data about the 
system. 

Lastly, the systems engineer should se- 
lect those TPMs that must fall within well- 
defined (quantitative) limits for reasons of 
system effectiveness or mission feasibility. 
Usually these limits represent either a firm 
upper or lower bound constraint. A typical 
example of such a TPM for a spacecraft is its 
injected mass, which must not exceed the ca- 
pability of the selected launch vehicle. 
Tracking injected mass as a high-level TPM 
is meant to ensure that this does not happen. 

Assessment Methods. The traditional 
method of assessing a TPM is by establishing 
a time-phased planned profile for it, and 
comparing the demonstrated value against 
that profile. The planned profile represents a 
nominal "trajectory" for that TPM taking 
into account a number of factors. These 
factors include the technological maturity of 
the system, the planned schedule of tests and 
demonstrations, and any historical exper- 
ience with similar or related systems. As an 
example, spacecraft dry mass tends to grow 
during Phases C and D by as much as 25 to 
30 percent. A planned profile for spacecraft 
dry mass may try to compensate for this 
growth with a lower initial value. The final 
value in the planned profile usually either 
intersects or is asymptotic to an allocated 
requirement (or contract specification). The 
planned profile method is the technical per- 
formance measurement counterpart to the 



Earned Value method for cost and schedule 
control described earlier. 



Examples ofHieh-Level TPMs for 
Planetary Spacecraft and Launch Vehicles 

High-level technical performance measures 
(TPMs) for planetary spacecraft include: 

• End-of-mission (EOM) dry mass 

• Injected mass (includes EOM dry mass, base- 
line mission plus reserve propellant, other 
consumables and upper stage adaptor mass) 

• Consumables at EOM 

• Power demand (relative to supply) 

• Onboard data processing memory demand 

• Onboard data processing throughput time 

• Onboard data bus capacity 

• Total pointing error 

Mass and power demands by spacecraft subsys- 
tems and science instruments may be tracked 
separately as well. 

For launch vehicles, high-level TPMs include: 

• Total vehicle mass at launch 

• Payload mass (at nominal altitude or orbit) 

• Payload volume 

• Injection accuracy 

• Launch reliability 

• In-flight reliability 

• For reusable vehicles, percent of value recov- 
ered 

• For expendable vehicles, unit production cost 
at the rc th unit. 



A closely related method of assessing a 
TPM relies on establishing a time-phased 
margin requirement for it and comparing 
the actual margin against that requirement. 
The margin is generally defined as the differ- 
ence between a TPM's demonstrated value 
and its allocated requirement. The margin 
requirement may be expressed as a percent 
of the allocated requirement. The margin 
requirement generally declines through 
Phases C and D, reaching or approaching 
zero at their completion. 

Depending on which method is chosen, 
the systems engineer's role is to propose 
reasonable planned profiles or margin re- 
quirements for approval by the cognizant 
manager. The value of either of these meth- 
ods is that they allow management by 
exception — that is, only deviations from 



73 



readings tn Systems engineering 



planned profiles or margins below require- 
ments signal potential future problems re- 
quiring replanning. If this occurs, then new 
cost, schedule and/or technical changes 
should be proposed. Technical changes may 
imply some new planned profiles. This is il- 
lustrated for a hypothetical TPM in Figure 
11(a). In this example, a significant demon- 
strated variance (i.e., unanticipated growth) 
in the TPM during design and development 
of the system resulted in replanning at time 
t. The replanning took the form of an in- 
crease in the allowed final value of the TPM 
(the "allocation"). A new planned profile was 
then established to track the TPM over the 
remaining time of the TPM tracking 
program. 

The margin management method of as- 
sessing is illustrated for the same example in 
Figure 11(b). The replanning at time t oc- 
curred when the TPM fell significantly below 
the margin requirement. The new higher 
allocation for the TPM resulted in a higher 
margin requirement, but it also immediately 
placed the margin in excess of that require- 
ment. 

Both of these methods recognize that the 
final value of the TPM being tracked is un- 
certain throughout most of Phases C and D. 
The margin management method attempts 
to deal with this implicitly by establishing a 
margin requirement that reduces the 
chances of the final value exceeding its allo- 
cation to a low number, for example, five per- 
cent or less. A third method of reporting and 
assessing deals with this risk explicitly. The 
risk management method is illustrated for 
the same example in Figure 11(c). The 
replanning at time t occurred when the 
probability of the final TPM value being less 
than the allocation fell precipitously into the 
red alert zone. The new higher allocation for 
the TPM resulted in a substantial improve- 
ment in that probability. 

The risk management method requires 
an estimate of the probability distribution 
for the final TPM value. Early in the TPM 
tracking program, when the demonstrated 



(a) Planned Profile Method 



T 
P 
M 



New 
Allocation 

Original 
Allocation 






.,-^> 


■ 




t . 

Margin 
at*d * 


* ^^^^ New 

* ^^^^ Planned 

*r^ Profile ^^ 

■^^ Original 
- Demonstrated Planned 

* Variance Profl!e 

Replanning 
Occurred Here 


c~ 

u 

r 
r 
e 
n 
t 

D 
a 

t 
e 



TIME 



(b) Margin Management Method 



T 
P 

M 



♦ 










Discontinuity 








^-"induced by shift 
.^s^ to new allocation 






^*- > >-»* 








Original ^^^fcj 










^^^■•A*.,.,^ 






Requirement 


r New Margin ^*~-m,_ 

Requirement ~^ 


















C 








u 








r 








r 








e 








n 






Replanning 


t 






Occurred Here 


D 

a 
t 




' 




e 





TIME 



(c) Risk Management Method 



1.0 



T 
P 
M 



Green Alert I 




''i! 



Note \Ithough red 
j eilow green alert zones 
are shown only m ic) 
corresponding zones 
apply to fa) andfbl 



TIME 



Figure 11 Three TPM Assessment Methods 



74 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



An Example of the Risk Management Method for 
Tracking Spacecraft Mass 

During Phases C and D, a spacecraft's injected mass 
can be considered an uncertain quantity. Estimates 
of each subsystem's and each instrument's mass are, 
however, made periodically by the design engineers. 
These estimates change and become more accurate 
as actual parts and components are built and 
integrated into subsystems and instruments and 
are integrated into spacecraft. Injected mass can 
also change during Phases C and D as the quantity 
of propellant is fine-tuned to meet the mission 
design requirements. At each point during 
development then, the spacecraft's injected mass is 
better represented as a probability distribution 
rather than as a single point. 

The mechanics of obtaining a probability 
distribution for injected mass typically involve 
making estimates of three points — the lower and 
upper bounds and the most likely injected mass 
value. These three values can be combined into 
parameters that completely define a probability 
distribution like the one shown in the figure below. 



Probability 
Density * ' 



Prob (Injected Mass 
s LV Specification 




- LV Specification 



Spacecraft Injected Mass, Kg 

The launch vehicle's "guaranteed" payload 
capability, designated the "LV Specification," is 
shown as a bold vertical line. The area under the 
probability curve to the left of the bold vertical line 
represents the probability that the spacecraft's 
injected mass will be less than or equal to the 
launch vehicle's payload capability. If injected mass 
is a TPM being tracked using the risk management 
method, this probability could be plotted in a 
display similar to Figure 11(c). 

If this probability were nearly one, then the 
project manager might consider adding more 
objectives to the mission in order to take advantage 
of the "large margin" that appears to exist. In the 
above figure, however, the probability is 
significantly less than one. Here, the project 
manager might consider descoping the project, for 
example, by removing an instrument or otherwise 
changing mission objectives. The project manager 
could also solve the problem by requesting a larger 
launch vehicle! 



value is based on indirect means of estima- 
tion, this distribution typically has a larger 
statistical variance than later, when it is 
based on measured data, e.g., a test result. 
When a TPM stays along its planned profile 
(or equivalently, when its margin remains 
above the corresponding margin require- 
ment), the narrowing of the statistical distri- 
bution should allow the TPM to remain in 
the green alert zone (in Figure 11(c)) despite 
its growth. The three methods represent 
different ways to assess TPMs and communi- 
cate that information to management, but 
whichever is chosen, the pattern of success or 
failure should be the same for all three. 

Relationship of TPM Tracking Program 
to the SEMP. The SEMP is the usual docu- 
ment for describing the project's TPM track- 
ing program. This description should include 
a master list of those TPMs to be tracked and 
the measurement and assessment methods 
to be employed. If analytical methods and 
models are used to measure certain high- 
level TPMs, then these need to be identified. 
The reporting frequency and timing of as- 
sessments should be specified as well. In de- 
termining these, the systems engineer must 
balance the project's needs for accurate, 
timely and effective TPM tracking against 
the cost of the TPM tracking program. The 
TPM tracking program plan, which elabo- 
rates on the SEMP, should specify each 
TPM's allocation, time-phased planned pro- 
file or margin requirement, and alert zones, 
as appropriate to the selected assessment 
method. 

Systems Engineering Process Metrics 

Status reporting and assessment of systems 
engineering process metrics provides addi- 
tional visibility into the performance of the 
"system that produces the system." As such, 
these metrics supplement the cost and sched- 
ule control measures discussed earlier. 

Systems engineering process metrics try 
to quantify the effectivity and productivity of 



75 



READINGS IN SYSTEMS ENGINEERING 



the systems engineering process and organi- 
zation. Within a single project, tracking 
these metrics allows the systems engineer to 
better understand the health and progress of 
that project. Across projects (and over time), 
the tracking of systems engineering process 
metrics allows for better estimation of the 
cost and time of performing systems engi- 
neering functions. It also allows the systems 
engineering organization to demonstrate its 
commitment to the TQM principle of con- 
tinuous improvement. 



arises from the insights they provide into the 
process that cannot be obtained from cost 
and schedule control measures alone. Over 
time, these metrics can also be a source of 
hard productivity data, which are invaluable 
in demonstrating the potential returns from 
investment in systems engineering tools and 
training. 

Examples and Assessment Methods. 

Table 2 lists some systems engineering pro- 
cess metrics to be considered. That list is not 



Selecting Systems Engineering Process 
Metrics 

Generally, systems engineering process 
metrics fall into three categories: those that 
measure the progress of the systems engi- 
neering effort, those that measure the qual- 
ity of that process, and those that measure 
its productivity. Different levels of systems 
engineering management are generally 
interested in different metrics. For example, 
a project manager or lead systems engineer 
may focus on metrics dealing with systems 
engineering staffing, project risk manage- 
ment progress and major trade study 
progress. A subsystem systems engineer 
may focus on subsystem requirements and 
interface definition progress and verification 
procedures progress. It is useful for each 
systems engineer to focus on just a few 
process metrics. Which metrics should be 
tracked depends on the systems engineer's 
role in the total systems engineering effort. 
The systems engineering process metrics 
worth tracking also change as the project 
moves through the project cycle. 

Collecting and maintaining data on the 
systems engineering process is not without 
cost. Status reporting and assessment of sys- 
tems engineering process metrics divert time 
and effort from the process itself. The system 
engineer must balance the value of each 
systems engineering process metric against 
its collection cost. The value of these metrics 



Function 


Systems Engineering 
Process Metric 


Cate- 
gory 


Requirements 
development and 
management 


Requirements identified vs. 
completed vs. approved 

Requirements volatility 

Trade studies planned vs. 
completed 

Requirements approved per 
systems engineering hour 


s 

Q 

s 

P 


Design and 
development 


Specifications planned vs. 
completed 

Processing of ECRs/ECOs 

Engineering drawings planned 
vs. related 


s 

Q 

s 


Verification and 
Validation ( V&V) 


V&V plans identified vs. 
approved 

V&V procedures planned vs. 
completed 

Functional requirements 
approved vs. verified 

V&V plans approved per 
systems engineering hour 

V&V procedures completed per 
systems engineering hour 

Processing of trouble reports 


s 
s 
s 
P 
P 
Q 


Reviews 


Processing of Review Item 
Discrepancies (RIDs) 

Processing of action items 


Q 
Q 



S = Progress, or schedule-related 
Q = Quality-related 
P = Productivity 

Table 2 Systems Engineering Process Metrics 

intended to be exhaustive. Because some of 
these metrics allow for different interpreta- 
tions, each NASA Center needs to define 
them in a common-sense way that fits its 
own processes. For example, each Center 



76 



MANAGEMENT ISSUES IN SYSTEMS ENGINEERING 



needs to determine what it meant by a 
completed versus an approved requirement, 
or whether these terms are even relevant. As 
part of this definition, it is important to 
recognize that not all requirements, for 
example, need be lumped together. It may be 
more useful to track the same metric sepa- 
rately for each of several different types of 
requirements, for example. 

Quality-related metrics should serve to 
indicate when a part of the systems engi- 
neering process is overloaded and/or break- 
ing down. These metrics can be defined and 
tracked in several different ways. For 
example, requirements volatility can be 
quantified as the number of newly identified 
requirements, or as the number of changes to 
already-approved requirements. As another 
example, engineering change request (ECR) 
processing could be tracked by comparing 
cumulative ECRs opened versus cumulative 
ECRs closed, or by plotting the age profile of 
of open ECRs, or by examining the number of 
ECRs opened last month versus the total 
number open. The systems engineer should 



apply personal judgment in picking the 
status reporting and assessment method. 

Productivity-related metrics provide an 
indication of systems engineering output per 
unit of input. Although more sophisticated 
measures of input exist, the most common is 
the number of systems engineering hours 
dedicated to a particular function or activity. 
Because not all systems engineering hours 
cost the same, an appropriate weighing 
scheme should be developed to ensure 
comparability of hours across systems engi- 
neering personnel. 

Displaying schedule-related metrics can 
be accomplished in a table or graph of 
planned quantities vs. actuals. With quality- 
and productivity-related metrics, trends are 
generally more important than isolated 
snapshots. The most useful kind of assess- 
ment method allows comparisons of the 
trend on a current project with that for a 
successful completed project of the same 
type. The latter provides a benchmark 
against which the system engineer can judge 
personal efforts. 



77 



SPACECRAFT SYSTEMS ENGINEERING 



Spacecraft Systems Engineering: 
An Introduction to the Process at GSFC 

by Tony Fragomeni and Mike Ryschkewitsch 



N 9 3 - &4#8 3 



/ 



Systems engineering means different things 
to different people. Some say it applies only 
to one spacecraft or a total mission. Others 
say it applies only to hardware and not to 
software, but that assumption is flatly 
wrong. Still others say it is electrically 
oriented while others say it is mechanically 
oriented; that depends upon whether you 
talk to an electrical or a mechanical engi- 
neer. Systems engineering is often equated 
with systems management and systems 
design. Some would reduce it to a purely ana- 
lytical process and others would reduce it to 
mere hands-on physical integration. 

Systems engineering is all of these and 
much more. It encompasses such terms as the 
system approach, system analysis and sys- 
tems integration. It includes systems re- 
quirements analysis and functional analysis. 
The Goddard Space Flight Center's Code 400 
Project Manager's Handbook says it is "one of 
the most important technical efforts of a pro- 
ject and . . . assures the design adequacy of 
the complete system to meet the stated 
user/experimenter requirements for a mis- 
sion." These efforts include both the ground 
and flight segments, launch vehicle inter- 
face, and the end-to-end data system from 
collection of raw data on orbit to reduced 
data on the ground ready for analysis. The 
handbook says: "The Systems Manager of a 
project serves as Chief Engineer and 
provides a focal point for the systems engi- 
neering effort throughout all phases of the 
project." 

As a succinct definition, that is as good as 
any but not really very helpful in under- 
standing the systems engineering process, 
especially in the development of spacecraft. 
The concept becomes much clearer and richer 
when we ask why we need systems engineer- 
ing, who a systems engineer is, what the 



systems engineer does and what are some of 
the products. 

But first we can state what systems engi- 
neering is not. It is not one, single, isolated 
process. The whole process of systems engi- 
neering is better described as an attitude . . . 
a plan of attack ... a way of thinking. Con- 
sider, for example, the difference between a 
chemist adding one ingredient to a fixed 
solution to achieve a predictable result, and a 
doctor who must consider a variety of uncer- 
tain and ever changing physical and emo- 
tional factors in the diagnosis and treatment 
of a patient. 

As shown in Figure 1, systems engineer- 
ing is not a process that is easily contained in 
a single manual or cookbook. Rather, it is the 
systematic use of many time-tested and 
experience-verified disciplines, tools and 
human resources needed to identify, define 
and solve problems. Which tools to use or 
expertise required depends not only on the 
mission under consideration but also the 
phase or stage of the project. The process 
thus demands a great deal of versatility and 
flexibility. 

Finally, systems engineering is not 
always one individual or even one organiza- 
tion. Instead, it is a flexible process which 
makes the development and design meet the 
requirements and constraints imposed by the 
user and the system environment. It is a 
process characterized by multiple starts and 
stops, frequent shifts and alternate ap- 
proaches, as opposed to a clear-cut path or a 
simple recipe for success. 

Systems engineering is clearly a dynamic 
process that cannot and will not be pinned 
down into a simple procedural formula. This 
process, however, is generally the same for 
different kinds of projects. In these times of 
increasingly constrained budgets, it is 



PRECEDING PAGE BLANK NOT FILMED 



1 



m&JlJLumMmuML am 



79 



READINGS IN SYSTEMS ENGINEERING 



Conduct 
Parametric, 
Functional, 
Timeline, 
and trade-off 
Analyses to 
Evaluate Each 
Approach 



Optimum approach 
selected on baaiB of 
performance, 
schedule and cost, 
configuration and 
compatibility of 
system physical, 
functional, and 
technical Interfaces 
and demonstrated 



Phase A 



Mission Objectives 
Operational 

Requirements 
Data Products 
Requirements 
Environ me nta 
Programmatics 

Constraints 



Review & analysis 
to establish top - 
level system 
•■equirements which 
define S/C.L/V, 
Orbit 

Require menu. 

Data Product 

Requirements 



Candidate 

Systems 

Designs 



Baseline system 
conceptual design 
defined: 

• Functional & 
Operational 
Descriptions 

• Block Diagrams 

• Hardware/ 
Software 
Characteristics 

• Physical 
Characteristics 



Phase B 



Conduct analyses to 
refi ne the 
conceptual design 

• Parametric 

• Functional 

• Trade off 

• System 



Output. 

• System 
Architecture 

• Allocation of 
Resources 

• Performance 
Requirements 

• Margins 



Flight Segment 

Performance 

Specification: 

• Mission Performance 
Requirements 

• System Level 
Performance, 
Operations, and 
Interface Requirements 

• Key Subsystem 
Performance 
Requirements 

• Verification 
Requirements 

• GSE Requirements 
« Design Guidelines 



Ground Segment 
Specification: 

• Timeline 

• System Acceptance 



Output 
Subsystem 
and 

Component 
Performance 
and Design 
Specifl cations 
and Drawings 



Conduct 
Analyses to 
Refine the 
System Design: 

• Parametric 

• Functional 

• Trade off 
» System 

• Subsystem 

• Component 



Phase C/D/E 



MRR/MRDand 
Ground Data 
Processing 
Requirements 



, , . 1 

I STRD | | Ground | 

i I f Data I 

f I f Processing | 

I I i . i 



n 



Hardware, 

Software, 
Fabrication, 
Assembly, 
Integration 
and Test 



Analysis of 
Design, Test 
and 

Inspection 
Data 



Design 
Changes 



Performance 
Verification 
Metric 



Launch 



Mission 
Operations 



On Orbit 
E ngineerinfj 
Checkout 



Figure 1 SE Process in the Evolution of a Mission 



incumbent upon the systems engineer to 
optimize the systems design and to do things 
efficiently and not just effectively. Systems 
engineers are called upon to identify the 
risks in increasingly complex projects, and 
then attempt to minimize the impact of those 
risks. In very complex spacecraft, which are 
expected to perform delicate and ultrasophis- 
ticated functions, a minor intrasystem per- 
turbation can have a major performance 
impact across multiple systems. Systems 
engineering is a disciplined technical ap- 
proach that forces us to do our homework up 
front and early on, to uncover problems be- 
fore they become showstoppers. Although we 
cannot conclusively test for everything, we 
are expected to identify and verify realities 
and adequate margins. 

In a sense, we have always had systems 
engineering in NASA, but it may aptly be 
termed "informal." Certainly, we recall engi- 
neers and managers who had a big-picture 
perspective, looking at all functions and how 



they interrelate, but more often than not, 
their trade studies were on isolated scratch 
pads and the logic kept in their heads or in a 
desk drawer. You can almost hear them say: 
"This is the way we've always done it." 

Sometimes this informal system worked, 
especially on small, relatively simple pro- 
jects. But as the spacecraft became more 
complex and development time elongated, a 
more formal process of systems engineering 
emerged. In simple terms, it starts with func- 
tional analysis and leads to functional 
requirements and then design requirements. 
It starts at the top and works down, fully 
documented at each step and traceable. The 
greater the complexity and duration of a pro- 
ject, the greater the penalty for not catching 
errors early on, and the greater the need for a 
well understood and well documented pro- 
cess. The SE process should ensure that all 
fixes be made before the start of hardware 
fabrication when the cost of fixes is relatively 
inexpensive. To wait until later is costly, and 



80 



SPACECRAFT SYSTEMS ENGINEERING 



it can be prohibitive at the interval between 
acceptance testing and launch. 

SE ROLES AND RESPONSIBILITIES 

The main objective in systems engineering is 
to devise a coherent total system design capa- 
ble of achieving the stated requirements. 
Requirements should be rigid. However, they 
should be continuously challenged, rechal- 
lenged and/or validated. The systems engi- 
neer must specify every requirement in order 
to design, document, implement and conduct 
the mission. Each and every requirement 
must be logically considered, traceable and 
evaluated through various analysis and 
trade studies in a total systems design. Mar- 
gins must be determined to be realistic as 
well as adequate. The systems engineer must 
also continuously close the loop and verify 
system performance against the require- 
ments. 

The fundamental role of the systems 
engineer, however, is to engineer, not man- 
age. Yet, in large, complex missions, where 
more than one systems engineer is required, 
someone needs to manage the systems engi- 
neers, and we call them "systems managers." 
Systems engineering management is an 
overview function which plans, guides, moni- 
tors and controls the technical execution of a 
project as implemented by the systems engi- 
neers. As the project moves on through 
Phases A and B into Phase C/D, the systems 
engineering tasks become a small portion of 
the total effort. The systems management 
role increases since discipline subsystem 
engineers are conducting analyses and 
reviewing test data for final review and 
acceptance by the systems managers. 

Requirements 

The name of the game in systems en- 
gineering is requirements. The statement, 
traceability and eventual verification of re- 
quirements is probably the most important 
aspect of systems engineering. Requirements 



are initially derived from user needs, i.e., the 
customer. It is understood that for each re- 
quirement there is an associated margin that 
must continually be challenged. As the pro- 
ject nears completion, the amount of avail- 
able margin is expected to decrease since the 
margins are updated based on "actuals." 

• Functional Requirements provide a 
description of the functions and subfunc- 
tions required to conduct the mission. 
These are generally derived from func- 
tional analysis and allocation. 

• Performance Requirements or source 
requirements define what the system 
must accomplish and how well the system 
must perform. These requirements are 
initially derived from user needs and 
requirements statements and refined 
through requirements analyses and trade 
studies. They are defined during each 
application of the systems engineering 
process based on outputs from previous it- 
erations of the process, program decisions 
and updates to user requirements. They 
provide the metrics that must be verified 
through appropriate analyses, demon- 
strations and tests. 

• Derived Requirements are lower level 
(subsystem and components) performance 
requirements resulting from an analysis 
of the user stated performance require- 
ments and the definition of functional re- 
quirements. These derived requirements 
are used by subsystem discipline engi- 
neers in characterizing the subsystem 
performance requirements necessary to 
ensure the attainment of the user-stated 
performance or source requirements. 

• Reflected Requirements are require- 
ments placed on other subsystems or on 
the higher level systems which must be 
provided to each of the subsystems to en- 
sure proper performance of the subsystem 
and the eventual attainment of the user 



81 



READINGS IN SYSTEMS ENGINEERING 



stated performance or source require- 
ments. 
• Design Requirements are described by 
drawings, material lists, process descrip- 
tions and other supporting documents for 
the fabrication, production or manufac- 
turing of a system element. These are 
generally derived from the synthesis of a 
solution for one or more higher level re- 
quirements. 

The systems engineer must be able to 
demonstrate the traceability of each require- 
ment through each level, right up to the 
contractually binding source requirements. 
User requirements are determined and 
refined during Phase A studies. A host of 
considerations are made in order to produce 
the best set of "integrated performance 
requirements," considering technical perfor- 
mance, first as mitigated by cost and sched- 
ule. Systems engineers should not and do not 
make cost and schedule decisions, especially 
in the later phases, but in Phases A and B, 
cost and schedule are trade-off parameters 
that must be considered in determining the 
best course of action. 

Phase A - Mission Analysis 

In Phase A Mission Analysis, systems engi- 
neers will translate user needs or goals into a 
quantifiable set of functional requirements 
that can be translated into design require- 
ments. User requirements are defined as a 
"set of objectives" that are quantified in 
broad terms and basic functions. The user 
should also state performance measures in 
terms of preferences as well as trade evalua- 
tion criteria. The systems engineers will 
conduct functional, parametric and system 
analyses to define and refine mission 
requirements and to generate alternative 
candidate system designs. Baseline system 
conceptual designs should emerge as design 
drivers are identified, as well as high risk 



areas and offsets. Common system drivers 
include size, weight, power, data rate, com- 
munications, pointing, orbital altitude, 
mission operations coverage (geometry and 
timing) and scheduling. Trade-off studies are 
conducted to balance the requirements, but 
even the optimal technical approach may not 
be the best way when the design is evaluated 
in terms of cost, schedule and risks. Since all 
projects will undergo cost, schedule and tech- 
nical perturbations during development, it is 
imperative that a good system be developed. 
However, contractual, legal and fiscal re- 
quirements dictate that the technical ap- 
proach must be agreed to by the start of 
Phase C/D. The overall system architecture 
must be established during Phase A; this 
includes the apportionment of functions be- 
tween the flight and ground segments. It is 
imperative that proper studies and analyses 
be done to result in the correct structure 
since this affects the remainder of the project 
up through the operations phase. 

Phase A outputs or products include a 
Phase A Report, a Science Requirements 
Document, preliminary Instrument Interface 
Requirements Documents, cost, schedule and 
a Project Initiation Agreement (PIA). The 
Phase A Report includes functional and oper- 
ational descriptions, hardware and software 
distribution, design requirements, system/ 
subsystem descriptions, mission description, 
a preliminary work breakdown structure 
(WBS) and recommendations for Phase B. 
The Phase A Report must have sufficient 
data to answer questions such as these: 

• Do the conceptual design and operational 
concept meet the overall mission objec- 
tives? 

• Is the design technically feasible? 

• Is the level of risks acceptable? 

• Are schedules and budget within the 
specified limits? 

• Do preliminary results show this option 
to be better than all others? 



82 



SPACECRAFT SYSTEMS ENGINEERING 



PHASE B - DEFINITION PHASE 

Assuming that each crucial question is an- 
swered affirmatively during Phase A, the 
systems engineer will continue development 
of the system requirements by conducting 
more detailed analyses to refine the baseline 
system conceptual design. These Phase B 
tasks must result in technical requirements 
and operational functions that are reflected 
in Interface Control Documents, perfor- 
mance and design specifications and state- 
ments of work that are used to produce the 
hardware during Phase C. 

Specifications are defined as "a descrip- 
tion of the technical requirements for a mate- 
rial or product that includes the criteria for 
determining whether the requirements are 
met." Basically, there are four types of speci- 
fications: 

• Functional - describes only the ultimate 
end use; contractor is responsible. 

• Performance - describes quantitatively 
what it must do; contractor is responsible. 

• Design - what to make and how to make 
it; buyer is responsible. 

• Levels of Effort - used only for support 
services. 

The statement of work (SOW) describes 
the work needed to carry out the entire mis- 
sion as well as how and where the work is to 
be done. The work breakdown structure 
(WBS) is used for reporting progress, perfor- 
mance and engineering evaluations. The 
WBS will structure the family of specifica- 
tions and drawings resulting from the pro- 
gressive stages of systems engineering. The 
final result of the Phase B process is a system 
definition in sufficient depth of detail to 
allow beginning the detailed design process 
for each of the individual subsystems. 

PHASE C/D - EXECUTION PHASE 

During Phase C/D, systems engineering 
provides technical oversight during design, 



development, test and evaluation to ensure 
that timely and appropriate intermeshing of 
all technical disciplines are reflected in the 
overall design. Technical performance re- 
quirements and margins are continually 
reaffirmed through analyses and tests dur- 
ing this phase. Phase C/D outputs or pro- 
ducts will also include a variety of analytical 
and test reports on hazards, faults, single- 
point failures and failure modes for "what-if ' 
or worst-case scenarios. Trade-offs and other 
analyses continue but in greater detail at the 
subsystem and component levels to ensure 
proper conversion of performance require- 
ments into the design and into the hardware. 

PHASES E AND F - PRE-MISSION AND 
MISSION OPERATIONS 

Phases E and F, Pre-mission and Mission 
Operations, also involve systems engineer- 
ing, although to a lesser degree since the 
most important SE work is done early on. 
However, the final verification of a space 
flight, system can only be done in flight, on- 
orbit. The systems engineering team is full 
time with the flight operations team during 
initial on-orbit engineering checkout and on 
call during mission operations. The final 
product is the "On-Orbit Engineering Perfor- 
mance Report" which measures mission 
performance against requirements. This 
document becomes useful in subsequent pro- 
jects, especially if it contains lessons learned. 
Finally, the systems engineer's job is only 
completed when the user has the final deliv- 
ered product, e.g., scientific data, in hand. 

SYSTEMS ENGINEERING ANALYSES 

Systems engineering is a highly analytical 
process. Throughout the entire project (not 
just at the beginning) the systems engineer 
will conduct or review numerous analyses to 
establish strong performance and design 
parameters as well as to continually evalu- 
ate design approaches and options. A 
systems engineer is expected to establish 



83 



READINGS IN SYSTEMS ENGINEERING 



performance parameters and margins, verify 
them with test and inspection data, and com- 
pare the actual to the predicted. Everything 
must be "what-ifed" to the lowest necessary 
level, not just once but continually, so that 
there are few if any surprises. 

One tool used by the systems engineer is 
functional analysis. This is a top-to-bottom 
effort done in all phases and at every hard- 
ware level. The systems engineer takes a 
performance requirement (function) at one 
hardware level of assembly and, after 
thorough analysis, determines the optimum 
distribution and implementation of the re- 
quirement at the next lower hardware level. 
Functional analysis is also used to determine 
whether a particular function is best accom- 
plished in flight or on the ground. Functional 
analysis results in a hierarchical structure 
(i.e., architecture) that progressively divides 
and allocates how a function is to be 
accomplished, down to the lowest common 
denominator. This is extremely useful in 
deciding where to cut the interface, especial- 
ly in view of verification, accountability and 
jurisdictional (i.e., contractual) boundaries. 

Another top-to-bottom systems engineer- 
ing analysis done in all phases is the require- 
ments flowdown and allocation analysis. 
This can be described as an equitable, attain- 
able and realistic distribution of system- level 
performance requirements and resources, 
including margins, to successively lower 
levels of hardware assemblies. To verify the 
validity and distribution of tolerances and 
margins, continued analysis and review are 
required throughout the project. This starts 
during Phase A and continues through every 
on-orbit checkout. Distribution should be 
compared to actuals, and estimates should be 
quantified as a function of design maturity. 

Trade-off studies and analyses also define 
margins and identify potential problem 
areas. They are done on all systems and for 
all technical disciplines to select the configu- 
ration that best satisfies a user requirement. 
Alternative technologies are examined to 
satisfy functional and design requirements, 



including those with moderate to high risk. 
Trade-off studies also support make-or-buy 
decisions and help manage technical risk. In 
Phases A and B, they establish system archi- 
tecture and configuration. In Phase C/D, 
they evaluate alternate solutions in sys- 
tem/subsystem/component design. After 
critical design review (CDR), however, trade- 
off studies are conducted only during the 
evaluation of design changes or responses to 
failures. All factors that affect the function 
or requirement must be studied: perfor- 
mance, reliability, safety, cost, risk, sched- 
ule, maintainability, servicing, power, 
weight, thermal, complexity, etc. 

System parametric and sensitivity model- 
ing and analyses are used to develop confi- 
dence that a design satisfies higher level 
requirements, and to provide traceability of 
functional, performance and design require- 
ments. This is accomplished by varying a 
particular performance parameter between 
its established worst-case limits and as per- 
turbed by worst-case environmental stresses 
to determine the resultant effect on succes- 
sively higher assembly levels or performance 
parameters. These analyses can serve as a 
primary vehicle for conducting trade studies 
and to assess the whole system effectiveness 
of synthesized design options and alterna- 
tives. Like all other studies and analyses, 
these analyses are done during all phases 
and are updated based on actual test data. 

Risk Assessment 

Risk assessment is approached from different 
but related directions. During Phases A and 
B, the systems engineer will want to do suffi- 
cient analyses to ensure that the technical 
approach is valid and that any new develop- 
ments or state-of-the-art items and their risk 
offsets have been identified. During Phase 
C/D, sufficient analysis must assure that 
performance requirements and margins are 
adequate and are in fact satisfied. Through- 
out the entire project life cycle, risk assess- 
ment and particularly Failure Mode Effects 



84 



SPACECRAFT SYSTEMS ENGINEERING 



Analyses and fault tree analyses should be 
used as design tools to enhance the overall 
system design and make it immune to fail- 
ures, both hardware and human. 

Risk assessment is the identification and 
evaluation of the impact upon the technical 
performance of those system elements that 
appear to possess an inherent probability of 
failing to meet some critical performance or 
design requirement essential for the success- 
ful accomplishment of the intended mission. 
Systems engineering identifies the potential 
failures, establishes margins and quantifies 
the risk. Risk taking gets down to knowing 
what your margins are and how they are dis- 
tributed. How do you know what the margins 
are? By doing lots of analyses and backing 
them up with tests. Two of the best tools are 
Failure Mode Effects Analysis (FMEA) and 
hazards analyses. 

The FMEA assures that the failure modes 
of a system are known and can be addressed 
in an orderly fashion. Initially the analysis 
must identify all critical functions and the 
effects of the impairment of those functions 
on mission success. Following this, a detailed 
component and system interaction study is 
conducted to determine all the ways a func- 
tion could be impaired, the effect on mission 
success and how such an impairment could 
be detected. The impact of these failures and 
the probability of occurrence must be evalu- 
ated in light of the user requirements and 
the desired level of reliability. 

The FMEA is also used in compiling the 
system-level fault tree used by the flight op- 
erations team (FOT) during mission oper- 
ations. The fault tree is a listing of every 
plausible anomaly or failure that may occur 
on orbit. It starts out with the detection of 
the anomaly or failure as observed by the 
FOT via telemetry. It then provides a road 
map used by the FOT in isolating the cause 
of the anomaly and taking the required cor- 
rective action or operational work-around so 
that the mission can proceed. The fault tree 
analysis and the development of the FMEA 
should be done together. 



Systems safety hazards analyses are also 
considered a systems engineering function. 
The intent of the systems safety hazards ana- 
lysis is to identify design deficiencies that 
could directly — or indirectly through opera- 
tor error — result in personnel injury or 
damage to the flight hardware. In this case, 
any potential hazards that could result in 
death, severe injury or illness must be elimi- 
nated. The impact of a major system loss or 
damage must be evaluated in light of user 
requirements. 

Operations hazards analyses look at 
possible failures occurring during testing, 
handling and transportation that could jeop- 
ardize the hardware or personnel. All catas- 
trophes and critical hazards resulting in 
death, severe injury or illness, or major 
system loss or damage must be eliminated. 
Marginal hazards may be tolerated if they 
can be rationally justified and accepted. 

REVIEWS, PERFORMANCE ASSESSMENT 
AND VERIFICATION 

The systems engineer is best advised to start 
early and stay late in reviewing and assess- 
ing performance requirements and the asso- 
ciated verification methods employed to 
prove the requirement has been satisfied. 
Reviews must be done at all levels. Non- 
advocate reviews (NARs) should be conduct- 
ed at the end of Phase B to evaluate the 
technical, cost and schedule approach for 
accomplishing the mission. System-level 
reviews and lower-level hardware design and 
test reviews should be conducted continually. 
Peer reviews are vital at all levels and must 
be conducted by "looking at the drawings and 
not the viewgraphs." Trend analysis is need- 
ed on all critical performance parameters, 
from box level acceptance through on-orbit to 
enable the early identification of potential 
problem areas. Technical performance mea- 
surement (TPM) is one proven method of as- 
sessing compliance to requirements and the 
level of technical risk. TPM is defined as the 
continuing analysis, test and demonstration 



85 



READINGS IN SYSTEMS ENGINEERING 



of the degree of anticipated and actual 
achievement of selected technical measures 
and performance parameters. TPM involves 
analysis of the differences among the 
achievement to date, current estimate and 
the required or target value for the par- 
ameter. 

Summary and Some advice 

Systems engineering is much more than a 
one-person job. It is best described as "the 
technical conscience of a project." As such, 
systems engineering is a highly structured 
and disciplined engineering process that cuts 
across all technical disciplines to ensure 
interface design compatibility, both inter- 
system and intrasystem. It organizes at the 
system level — not at the subsystem level, 
where compromises may be made. It estab- 
lishes performance requirements and 
margins. Systems engineering evaluates the 
validity of hardware through analysis and 
review of test data. It identifies risk and 
offers approaches for the project manager to 
eliminate or reduce the impact. One eye of 
the system engineer is on how the end prod- 
uct is used during mission operations; the 
other is focused on how analyses and tests 
can prove it can do the job within acceptable 
margins. Both eyes work in tandem, togeth- 
er, clearly and in focus. Remember: 
1. Perform sound systems analyses and de- 
sign; consider all options. 



2. Don't box yourself in with unnecessary 
and undue constraints. 

3. Exercise extreme'care in system design, 
especially incorporating appropriate (to 
the risks) redundancy and provisions for 
late design changes and on-orbit oper- 
ational work-arounds, and factor in test- 
ing ability. 

4. Institute the discipline to ensure pains- 
taking attention to details — great and 
small. 

5. Maintain a total dedication to quality — 
quality is designed in, it does not acci- 
dentally happen. 

6. Ensure rigorous pre-launch testing to es- 
tablish that requirements are in fact 
satisfied, and any workmanship or mar- 
ginal designs are uncovered. 

7. Insist on inexhaustible diligence in test- 
ing — allow an unexplained or random 
failure only after all reasonable and 
practical steps to isolate are taken. 

8. Attempt to design backwards — satisfy 
mission requirements first. 

9. Conduct extensive reviews — look at the 
drawings, not viewgraphs. 

10. Have adequate documentation to know 
where you are going, how you are get- 
ting there, where you have been and 
when you are there. 

11. Have an open door policy to foster strong 
intra-project technical communications. 

12. Ensure total openness regarding prob- 
lem identification and resolution. 



86 



SE&I AND MANAGEMENT 

Systems Engineering & Integration and Management 
for Manned Space Flight Programs /£3S*7fe 

by Owen Morris 




The development of systems engineering and 
program management in NASA manned 
space programs has grown in a largely un- 
coordinated manner over the last 30 years. 
However, the systems and practices that 
have been developed form a proven pattern 
for successfully integrating large, technical- 
ly complex programs executed in several geo- 
graphical locations. This development has 
not been recorded in a comprehensive man- 
ner, and much of the reasoning behind the 
decisions made is not obvious. 

For the purposes of this discussion, sys- 
tems engineering is defined as the inter- 
disciplinary engineering that is necessary to 
achieve efficient definition and integration 
of program elements in a manner that meets 
the system-level requirements. Integration 
is defined as the activity necessary to de- 
velop and document the systems' technical 
characteristics, including interface control 
requirements, resource reporting and analy- 
sis, system verification requirements and 
plans, and integration of the system 
elements into the program operational 
scenario. 

This paper discusses the history of SE&I 
management of the overall program archi- 
tecture, organizational structure and the 
relationship of SE&I to other program orga- 
nizational elements. A brief discussion of the 
method of executing the SE&I process, a 
summary of some of the major lessons 
learned, and identification of things that 
have proven successful are included. 

History 

NASA, then the National Advisory Commit- 
tee for Aeronautics (NACA), participation in 
the management of major aerospace pro- 
grams began shortly after World War II with 
the advent of the X series research aircraft. 



In these projects, essentially all of the tech- 
nical responsibility was delegated to one of 
the Centers, which were primarily expert in 
the technical area being explored (i.e., aero- 
dynamics, stability, control and structures) 
but did not have experts in the development 
of hardware. Accordingly, NACA entered 
into agreements with the Air Force or Navy 
to manage the actual development of the 
aircraft. The NACA Centers focused their 
direction on the technical requirements and 
performance characteristics to be demon- 
strated by the aircraft. The contractor's 
responsibility was similar to that for the 
development of any aircraft, and the contrac- 
tor usually furnished test pilots for early 
demonstration flights. 

With the formation of NASA and the 
start of major manned space programs, it 
was necessary for NASA to develop the capa- 
bility to manage complex development 
activities. Very little SE&I capability exist- 
ed within the functional organizations of the 
NASA Centers. As a result, SE&I expertise 
was developed within each of the program 
offices. In particular, the Gemini program 
office was set up with autonomous capability 
to manage SE&I and direct the development 
contractor. 

With the advent of the Apollo program, 
SE&I was again managed from the project 
offices at the development centers. The 
project offices used specialized technical 
capability from the Center functional orga- 
nizations and prime contractors and initiat- 
ed the practice of hiring support contractors 
to assist in implementing SE&I. After the 
Apollo I fire, a review committee was estab- 
lished to determine the cause of the fire and 
recommend modifications to the program. 
One of the recommendations made was that 
NASA acquire a technical integration and 
engineering support contractor to assist in 



87 



READINGS IN SYSTEMS ENGINEERING 



accomplishing SE&I activity. The Washing- 
ton program office selected Boeing as the 
contractor and managed the contract for this 
activity; however, a large portion of the work 
force was located at the Centers. The con- 
tractor's responsibilities included moni- 
toring the development and operational 
activities at the Centers, forming integrated 
assessments of the activity, and making 
recommendations to the program director for 
improvements. As the program matured, the 
contract focus was changed, and the contrac- 
tor provided a significant number of person- 
nel to directly support the Centers in SE&I 
and systems development activities. 

With the initiation of the Space Shuttle 
program and the adoption of the Lead Center 
concept, it was decided to manage the Level 
II integration activity, including SE&I, by 
providing a small management core within 
the program office and using many of the 
Centers' functional organizations to provide 
technical support in a matrix fashion. At the 
Johnson Space Center (JSC), the lead person 
from the functional organization was gener- 
ally a branch head or an assistant division 
chief. JSC had a relatively large staff to 
draw from to provide the specific technical 
expertise and the level of effort needed to 
accomplish a given task. 

The Space Station Freedom program was 
started using the Space Shuttle program as a 
model. As the Lead Center, JSC managed in- 
tegration. Later, the Level II function was 
moved near Washington, D.C., under the 
deputy program director, and an indepen- 
dent contractor was brought in to assist the 
integration process. The Space Station Free- 
dom management organization will be dis- 
cussed in more detail in the next section. 

Program Management 
Organizational Structure 

A single NASA Center largely managed ear- 
ly NASA manned space flight programs, 
which allowed for a relatively simple organi- 
zational structure to accomplish program 



integration. JSC, then called the Manned 
Space Center, managed both development 
and flight operational aspects of the Mercury 
and Gemini programs with the checkout and 
preflight testing being performed by support 
elements at Cape Canaveral. 

Apollo became organizationally more 
complex (Figure 1). The spacecraft develop- 
ment was managed by JSC, the launch vehi- 
cle development by Marshall Space Flight 
Center (MSFC), the prelaunch activities by 
Kennedy Space Center (KSC) — by then an 
independent NASA Center — and the flight 
operations by JSC. In all of these programs, 
the responsibility for the development of the 
flight hardware was delegated to the 
Centers, and the interfaces between projects 
were intentionally kept as simple as possi- 
ble. The Washington office, under direction 
of the program director, was responsible for 
overall direction of the program including 
budgetary allocations, congressional rela- 
tions, and management of development 
issues between the project offices at the 
different Centers. The actual integration 
activity (SE&I) was coordinated by a series 
of panels and working groups in which 
individuals from the Washington program 
office served as either chairperson or 
members, with the program director over- 
seeing the activity. In the early programs 
(Mercury and Gemini), this activity was the 
responsibility of a single Center, and the 
Washington office was coordinated in an 
informal manner, but by the end of the 
Apollo program, the management of the pan- 
el and working group activity was relatively 
formal. In all of these programs the Center 
directors took an active part and personally 
felt responsible for the technical excellence 
of the work performed by their Centers. This 
intercenter involvement was accomplished 
primarily through the management council 
and major program reviews where Center 
directors personally participated in major 
decisions. 

In part of the Apollo program, the 
Washington office retained the responsibil- 



88 



C-£ 



SE&I AND MANAGEMENT 



Level I 



Apollo Program 
Director 



Gen. S. Philips 



Level II 



Apollo Spacecraft 
Program Office 



G.Low 



Satum V 
Office 



H. Rudolph 



Launch 
Operations 



R. Petrone 



Flight 
Operations 



C.Kraft 



Level III 



CSM 
Project 



LM 
Project 



S-I Stage 
Project 



S-II 
Project 



S-IV 
Project 



Instrument 

Unit 

Project 



Figure 1 Apollo Program Management Organization 



performing the SE&I activity with the actu- 
al work being led by Bellcom, a division of 
Bell Laboratories. Ultimately, this approach 
was abandoned, at least partly because much 
of the Center director's responsibility was 
lost, and an adversarial relationship be- 
tween the program director and the Center 
organizations developed. The execution of 
the SE&I was returned to the Centers with 
management and coordination of intercenter 
activities achieved through the use of work- 
ing groups, panels and management re- 
views. 

At the outset of the Space Shuttle pro- 
gram (Figure 2), the management of SE&I 
was markedly changed. Some of the more im- 
portant changes were adoption of the Lead 
Center management concept in which one of 
the participating Centers was delegated the 
management of program level integration 
including SE&I activities; the adoption of a 
configuration with functional and physical 



interfaces of much greater complexity; and 
the employment of one of the major hard- 
ware development contractors as the inte- 
gration support contractor. The complex 
interfaces made SE&I activity voluminous 
and involved and required the commitment 
of a larger percentage of the program re- 
sources to this activity. 

The Space Station Freedom program was 
structured so that the interface activity 
between the work packages was even more 
complex than that of the Shuttle program. 
Initially, the Lead Center approach to SE&I 
activity was adopted, but the implementa- 
tion was not effective. As a result of recom- 
mendations made by study groups and the 
committee reviewing the Challenger acci- 
dent, it was decided to transfer the responsi- 
bility for program integration activity, 
including SE&I, to the deputy program 
director in Reston, Virginia, and to bring on 
a contractor to provide program integration 



89 



READINGS IN SYSTEMS ENGINEERING 



Level I 



Space Shuttle 
Program Director 



M. Malkin 



Level II 



Space Shuttle 
Program Manager 



R.F. Thompson 



Systems 
Integration 



0. Morris 



Management 
Integration 



R. Machell 



Operations 
Integration 



D. Cheatham 



1 



Resources and 

Schedules 

Integration 



R. Young 



Integration 



J. Lovingood 



MSFC 
Space Shuttle 
Projects Office 



R. Lindstrom 



Level III 



Orbiter 
Project 



A. Cohen 



SSME 
Project 



J.R. Thompson 



External Tank 
Project 



J. Odom 



SRB 
Project 



G. Hardy 



Figure 2 Space Shuttle Program Management Organization 



support (Figure 3). Contractors having sig- 
nificant hardware development contracts 
were excluded from the contract competition. 
The first approach was to provide detailed 
management of SE&I activity by the Reston 
civil service personnel with the integration 
contractor providing support in executing 
the activity. Additionally, it was thought 
that much of the technical integration could 
be accomplished by having the work package 



contractors negotiate the definition and 
execution of much of the detailed integration 
process directly between themselves. This 
proved ineffective, however, because there 
was no clear lead responsibility and no clear 
way to resolve differences. As a result, 
because of the complexity of program in- 
tegration and the lack of in-depth backup ca- 
pability, this management approach has not 
been completely effective. 



90 



SE&I AND MANAGEMENT 



Level I 



Space Station Freedom 
Program Director 



Level II 



Space Station Freedom 
Deputy Program Director 



Deputy Program Manager 

for 

Integration (JSC) 



Element 

Integration 

Manager 

(MSFC) 



System 

Integration 

Manager 

(JSC) 



Systems 

Engineering & 

Analysis 

Group 



Management 

Integration 

Group 



Deputy Program Manager 

for 
Utilizations & Operations 



International 

Programs 

Group 



Program 

Control 

Group 



Program 

Assessments 
Office 



Level m 



Work 
Package 1 

(MSFC) 



Work 
Package 2 

(JSC) 



Work 

Package 3 

(GSFC) 



Work 

Package 4 

(LeRC) 



KSC 



ZL 



Langley 



Figure 3 Space Station Freedom Program Management Organization (1990) 



Recently, it was decided to give the inte- 
gration support contractor direct responsibil- 
ity for the integration of the program but 
without authority to directly manage the 
work packages or their contractors. In an 
attempt to obtain more in-depth capability, 
the program director and deputy program 
director decided to execute the systems in- 
tegration portion of the SE&I activity at two 
of the Centers with the deputy director for 
integration physically located at one of the 
Centers. Since these functions were still re- 
tained organizationally within the program 
office, they were under the control of the dep- 
uty program director and, at the same time, 



had the advantage of drawing from the in- 
depth technical capability residing at the 
Centers. Simultaneously, the integrating 
contractor's work force at the Centers was 
increased in both responsibilities and num- 
bers. 

Growing Program Complexity 

One of the major factors determining the 
efficiency of the integration of a program is 
the methodology used to delegate the engi- 
neering and development responsibilities to 
the project offices at the Centers. It has been 
found that less complex organizational 



91 



READINGS IN SYSTEMS ENGINEERING 



structures and simple interfaces are ex- 
tremely important to allow efficient manage- 
ment of SE&I activities. Each of NASA's 
manned space programs has been organiza- 
tionally more complex than its predecessor 
and has had more complex interfaces. In both 
the Mercury and Gemini programs, the 
flight elements were divided into two parts, 
spacecraft and launch vehicle, and the phys- 
ical and functional interfaces between the 
two were quite simple. The induced environ- 
mental interfaces were somewhat more com- 
plex but readily amenable to experimental 
and analytical determination. 

The Apollo program involved a major in- 
crease in program complexity. The space- 
craft was divided into two project offices and 
the launch vehicle was divided into four 
project offices. By assigning the four launch 
vehicle projects to the same Center (MSFC), 
the integration between launch vehicle 
stages could be accomplished at the Center 
level. Similarly, both spacecraft projects 
were assigned to one center (JSC) for the 
same reason. The physical and functional in- 
terfaces between the spacecraft and launch 
vehicle, and hence between Centers, was rel- 
atively simple. In a 1971 paper titled "What 
Made Apollo a Success," George Low stated: 
"Another important design rule, which we 
have not discussed as often as we should, 
reads: minimize functional interfaces be- 
tween complex pieces of hardware. Examples 
in Apollo include the interfaces between the 
spacecraft and launch vehicle and between 
the command module and the lunar module. 
Only some 100 wires link the Saturn launch 
vehicle and the Apollo spacecraft, and most 
of these have to do with the emergency detec- 
tion system. The reason that this number 
could not be even smaller is twofold: redun- 
dant circuits are employed, and the electrical 
power always comes from the module or 
stage where a function is to be performed. 
For example, the closing of relays in the 
launch vehicle could, in an automatic abort 
mode, fire the spacecraft escape motor. But 
the electrical power to do this, by design, 



originates in the spacecraft batteries. The 
main point is that a single person can fully 
understand this interface and can cope with 
all the effects of a change on either side of the 
interface. If there had been 10 times as many 
wires, it probably would have taken a hun- 
dred (or a thousand?) times as many people 
to handle the interface." However, the oper- 
ational complexity of the Apollo vehicle 
demanded a more extensive integration 
activity between the Centers and for the first 
time posed the problem of accomplishing 
detailed technical coordination between 
Centers. 

One of the basic tenets of the Space 
Shuttle was to have an integrated vehicle 
that would recover the most expensive ele- 
ments of the system for reuse. This led to a 
design concept that placed a great majority 
of the electronics and major components of 
the main propulsion systems in the orbiter. 
This design concept led to very large 
increases in interface complexity between 
the program elements and, more important- 
ly, between the Centers. For instance, the 
number of electrical wires running between 
the external tank and the orbiter was more 
than an order of magnitude greater than 
between the spacecraft and launch vehicle of 
Apollo, and for the first time, major fluid 
systems ran across the interfaces. This 
represented a formidable increase in the ef- 
fort required to successfully accomplish the 
SE&I activity. As previously noted, a new 
program management structure (Figure 1) 
was adopted to accommodate the increase. 
The accomplishment of program-level SE&I 
was given to a "Lead Center." The program 
director at Headquarters was still respon- 
sible for program budgetary control, Con- 
gressional relations and a technical staff 
sufficient to assure that the program tech- 
nical activity was being properly implement- 
ed. At JSC, which was the Lead Center for 
the Shuttle program, a Level II program 
office was established totally separate from 
the Level III orbiter project office located at 
the same Center. 



92 



SE&I AND MANAGEMENT 



The development of the flight hardware 
was delegated to four project offices with the 
orbiter office located at JSC, as mentioned 
above, and the other three— the Space Shut- 
tle main engine office, the external tank 
office, and the solid rocket booster office- 
located at MSFC. In addition to the hard- 
ware development project offices, a pre- 
launch processing office was formed at KSC. 
All of the project offices reported to the Level 
II program manager for all programmatic 
direction except budget allocation, which 
was retained by the program director at 
Headquarters. 

The SE&I activity was delegated to the 
systems integration office located within the 
JSC Level II office. The orbiter contractor, 
Rockwell International, was selected to be 
the integration support contractor, but to 
increase objectivity, the integration activity 
was made a separate exhibit to the contract 
and technical direction was delegated to the 
Level II systems integration office. The 
MSFC Space Shuttle project office appointed 
an integration manager to manage the 
integration of the Marshall Space Shuttle 



projects and to serve as the primary interface 
to the Level II systems integration office. 

The flight hardware developmental dele- 
gation of the Space Station Freedom 
program was formulated in an even more 
complex manner (Figure 4). End-to-end 
developmental responsibility for each of the 
major functional systems was delegated to 
one of four project offices called work pack- 
age offices in the Space Station Freedom 
program. Responsibility for assembling and 
delivering the flight hardware was broken 
down by launch elements, again assigned to 
one of the work package offices. Each of these 
launch elements incorporates components of 
most of the distributed systems, neces- 
sitating the transfer of an extremely large 
number of hardware and software items 
between work packages prior to their deliv- 
ery to the Government. This resulted in 
another major increase in the complexity of 
the program-level SE&I process and directly 
contributed to the difficulty of implementing 
a satisfactory SE&I process in the Space 
Station Freedom program. 



Level II 
Support 




Figure 4 Space Station Integration Job 



93 



READINGS IN SYSTEMS ENGINEERING 



SE&I Scenario 

As a program develops from concept to oper- 
ational status, the characteristics of the 
SE&I activity vary greatly. Early in the pro- 
gram, conceptual SE&I is intimately in- 
volved in defining systems that will meet the 
overall program objectives and in evaluating 
the relative merits of each. This is usually 
accomplished in NASA manned programs by 
the civil service organizations, often in con- 
cert with Phase A/B contracts with industry. 
After the general systems specification has 
been developed and a detailed evaluation of 
systems concepts has been completed, SE&I 
provides a lead in the preparation of the pro- 
curement specifications for the Phase C and 
D activities and is usually directly involved 
in the source selection process. After award 
of the Phase C and D contracts and final 
selection of the design approach chosen for 
implementation, SE&I is responsible for pre- 
paring system-level technical specifications, 
which define the performance requirements 
to be satisfied by each of the major program 
elements. SE&I then develops the system 
characterization process to be used (dis- 
cussed in detail later) and starts an initial 
analysis cycle. The results of this cycle are 
extremely important in verifying the valid- 
ity of the system technical specifications and 
providing a technical basis for conducting 
the Program Requirements Review (PRR). 
After completion of the PRR and updating of 
the technical specifications, SE&I starts the 
definition of the interface control document 
tree and the initial document drafts. An- 
other system characterization cycle is start- 
ed, based on the updated specifications and 
the hardware and software concepts chosen 
to assess the adequacy of the proposed pre- 
liminary design approach. 

By this time in the program, the ad hoc 
organizational structure should be well in 
place and functioning routinely. The commu- 
nication and management overview provided 
by this structure of working groups, panels 



and reviews is central to accomplishing hori- 
zontal integration among the project offices 
and is discussed in more detail later. 

In preparation for the preliminary design 
review (PDR), SE&I defines the minimum 
content required in the PDR data packages 
and is responsible for preparing system-level 
documents supporting the Integrated 
System PDR. During the PDR process, SE&I 
representatives participate in the project- 
level reviews with particular emphasis on 
the compliance of the project to the system- 
level requirements. During the Integrated 
System PDR, emphasis is placed on assuring 
that the preliminary designs proposed by the 
projects are compatible across the interfaces 
and that the integrated system is capable of 
meeting the operational requirements of the 
program. The SE&I organization is inti- 
mately involved with the evaluation and dis- 
position of review item discrepancies (RIDs) 
that are submitted during the review. 

As a result of the PDR process, changes to 
the requirements and modifications to the 
preliminary design of the elements are incor- 
porated. A new characterization cycle is then 
initiated to evaluate the compatibility be- 
tween the modified requirements and pro- 
posed system capabilities. At this time, the 
drafts of the interface control documents are 
expanded and quantitative detail is added to 
assure that the documents are mature 
enough to become baseline requirements in 
the program. This maturation process inevi- 
tably results in the identification of physical 
and functional disconnects among the ele- 
ments and in a significant number of 
changes to the baseline. 

In a similar manner, the verification 
plans of the elements and the integrated 
system are refined and baselined. The 
responsibility for executing the test and ana- 
lysis required by the integrated system ver- 
ification plan are delegated to appropriate 
organizations that prepare detailed plans for 
accomplishing the assigned portions of the 
verification. 



94 



SE&I AND MANAGEMENT 



Detailed mission operational scenarios 
and timelines are prepared by the operations 
organizations, and the operations and SE&I 
organizations jointly conduct an analysis of 
the system capabilities to support the sce- 
narios. Concurrently, the acceptance test 
and prelaunch operations requirements and 
plans are prepared and delegated for execu- 
tion. 

In preparation for the critical design 
review (CDR), another system characteriza- 
tion cycle is performed, based upon the 
detailed design of the elements. This cycle 
typically uses mature models to synthesize 
the hardware and software systems and also 
incorporates the results of tests performed to 
that time. SE&I participates in the conduct 
of the CDR in a manner similar to that of the 
PDR. After completion of the CDR, the 
system requirements and design changes re- 
sulting from the CDR are incorporated into 
the documentation, and another complete or 
partial system characterization cycle vali- 
dates the decisions made during CDR. 

After CDR, the primary activity of the 
SE&l organization is to analyze test results 
and conduct analysis to verify the capability 
of the system that is being manufactured. 
Particular emphasis is given to verifying the 
interface characteristics of the elements as 
defined by the interface control documents. 
This activity directly supports the prepara- 
tion for the design certification review 
(DCR), and provides interface information 
necessary to allow acceptance of the system 
hardware and software by the Government. 

The DCR is conducted similarly to the 
PDR and CDR but addresses the as-built 
hardware and software. Successful comple- 
tion of the DCR certifies the acceptability of 
the as-built elements and the ability to be 
integrated into an overall system that will 
satisfy the initial program operational re- 
quirements. Final operational certification 
of the system is obtained by a combination of 
the DCR process and analysis of information 
obtained during early flight operation of the 
system. 



The SE&I organization's participation 
throughout the program development cycle 
supports operational planning and real-time 
operations. SE&I is the repository of corpo- 
rate knowledge of the details of system 
capability, which is vital to the effective and 
efficient operation of the system. 

relationship of se&i to other 
Program functions 

To effectively accomplish the SE&I task, the 
SE&I management organization must main- 
tain good communications and obtain the 
support of other program office organiza- 
tions. Some of the more important interac- 
tions are discussed below. 

Configuration Management. The in- 
teraction between SE&I and configuration 
management is particularly strong. As the 
developers and keepers of the systems speci- 
fications, SE&I has an interface with the 
configuration management function that is 
extremely active throughout the life of the 
program. The SE&I office recommends the 
baselining of the technical requirements as 
they become sufficiently mature and then 
serves as the office of primary responsibility 
for defining and evaluating most of the pro- 
posed changes to this baseline. The SE&I of- 
fice, after proper coordination throughout 
the integration function, also recommends 
the processing of noncontroversial changes 
outside of the formal control board meetings, 
where appropriate. This significantly re- 
duces the board's workload and conserves the 
time of the key managers who are members 
of the change control board. As significant is- 
sues are referred to the board, SE&I presents 
an analysis of the issues involved and makes 
appropriate recommendations for action. 

Program Control. SE&I supports the 
program control function in the development 
of program schedules and budgets. The key 
to making this support effective is the use of 
the SE&I logic networks and estimates of the 



yo 



READINGS IN SYSTEMS ENGINEERING 



manpower required to accomplish the activi- 
ties. Because of SE&Fs interdisciplinary 
nature, SE&I can assist in planning activi- 
ties in many areas of the program. 

Early in the program, SE&I helps define 
the content and schedule milestones of each 
project to permit coherent development of 
project-level schedules and cost estimates. 
SE&I also provides program control with the 
engineering master schedules (EMS) and 
associated budget estimates for incorpora- 
tion in the overall schedule and budget 
system. SE&I also works with program 
control in planning major program reviews; 
provides technical leadership in conducting 
the reviews; and frequently chairs the 
screening groups and pre-boards. 

Operations. In all of the NASA manned 
space programs to date, the SE&I function 
has been managed in an organization differ- 
ent from the operations definition and plan- 
ning function. Although this is undoubtedly 
the best choice in the later phases of the pro- 
gram, it may result in a less thorough incor- 
poration of operational requirements in the 
systems specifications and other SE&I pro- 
ducts early in the program. It may be desir- 
able to combine the management of SE&I 
and operations in the same office early in the 
program and then separating them later, 
perhaps at the completion of the preliminary 
design review. The stated reason for separat- 
ing the functions in the past has been that 
they serve as a check and balance on each 
other; however, the separation also discon- 
nects the detailed interfaces between the two 
functions. 

SR&QA. The interactions between SE&I 
and the system reliability and quality assur- 
ance (SR&QA) functions depend on how 
responsibility for executing the program is 
delegated. If a large part of the SR&QA 
activity is accomplished within the SR&QA 
organization, SE&I is used as a reservoir of 
information or to perform specific tasks as 
requested by SR&QA. However, if the 



SR&QA office is responsible for setting the 
requirements for SR&QA activities and for 
evaluating the outcomes — while other orga- 
nizations are delegated the responsibility for 
executing the work— then SR&QA must de- 
fine and obtain baseline approval of task re- 
quirements, monitor execution of the task by 
SE&I, and evaluate the results to assure sat- 
isfactory achievement. 

The former mode of operation was exem- 
plified during the early Apollo program, in 
which the SR&QA activities were largely ac- 
complished within the SR&QA office using 
basic engineering information obtained from 
SE&I and other program organizational 
offices. Later in the Apollo program, the 
second mode of execution was adopted; the 
engineering offices, primarily SE&I, actual- 
ly performed the work and made a first-level 
analysis before formally transmitting the 
results to SR&QA for authentication. This 
latter method was considered more effective 
primarily because problems and discrepan- 
cies were often discovered by the originating 
engineering office and corrected even before 
the task was completed. 

SE&I Execution 

Techniques developed in past NASA manned 
programs have proven effective and have 
become an integral part of implementing 
SE&I activities. The following paragraphs 
describe, in no particular order, some of the 
most important techniques in planning and 
implementing new programs. 

Importance of SE&I Early in a Pro- 
gram. In the early stages of complex 
programs, comprehensive SE&I support 
helps determine the architecture to be used 
to delegate project responsibility. This is 
accomplished by dividing the program into 
the next lower level of management, the pro- 
ject offices. The primary outputs are compre- 
hensive and clear program requirement 
specifications, identification of major pro- 
grammatic interfaces, development of the ad 



96 



SE&I AND MANAGEMENT 



hoc SE&I management structure, definition 
of operating concepts, and preparation of 
initial specifications for the hardware to be 
delegated to each project office. 

The SE&I organization is responsible for 
managing technical integration both verti- 
cally between different levels of the man- 
agement organizations and horizontally 
across the organizations at each level. To 
efficiently achieve both dimensions of inte- 
gration, it is necessary to develop logic 
diagrams of the major SE&I activities to be 
accomplished by each of the organizational 
elements and then to determine the interre- 
lations between them. By developing these 
diagrams and playing them against different 
organizational structures, it is possible to 
evaluate the proposed organizations in 
simple terms and easily define the inter- 
actions between the organizational ele- 
ments, thus helping to choose the most 
efficient management structure. The impor- 
tance of the logic diagrams will be discussed 
later. 



Development and Use of Ad hoc Inte- 
gration Structure. To manage the defini- 
tion and implementation of the SE&I 
activities in manned space programs, NASA 
has developed an effective ad hoc organiza- 
tional structure. The structure consists of a 
series of reviews, panels and working groups 
that address the definition and management 
of integration functions throughout the pro- 
gram. Each organization has members who 
represent all of the organizations interested 
in the particular integration function being 
managed. In the Space Station Freedom pro- 
gram, the working group structure is formed 
by technical disciplines and distributed 
systems, such as Guidance, Navigation and 
Control, Robotics, and Loads and Dynamics. 
The panels are formed to address specific 
programmatic management areas (i.e., as- 
sembly requirements and stage definition, 
system design integration, and element de- 
sign integration) that span a number of orga- 
nizations. The reviews are formed to address 
relatively broad program areas as shown in 
Figure 5. 



Program Management 
Integration 



Engineering 



Integration 
Management 



Mission 
Integration 



Element 
Integration 



System 
Integration 



Figure 5 Space Station Freedom Technical Review Structure (1990) 



97 



READINGS IN SYSTEMS ENGINEERING 



Each organization is responsible for de- 
veloping the integration plan in its area of 
responsibility, monitoring the execution of 
the tasks, identifying problem areas, and 
either resolving them or submitting them to 
the overall program management structure 
for resolution. Although these organizations 
by their nature do not perform work, the 
members, by working back through their 
functional organizations, greatly influence 
the work being accomplished in their par- 
ticular area of expertise. As rapport develops 
between members, many potential problems 
and issues are identified and resolved with- 
out being referred to formal management 
decision channels. In addition, the quality of 
the work materially improves. This ad hoc 
organizational structure also provides obvi- 
ous places for program elements to present 
any issue for deliberation and resolution. All 
of the panels and working groups support 
each review as needed, and submit their 
open issues to the most appropriate review 
for resolution. 

The reviews address broad issues and 
serve as a communication channel between 
the panels and the working groups. Since the 
reviews cover all of the panels and working 
groups, they provide an excellent way of 
assessing and recommending to manage- 
ment the interdisciplinary priorities of the 
program. 

Chairpeople of the panels and working 
groups are the most qualified individuals 
available in a particular discipline. Only sec- 
ondary consideration is given to selecting a 
person from a specific organizational ele- 
ment. As a result of their recognized stature, 
the chairpeople provide leadership, which 
makes their recommendations and decisions 
more credible. The panels and working 
groups also call in outside expertise when 
needed, but such outside inputs are filtered 
by the panels and working groups before 
making a recommendation to the reviews or 
other management organizations. 



Internal vs. Matrix SE&I Staffing. As 
already noted, SE&I has been staffed and 
accomplished in different ways in different 
NASA manned programs. In the early 
manned space programs, the personnel 
required to accomplish the SE&I activity 
were assigned directly to the program and 
project offices. During the Apollo and Shut- 
tle programs, the program office had only the 
people necessary to manage the SE&I activ- 
ity, and most of the work was accomplished 
by technical experts assigned from the 
Centers' functional organizations in a 
matrix fashion. Although each method has 
its advantages and disadvantages, the ma- 
trix approach generally has more advan- 
tages in that manpower can be increased or 
decreased as needed by pulling support from 
the matrix organizations without reassign- 
ing the people involved. The primary disad- 
vantage is that the leader of a particular 
area does not report functionally to the pro- 
gram or project office, which means that the 
line of direction is not as strong. The 
importance of this negative factor, however, 
is inversely proportional to the working 
relationship between the organizations. In 
the Space Shuttle program, this relationship 
and the matrix approach worked well. In 
other programs, the relationship was not as 
good and direction through the matrix was 
less effective. On occasion, program man- 
agement appointed all panel and working 
group chairpeople from the program office 
staff, giving less regard to the individual's 
personal qualifications. This led to a marked 
decrease in the stature of the ad hoc 
structure, which then resulted in a lack of 
support from the functional organizations 
and a decrease in the quality of the integra- 
tion activity and products. As in many areas 
of SE&I, effective implementation relies 
heavily on the quality of the leadership and 
the maintenance of free and open communi- 
cations among the organizations involved. 



98 



SE&I AND MANAGEMENT 



Logic Networks. As the NASA manned 
space programs have become increasingly 
complex, it has become difficult to define the 
specific content and tasks needed to accom- 
plish the SE&I function. Central to the de- 
velopment of a comprehensive SE&I plan is 
the development of detailed logic networks, 
which form the basis for planning, executing 
and evaluating the SE&I activities. 

As used in the Space Shuttle program, 
logic networks covered all of the SE&I activi- 
ties that had to be accomplished by all 
elements of the program organization. Thus, 
these networks were able to interrelate 
SE&I activities both vertically and horizon- 
tally throughout the program management 
structure. The basic summary logic net- 
works were developed for the entire program 
duration, to identify all major activities 
required as a function of time, and were 
instrumental in developing cost and man- 
power forecasts for the entire duration of the 
program. Detailed logic networks were then 
prepared for the near-term in the Shuttle 
program for 12 months, identifying in 
greater detail the specific activities to be 
accomplished by each organizational ele- 
ment during that period. The networks were 
revised every six months to extend the detail 
planning horizon; in addition, the summary 
networks were reviewed and modified as 
needed on an annual basis. The logic 
networks were a primary input to the devel- 
opment of the engineering master schedules 
discussed in the next paragraph. 

Engineering Master Schedules (EMS) 
and Associated Dictionary. The activities 
identified in the SE&I integration logic net- 
works were then assigned to specific organi- 
zations for execution and presented as a 
schedule for each organization involved. By 
using a numbering system for the activities, 
the logic network and the schedule could be 
easily correlated. The schedules allowed cost 
and manpower estimates to be prepared for 
each organization and provided an excellent 



2^ 

means of determining status and managing 
activities in real time. 

Associated with the EMS, a dictionary 
was prepared with an entry for each activity. 
Each entry identified all input information 
required to allow the accomplishment of the 
activity; described the contents of the pro- 
ducts; and identified the primary user of 
each product, the scheduled completion date, 
and the person responsible for preparing the 
product. The EMS and the dictionary were 
the primary tools for defining and communi- 
cating SE&I activities throughout the entire 
program structure. 

As would be expected, the content of the 
EMS changes character over the life of the 
program and accordingly, requires various 
technical capabilities over time. Early in the 
program, the design activities involve a 
large number of trade studies and the devel- 
opment of synthesis tools to be used in evalu- 
ating the capabilities of the proposed design. 
As the program matures and the design so- 
lidifies, the activities become more involved 
with exercising the system models, conduct- 
ing tests and analyzing data. As the flight 
phase approaches, the activities are pre- 
dominated by operational considerations, in- 
cluding the development of operational data 
books, mission requirements, certification of 
system readiness, and support of mission 
planning and real-time mission operations. 

System Characterization Process. A 

major SE&I activity throughout the program 
life span is the assessment of the capability 
of the system to meet specified requirements. 
In the NASA manned space program, this 
has been accomplished in an analytic sense 
by synthesizing the vehicle characteri- 
zations in the form of either models or 
simulations, and then developing detailed 
performance characterizations by exercising 
the models against selected mission time- 
lines and significant mission events. 

The methodology used to perform the sys- 
tem synthesis is central to the development 



99 



READINGS IN SYSTEMS ENGINEERING 



of the logic networks and schedules described 
earlier. An examination of the system usual- 
ly reveals scenarios useful in conducting the 
overall system evaluation; after selecting 
the most desirable scenario, it forms the nu- 
cleus of the overall SE&I logic. In the Space 
Shuttle program, the scenario chosen was (1) 
develop the necessary models and simula- 
tions; (2) determine the structural modal 
characteristics; (3) determine the loads on 
each of the system elements; and (4) perform 
stress analysis of the system when subjected 
to these loads. Using this scenario it was rel- 
atively easy to define and interrelate the 
SE&I activities of other disciplines, such as 
GN&C, propulsion, and thermal, among 
others. After defining all of the required ac- 
tivities, a document was prepared to identify 
the models to be used, and the mission events 
to be analyzed and to define the configura- 
tion to be used. The sequence described 
above formed an analysis cycle of a specific 
configuration subjected to specific operation- 
al requirements. In the Shuttle program, it 
was termed an integrated vehicle baseline 
characterization cycle (IVBC). As previously 
described in the SE&I scenario, several char- 
acterization cycles are needed during the 
program: as the program matures, the cycles 
have additional synthesis detail, more de- 
finitive configuration information, and bet- 
ter operational information. 

At the completion of each of the charac- 
terizations cycles, system deficiencies are 
identified and modifications to either the 
system specifications or the requirements 
are made. For program management pur- 
poses, it is usually convenient to schedule 
the completion of one of the characterization 
cycles to occur just before each of the major 
program-level review milestones. 

Program Reviews. SE&I has a large 
input to each of the program-level reviews, 
such as system requirements review, pre- 
liminary design review, critical designre- 
view, design certification review, and flight 
readiness reviews. As mentioned above, com- 



pletion of one of the system characterization 
cycles is an excellent indicator of whether 
the system design meets the specified 
requirements. The engineering master 
schedule gives a graphic representation of 
whether the integration progress is being 
achieved. Reports produced by the SE&I ac- 
tivity, such as resource allocation status and 
margins, interface control document status, 
design reference mission maturity, and sys- 
tem operational data books indicate the 
maturity of the element participation in the 
system-level SE&I process. 

Design Reference Missions. Most of the 
manned space programs had to be capable of 
performing a relatively large number of di- 
verse missions, and the specifications are 
written to allow hardware and software sys- 
tems and elements that are flexible enough 
to satisfy all of the missions. For analytical 
purposes, however, it is convenient to define 
and adopt one or more design reference mis- 
sions (DRMs) that stress all of the systems 
capabilities to a significant extent. The 
DRMs are used as the primary mission re- 
quirements in the system characterization 
cycles, and in evaluating the ability to meet 
performance specifications. In addition to 
evaluating the baselined configuration 
against the DRMs, other specification 
requirements are evaluated by the accom- 
plishment of specific analyses or tests, as 
necessary. 

The DRMs also allow the user community 
to evaluate whether the system is capable of 
meeting specific user needs and whether 
these needs are specifically in the system 
specifications. The DRM is used by mission 
planners to determine the system's capabil- 
ity of performing any specific mission under 
consideration. 

Verification. Verification plays a major 
role in program planning and in the ultimate 
cost of the system. Although most of the 
verification is delegated to projects, SE&I is 
responsible for identifying the overall 



100 



SE&I AND MANAGEMENT 



verification requirements and specific 
system-level verification tests and simula- 
tions, which frequently require specialized 
facilities and significant amounts of system 
hardware and software. Since these system- 
level verification tests are frequently com- 
plex and expensive, planning for them needs 
to start very early in the program. The 
system-level verification network is devel- 
oped as an integral part of the program SE&I 
logic networks and is baselined early in the 
program. 

Final verification of some system require- 
ments can only be accomplished in the real 
flight environment, and these are demon- 
strated in early operations before final certi- 
fication of system operational capability is 
accomplished. It is also important to inte- 
grate the system-level verification planning 
and the operations planning to promote the 
maximum synergism possible between sys- 
tem verification and operational training. 

In manned space programs, all of the 
major system level verification tests have 
been assigned to program or functional orga- 
nizational elements other than SE&I for 
implementation. This has helped to assure 
that the management of SE&I can remain 
objective in the evaluation of overall certifi- 
cation adequacy. 

DCR Process. One of the most signifi- 
cant activities of SE&I its role in the certifi- 
cation of the system design prior to the start 
of the flight operations and then later, prior 
to committing the system to operating 
throughout the entire design envelope. SE&I 
is instrumental in setting the overall re- 
quirements for the DCR and is directly re- 
sponsible for the system-level portion of the 
review. This process becomes the final major 
system characterization cycle, using a syn- 
thesis of the as-built vehicle hardware and 
software capabilities and results of tests and 
analyses. DCR results also form the basis for 
the system operational data books that are 
used to plan and conduct the operational 
phase of the program. The DCR requires that 



all system requirements be evaluated 
against all of the as-built system capabil- 
ities, and where possible, the system mar- 
gins are quantified to assist the operations 
organization in planning and conducting 
flight operations. 

ICD Development. As the program 
management organizational structure is 
determined and responsibility for developing 
hardware and software is delegated, it is nec- 
essary to start the development of the 
interface control document (ICD) tree, which 
identifies each required ICD and the content 
to be presented. As previously noted, the di- 
vision of program activities to minimize the 
number and complexity of interfaces has a 
strong influence on the overall program cost 
and the ability of the program to meet sched- 
ules. The early development of strawman 
ICD trees can greatly assist in optimizing 
the overall program management structure. 
As the program progresses and the system 
configuration becomes better defined, the 
content of each ICD is developed in more de- 
tail and ICD working groups are formed to 
quantify the environmental, physical, func- 
tional and operational characteristics in 
detail. In most manned programs, the ICDs 
have been baselined at a relatively early 
point in the program and have usually con- 
tained a large number of TBDs (to be 
determined). After baselining the ICDs, 
working groups continue their work to arrive 
at specific values for each of the TBDs and to 
continually assess the adequacy of the ICDs 
as the design matures. 

The ICDs are primary documents at each 
program review and provide a basis for eval- 
uating the adequacy of the items being 
reviewed to satisfactorily function as part of 
the total system. 

Program Management Organization- 
al Structure. The efficiency of program 
management is greatly influenced by the 
organizational structure selected. Organi- 
zational structures that are compact and 



U» 



READINGS IN SYSTEMS ENGINEERING 



simple promote effective program manage- 
ment. Compactness is measured vertically 
by the number of levels of the program man- 
agement organization and horizontally by 
the number of organizations at each level. 
Each additional organizational element 
significantly increases the manpower and 
costs of achieving program integration, in- 
cluding SE&I. If each organizational ele- 
ment must interface with all others in the 
program, the number of interfaces increases 
rapidly as organizations are added. Adding 
management levels increases the complexity 
for delegating the execution of the program. 
This factor was evident to the Augustine 
Commission in their recent summary report 
The Future of the U.S. Space Program, in 
which they recommended that "multicenter 
projects be avoided wherever possible, but 
when this is not practical, a strong and inde- 
pendent project office reporting to Headquar- 
ters be established near the Center having 
the principal share of the work for that 
project; and that this project office have a 
systems engineering staff and full budget 
authority." 

In addition to keeping the management 
structure compact, it is also very important 
to select an architecture that divides the 
program into project offices, to enable simple 
interfaces between projects and delegation 
that is all-encompassing. All of the deliver- 
able hardware assigned to a given project 
should be the responsibility of that project to 
design and manufacture. In all manned 
programs prior to the Space Station, there 
was little transfer of hardware and software 
between projects — with one exception, that 
being the development flight instrumenta- 
tion in the Apollo program. 

Early in Apollo, a decision was made to 
establish a civil service project office to 
develop, procure and deliver the specialized 
development flight instrumentation to the 
prime spacecraft contractors for installation 
and integration in the early spacecraft. 
Coordination of the large volume of interface 
information required the development and 



maintenance of the complex bilateral sched- 
ules and support required. The complexity of 
providing support after the transfer of the 
instrumentation was a significant manage- 
ment problem throughout the entire time 
that the development flight instrument was 
used. In the Space Station Freedom program, 
considering the many hardware and soft- 
ware items that must be passed between 
work packages, it will be difficult to develop, 
coordinate and maintain all of the interface 
information required. 

Objectivity In Management. To pro- 
mote objectivity in managing SE&I, one of 
the basic ground rules in the Shuttle pro- 
gram was that the SE&I function would not 
be responsible for the development of any 
flight hardware or software products; thus, 
they had no conflicting pressure to make 
their development job easier at the expense 
of another organization. It was found that 
any bias, either perceived or real, immedi- 
ately brings the objectivity of management 
into question and rapidly destroys the confi- 
dence between organizational elements. 

Need for Good Communication. The 

nature of SE&I is such that most of the pro- 
gram elements and many other agency orga- 
nizations are involved in the execution of 
SE&I tasks. To facilitate accomplishment of 
the work, the importance of free and open 
communication cannot be overstressed. One 
of the ways of accomplishing this is "to live 
in a glass house." All decisions and, of equal 
importance, the logic behind those decisions 
must be communicated to all parties 
involved if they are to understand their role 
and how it fits into the overall picture. All 
parties must feel that their inputs are in- 
cluded in the decision-making process. This 
openness, and the accompanying feeling of 
vulnerability, is often not welcomed and 
requires faith and confidence between the 
organizations involved. The fact that mis- 
takes will be made must be accepted, and all 
organizations involved must constructively 



102 



SE&I AND MANAGEMENT 



assist in correcting them. Frequent open 
meetings of the ad hoc organizational ele- 
ments described above have proven to be an 
effective tool in developing rapport between 
peers and communicating information and 
decisions throughout the program structure. 
As noted earlier, however, such meetings 
become increasingly time-consuming and 
expensive as the complexity of the organiza- 
tional structure is increased. 

Importance of Margins. At the time 
programs are initiated, they are frequently 
sold on the basis of optimistic estimates of 
performance capability, cost and schedules. 
This often results in reducing margins to low 
levels at program initiation and solving 
early program costs and schedule problems 
by reducing weight, power and other re- 
source margins. As a consequence, margins 
are reduced to zero or negative values early 
in the program, making it necessary to modi- 
fy the program to either reduce requirements 
or introduce program changes that will 
reestablish positive margins. The recovery of 
the margin inevitably leads to significantly 
higher ultimate program costs in both 
dollars and days. Minimum life cycle costs 
are achieved by holding relatively large 
margins early in the program and then 
allowing them to be expended at a prudent 
rate during the program life cycle. 

Things That Have Worked Well 

In the management of the manned space pro- 
grams' SE&I activities, several approaches 
have been particularly successful. Some of 
the most important, have been discussed pre- 
viously but are readdressed here because of 
their assistance in the management of SE&I. 

Ad hoc Organizations. The use of ad 

hoc organizations to coordinate SE&I activi- 
ties has proven to be a valuable tool. The 
effectiveness of SE&I depends heavily on 
good communications between organizations 
and the assurance that all organizational 



elements take a common approach to the 
implementation of SE&I. This is difficult to 
accomplish using the normal program office 
organizations because they cannot directly 
address inter-organizational communica- 
tions and have difficulty managing across or- 
ganizational lines. The ad hoc organizational 
structure, on the other hand, is made up of 
specialists from each of the affected organi- 
zations, and their activities directly promote 
inter-organizational communications. Using 
this technique, technical peers can plan and 
monitor the execution of specific SE&I ac- 
tivities. When a resolution cannot be reached 
within the ad hoc organization, the issue can 
be referred to the proper program manage- 
ment office for decision. 

Standard Organization Structure 
within the Program and Project Offices. 

During the Apollo program, the program di- 
rector decided to have all of the program 
management offices at both Level II and 
Level III adopt a standard organization 
structure: five offices reported to the 
program manager and the same five offices 
reported to each project manager. This tech- 
nique assured that the work breakdown 
structure was similar for all offices, that 
direct counterparts could be identified in 
each of the offices, and that budget alloca- 
tions flowed down in a uniform and predict- 
able manner. All of these features resulted in 
less cross-linking between organizations and 
made the required program management 
activity more rational and predictable. 
Although the specific office structure chosen 
would be different for each program, having 
uniformity between the Level II and Level 
III management offices should be considered 
for future programs. 

System Characterization Cycles. Con- 
structing the SE&I plan and identifying the 
required tasks is a very complex under- 
taking in large programs. As previously 
described, it is best to have a well-defined 
core of activity that, when completed, will 



103 



READINGS IN SYSTEMS ENGINEERING, 



characterize the capability of the system to 
meet the specified requirements. Analysis of 
the results reveals deficiencies and allows 
modifications to either the requirements or 
the system design to be identified, thus as- 
suring an adequate margin of performance. 
Building on this core analysis cycle, it is rel- 
atively easy to plan the other SE&I tasks in 
a consistent manner, and create a complete 
characterization of the system capability. 

Matrix Management Organizational 
Approach. The concept of staffing the 
program management office with a small 
number of people who serve as managers 
only and then augmenting their capability 
with personnel drawn from other Center or- 
ganizations in a matrix fashion has signifi- 
cant advantages. Manpower can be brought 
in from the organizations only when it is 
actually needed, and the technical composi- 
tion can be changed over time to satisfy pro- 
grammatic needs. The quantity of personnel 
can be augmented to meet program needs, 
i.e., during major program reviews; the per- 
sonnel involved can be assured of a career 
path in their parent organization; and the 
individuals involved can continually replen- 
ish their expertise by participating in the 
R&D activities of their parent organization. 

This mode of operation has been quite 
successful and has demonstrated several 
additional advantages, such as reducing fric- 
tion and undesired competition between the 
program office and Center functional organi- 
zations, improving technical communica- 
tions across programs being implemented 
simultaneously, and providing an efficient 
way of phasing the development program 
into an operational role. In particular, the 
assignment of program-level SE&I to a Lead 
Center, coupled with the execution of this 
assignment using Center functional organi- 
zations in a matrix fashions, allows the pro- 
gram to take advantage of both the quality 
and quantity of technical expertise available 
throughout the Center. 



Use of a Prime Development Contrac- 
tor to Provide SE&I Support. In the 

Shuttle program, the SE&I support contrac- 
tor was also the prime contractor for the de- 
velopment of the Space Shuttle orbiter. 
Although there was considerable concern 
about the ability of the contractor to main- 
tain objectivity in supporting SE&I, this con- 
cern was reduced to an acceptable level by 
separating the direction channels of the 
development and integration activity both 
within NASA and within the contractor's 
organization. The support contract was also 
set up with an award fee structure in which 
SE&I was responsible for providing inputs 
for the SE&I activities. There were many 
advantages in this arrangement: 

a) The integration personnel were familiar 
with one of the major program elements 
and did not need to become familiar with 
that element or the general program 
structure. 

b) Technical experts could be made avail- 
able for both activities as needed. 

c) Many of the synthesis tools required by 
both activities were similar, and fre- 
quently one model could be used for both 
purposes with only minor modifications. 

d) Uniformity in approach assured ease of 
comparison of results from both project- 
level and program-level activities. 

The management of SE&I in NASA man- 
ned space programs has developed over the 
last 30 years to satisfactorily integrate 
relatively complex programs. Some of the 
approaches and techniques described in this 
paper may be helpful in integrating future 
programs. Careful consideration of the 
organizational structure and systems archi- 
tecture at a start of a program has an 
overriding effect on the effort required to 
accomplish the SE&I activity. 



104 



THE SYSTEMS ENGINEERING ROLE IN TOP-LEVEL REQUIREMENTS 



The SE Role in Establishing, Verbifying and -%£ y ~7 

Controlling Top-level Program Requirements ' 

by Charles W. Mathews \ < 



People working in the field of systems engi- 
neering have differing views as to the range 
and depth of this subject. Without venturing 
into the controversial arena of specific defini- 
tions, I will assert that systems engineering 
has much to do with the definition, evalua- 
tion and control of the technical effort aimed 
at achieving the objectives of a program. 
Efforts in the field of systems engineering 
may in fact go well beyond purely technical 
considerations, e.g., when cost or political 
considerations impact the technical ap- 
proach to a program. In this context, the 
systems engineering process must function 
to maximize the probability that a program's 
technical requirements can be met while at 
the same time recognizing and including 
other program factors and constraints. New 
constraints as well as technical problems can 
be encountered at all stages of a program, 
often necessitating some adjustment to the 
program objectives and requirements. Such 
activities are part of the systems engineer- 
ing process, which must begin immediately 
at the start of a program and continue 
throughout the life of the program. 

Sometimes a program manager will con- 
centrate on insuring that hardware elements 
perform well and all play well together, 
assuming that this alone will enable the 
program requirements to be met. Then on 
entering the operational phase, while the 
system may indeed perform, it may not do 
what was intended. This situation frequent- 
ly occurs because many engineers, scientists, 
managers, and yes, even administrators tend 
to be intrigued by and want to concentrate 
on configuration selection and design prob- 
lems. It is the responsibility of the top-level 
systems engineering professionals to be the 
conscience of all participants in making sure 
that program requirements are met or prop- 
erly adjusted. 



The need is to focus on program require- 
ments during all phases and facets of a 
program, e.g. definition, development, man- 
ufacturing, testing, operations, growth and, 
most important, effective use or mission 
accomplishment. The effort just described in- 
volves the entire systems engineering task; 
however, the main emphasis of this paper is 
the interaction of the systems engineering 
process with the top-level program require- 
ments. This aspect of systems engineering is 
often given inadequate attention during 
certain phases of a program. This paper will 
endeavor to answer such questions as: 

What is meant by top-level program re- 
quirements, and who generates them? 

How are these requirements validated, 
altered, and controlled by the systems engi- 
neering process? 

What capabilities are needed to accom- 
plish such efforts effectively? 

WHAT ARE TOP-LEVEL PROGRAM 
REQUIREMENTS? 

Top-level program requirements are directly 
related to program objectives or systems uses 
determined and stated early during the 
program definition. Probably the most re- 
membered program objective of the past was 
to "land men on the moon and return them 
safely to Earth." The program requirements 
that emerged from early studies included, 
among others, one to two-week mission dura- 
tions, lunar landing, extravehicular activi- 
ties, launch from a remote site, rendezvous, 
and reentry from near escape velocity, all of 
which had never been accomplished at the 
time of President Kennedy's statement. 

These requirements in turn highlighted 
the need to define and validate specific 
technical approaches— redundancy concepts, 
simple system interfaces, new technology 



105 



NAL MONOGRAPH SERIES. SYSTEMS ENGINEERING PAPERS 



requirements (e.g., fuel cells), operational 
demonstrations such as Gemini, entirely 
new configurations such as the LM, and the 
nature of the flight program buildup. Inci- 
dentally, many of the program requirements 
for Apollo determined the mission objectives 
for the earlier Gemini program. In any 
event, program requirements must be estab- 
lished early and stated distinctly so that all 
necessary steps for meeting and validating 
them can be determined. This effort is a fun- 
damental systems engineering function. 

Types of Program Objectives and 
Requirements 

The program objectives and requirements 
described in the preceding paragraphs em- 
phasize mission demonstrations. Obtaining 
desired science or applications information is 
another type of program objective. The pro- 
gram requirements then state the need for 
specific data, usually specifying a particular 
instrument or instrument set; the operating 
conditions under which the data is to be ob- 
tained (e.g., orbit altitude, field of view, and 
pointing accuracy); and the data handling 
and use. Conversely, a new instrument may 
be conceived or created with the program ob- 
jective to establish its use potential. The 
Multispectral Scanner employed in the 
Landsat program is an example. 

Another space program category includes 
service functions such as Earth-to-orbit 
transportation or a space laboratory. In the 
first case, the program objective might be 
economical and an easy access to the space 
environment for the using community. Pro- 
gram requirements then include such pa- 
rameters as dollars per pound to orbit, 
launch frequency and payload integration 
lead times. Conversely, in this case, the 
program objectives might also be stated in 
terms of capability demonstrations such as 
the reentry of a winged spacecraft, ground 
landing and reusability. The program 
requirements then are related to system 



performance in accomplishing these mission 
and configuration demonstrations. 

It is important to firmly establish which 
of the above two categories reflect the real 
program objectives because a capability 
demonstration has a higher potential for suc- 
cess than a tightly specified use commit- 
ment. The systems engineering organization 
should be providing top-level program man- 
agement with the information to make such 
determinations. The program objectives may 
vary during program implementation be- 
cause of early "selling" pressures or because 
of unforeseen technical problems When this 
happens, the systems engineering organiza- 
tion should provide concrete evidence to 
management so that a strategy can be devel- 
oped to properly inform the outside world, 
e.g., Office of Management and Budget 
(OMB), Congressional committees and the 
media; if the outside elements are not made 
to understand and accept such changes in a 
timely way, support can be alienated, 
placing extreme pressure on the program. 

Establishing Priorities 

When a large number of objectives and asso- 
ciated requirements are included in a given 
program, an additional complication occurs. 
Several past programs qualify including pro- 
grams as early as Gemini and space station 
programs such as Skylab. Even Apollo, with 
its simply stated mission objective, had 
many secondary objectives associated with 
lunar exploration and lunar science. It is 
very important to establish priorities with- 
out precluding the accomplishment of objec- 
tives of lower priority. For example, the two 
top priorities in the Gemini program were 
demonstration of long duration flight and 
rendezvous, but large quick-opening hatches 
were incorporated to accommodate extrave- 
hicular activities (EVA) and the spacecraft 
structure was designed to permit the firing 
of a large propulsive stage once docked to it. 
Most of these secondary objectives were 



106 



THE SYSTEMS ENGINEERING ROLE IN TOP-LEVEL REQUIREMENTS 



accomplished. In fact, because of the way the 
actual flight program developed, EVA was 
one of the first accomplishments. The secon- 
dary program objectives also afforded some 
flexibility; the paraglider system planned for 
use in ground landing, for example, was 
dropped from Gemini in order to meet cost 
and schedule objectives. 

To summarize what has been stated thus 
far, a number of classes of top-level program 
requirements exist. They can be associated 
with mission objectives, scientific investiga- 
tions or space services, among others. In 
addition, different ways of looking at top- 
level program requirements include demon- 
strations as compared with tightly specified 
commitments. Many programs have multi- 
ple requirements. Nevertheless, it is impor- 
tant to 'zero in' on these requirements early 
in the systems engineering process, i.e., 
during Phase A. Most important, they must 
combine to realistically meet the stated 
objectives of the program; they must be 
prioritized when necessary; and they must 
be clearly stated and documented in the 
Program Requirements Document. 

These requirements may have to be 
changed, adjusted or reprioritized as the 
program proceeds, and any changes must be 
carefully controlled and formally approved 
at the top level of the program throughout its 
life. If program objectives are affected, a 
decision by the administrator is required (at 
least for medium-to-large programs). The 
outside world needs to be kept abreast of 
significant changes in objectives or top-level 
requirements so that no sudden surprises 
occur that affect support. 

The systems engineering function should 
provide the initial evaluation and validation 
of the top-level program requirements and 
should continue to evaluate proposals or 
events that would produce any change. The 
effort should occur at the top level of a dis- 
tributed systems engineering function and 
guide upper level program management and 
the administrator. 



WHO GENERATES TOP-LEVEL PROGRAM 
REQUIREMENTS? 

A program objective can be conceived and 
stated initially by almost anyone working at 
any level, from the President, as in Apollo, to 
others on down. If considered seriously, such 
an objective is studied to determine its valid- 
ity, practicality and usefulness. Sometimes 
it takes a short time to obtain a go-ahead; 
sometimes it takes many years, as on the 
Space Station. One of the fallouts of these 
efforts should be a clear statement of top- 
level program requirements. 

The involvement of the right people in 
the generation of top-level program require- 
ments is extremely important. Depending on 
the nature of the program, this involvement 
can include customers, users, operators and, 
of course, designers and developers. Program 
managers and directors, however, should 
guard against limiting involvement in this 
activity to just the latter two. Systems engi- 
neering, should be involved early to assure a 
reasoned and logical approach to the genera- 
tion and iteration of program requirements. 

In the space science and applications 
arenas, program requirements are frequent- 
ly generated by a process that begins with a 
program objective or a flight system capabil- 
ity being stated in an "Announcement of 
Flight Opportunity." Investigators are then 
selected through evaluation of the responses 
obtained. The experiments selected deter- 
mine the actual requirements of the flight 
program. Other inputs are often required, as 
adjustments may be needed in consideration 
of technical limitations or program costs, for 
example. The analysis and resulting output 
of the systems engineering group usually 
gives rise to an iteration of the program 
requirements, which again involves the sci- 
ence team. Frequently, a selected proposal 
provides for excellent science but does not 
deal adequately with other constraining 
technical considerations and the cost impli- 
cations associated with the overall effort. 



107 



NAL MONOGRAPH SERIES: SYSTEMS ENGINEERING PAPERS 



Hierarchical Consideration in 
Requirements Generation 

In all classes of space flight programs, the 
systems engineering organization should 
work closely with groups having expertise in 
and cognizance over program requirements. 
In Apollo, because the primary program 
objective was oriented to the accomplish- 
ment of a specific mission demonstration, 
operational personnel — particularly those 
involved in flight operations — tended to be 
near the top of the program requirements 
hierarchy. Even though science re- 
quirements existed and science teams and 
advisory committees were active, the science 
requirements were of lower priority, at least 
until after the first lunar landing was accom- 
plished. In contrast, a program such as 
Skylab always included the solar scientists 
and Earth resources investigators, among 
others, at the top of the requirements hierar- 
chy, even though the engineering and 
operations personnel may have been 
somewhat confused by this arrangement. 

The Space Shuttle involves still another 
situation. The operations groups can be per- 
ceived to be the customers for the system, 
but the real users at the top of the hierarchy 
are the scientists, commercial firms, indus- 
trial experimenters and NASA engineers 
who provide the payloads that fly on the 
Space Shuttle or conduct related experi- 
ments or other use functions. This is similar 
to the relationship between passengers and 
shippers, the airlines, and the commercial 
airplane developer in the air transport 
industry. In addition to general operating ef- 
ficiency, consideration must be given to user 
accommodation from the start. Such needs 
are now quite successfully accomplished in 
commercial aviation. Naturally, expecta- 
tions are less in the case of the Space Shuttle 
because of its experimental nature, but it is 
fair to say that user accommodation has not 
been accomplished to the degree desired. 

The foregoing discussion is not meant to 
imply that successful hardware design, 



development and systems integration is not 
an important facet of systems engineering. 
There are instances where these consider- 
ations are at the top of the requirements 
hierarchy. An instrument demonstration 
such as the Multispectral Scanner is one case 
in point, and the Advanced Communications 
Technology Satellite (ACTS) is another tech- 
nology demonstration of this type. In most 
respects, the research airplanes such as the 
X-l and X-15 fit into this category. However, 
this case does not fit the situations occurring 
in most NASA programs. It is therefore criti- 
cal for top-level program management to 
examine its program, determine who the 
main contributors or generators of the pro- 
gram requirements are, and assure that they 
are interfacing adequately with the systems 
engineering function. This need exists at the 
outset of the program but should continue 
through the design and development phases, 
for as hardware and software systems prob- 
lems are encountered, the tendency is to 
focus on them, and top-level program re- 
quirements can be altered or even disappear 
without due consideration. 

Who Validates Top-level Program 
Requirements? 

Activities that validate top-level program 
requirements are mostly of a systems en- 
gineering nature. This validation, is an 
important, though small, part of the total 
systems engineering job. In total, systems 
engineering, particularly during design and 
development, is a distributed activity. Space- 
craft hardware systems such as electrical 
power, attitude control and communications 
all have to be systems engineered. Total 
systems elements (e.g., a launch vehicle 
stage, a checkout facility, a launch complex 
and a flight control center) all have to be sys- 
tems engineered to correctly perform their 
functions. In the end, all elements involved 
in a program — the total flight system, the 
operational support facilities, the mission 
planning, and the user integration, among 



108 



THE SYSTEMS ENGINEERING ROLE IN TOP-LEVEL REQUIREMENTS 



others— need to be brought together in a 
timely fashion to meet the program objec- 
tives and requirements. An effort of this na- 
ture, even for a very modest program, is too 
complex to be handled in a purely top-down 
fashion. The cardinal rule is that all the in- 
terfaces at any particular level, both hori- 
zontally and vertically, should be as clean 
and simple as is practical. 

Validation Efforts During Program 
Definition 

At the start of program evolution, practically 
all of the mainstream effort is of a systems 
engineering character and is more top-down 
than later in the program. The validation 
effort begins in pre-Phase A, where options 
are examined for meeting the program objec- 
tives as well as certain initially stated pro- 
gram requirements. These requirements 
should endeavor to incorporate most of the 
major program factors but are usually gener- 
al and often are quite optimistic. All aspects 
of the technical and programmatic approach 
should be studied. Although effort is limited 
in this phase, a determined attempt must be 
made to establish and to ascertain the feasi- 
bility of meeting the program requirements. 
This work should usually be accomplished by 
a team working at a single location, 
although supporting effort and information 
can be obtained from groups in other loca- 
tions. There have been cases where alterna- 
tive approaches are studied by separate 
teams, which has proved to be effective in 
some pre-Phase A efforts. In all likelihood, 
the program requirements will be changed 
and expanded to account for such factors as 
technology readiness, knowledge of the 
operating environment, mission complexity 
and similar factors. A need for additional 
technology development or operational 
verifications may be identified as well. Any 
pre-Phase A study that is completed with 
everything looking rosy should be viewed 
with caution. 



Phase A efforts are aimed at selecting 
and analyzing a single programmatic and 
technical approach, at least in theory, to best 
meet the requirements of the program. 
Again, the Phase A activity is chiefly a sys- 
tems engineering effort usually conducted by 
a single team at a single location. If a work 
breakdown structure with clear interfaces 
can be established at this time, then systems 
engineering at multiple locations may be 
possible. In any case, the group that worked 
during the pre-Phase A study needs to be 
augmented considerably, and the support of 
one or more contractors is frequently 
obtained. 

In this phase, emphasis should be placed 
not only on hardware but on validating the 
mission design and other operational or use 
aspects of the program. This emphasis is par- 
ticularly important where the operational 
life of the program is envisioned to be very 
long, e.g., Space Shuttle, Hubble Telescope, 
Space Station and the Earth Observing 
System (EOS). It is important to clearly 
establish what is required in the operational 
phase and to establish with adequate confi- 
dence the feasibility of accomplishing the 
programs with realistic operational costs 
and schedules. 

At the time the program enters Phase B, 
a complete work breakdown structure should 
be established, including all facets of the pro- 
gram with simple and clear interfaces and as 
little overlap as possible. Program work 
assignments will be made. For moderate to 
large programs, these assignments may 
involve program groups at different geo- 
graphic locations, including parts of the total 
systems engineering effort. The top-level 
program requirements should have been 
established in adequate detail, and each 
program organizational element should 
regard these requirements as program con- 
straints. 

The program requirements or even the 
objectives can be changed because of unfore- 
seen events or other activities occurring 



109 



NAL MONOGRAPH SERIES: SYSTEMS ENGINEERING PAPERS 



throughout the course of the program, but 
they should be subject to formal change 
control. Obviously this particular change 
control activity deals with top-level program 
requirements and must occur at the highest 
level in the program; in certain cases, the 
administrator should be informed of an 
impending change and must be informed 
when program objectives are significantly 
impacted. 

Validation Efforts During Design, 
Development and Operations 

Although the top-level systems engineering 
effort in the definition phases of a program is 
important, this function is critically impor- 
tant in Phases C/D, the design and develop- 
ment phases. It is during this time that most 
of the technical difficulties and other pro- 
gram limitations surface. There is a strong 
tendency to focus on the flight hardware and 
to get it delivered and flying. These situa- 
tions sometimes allow the top-level require- 
ments to "fall through the cracks," later 
producing surprises, embarrassments and 
undue pressures, which can contribute to the 
potential for accidents and failures in the 
operational phase. 

Systems engineering must continue 
throughout the operational phases of a pro- 
gram. Although the character of the top- 
level activities change, there still is a need to 
deal with program requirements and their 
alteration. Some of the possible subjects are 
the rate and nature of the flight program 
buildup, working around performance 
deficiencies or failures, and adjustments to 
mission objectives. On the positive side, the 
top-level systems engineering in the oper- 
ational phase involves the incorporation of 
new system capabilities and mission exten- 
sions, including the development and control 
of the associated program requirements. 

Support to the activities just described is 
accomplished by a systems engineering 
group also operating at the highest level in 
the program's organizational structure. This 



group is the guardian and conscience of the 
top-level program requirements but by no 
means includes the total systems engineer- 
ing effort. The group should be composed of 
engineering personnel, each of whom has 
considerable technical experience in one or 
more of the applicable areas and possesses a 
natural talent and desire to deal with all 
aspects of the program. The individuals 
should be selected so the group encompasses 
as many of the technical, scientific and 
programmatic disciplines involved in the 
program as possible, but the group does not 
have to be large. By selecting people with the 
right backgrounds and talents, the work can 
be done in part by obtaining information 
from other elements of the program — in 
particular, other systems engineering 
groups. 

how are top-level program 
Requirements Controlled? 

Control of top-level program requirements is 
extremely critical to program success. This is 
not to say that such requirements cannot be 
changed. Almost without exception changes 
will occur, but they must be carefully 
controlled by a well-defined process that es- 
tablishes the change impact on the program, 
particularly its objectives. This process also 
must inform program participants inside 
and outside the program organizational 
structure, including those having responsi- 
bilities or scrutiny from above. 

The program director is the individual 
who is personally responsible for the integri- 
ty and control of the top-level program 
requirements. As such, the program director 
must assure that a Program Requirements 
Document is produced during Phase A and 
that it is properly updated immediately 
following a change. This effort is supported 
mainly by the program director's systems 
engineering group described in previous sec- 
tions. This group is responsible for analyzing 
any proposed change that could potentially 
impact the top-level program requirements. 



110 



THE SYSTEMS ENGINEERING ROLE IN TOP-LEVEL REQUIREMENTS 



The analysis can be done by the group itself 
or by support groups, including contractors. 
The analysis must specifically include in 
writing how the affected requirement(s) 
would be changed and the determination of 
other impacts such as cost or schedule, which 
could be either positive or negative. 

Change Control of Program 
Requirements 

Change proposals are brought before a 
standing committee, usually called a change 
board, selected by the program director. 
There will be other change boards through- 
out the program, but this one should deal 
only with top-level program requirements. 
Anyone who proposes a legitimate change in 
the program requirements should be able to 
come before this board. In general, individu- 
als who have a significant input should also 
be invited. The proposed change is usually 
presented by its sponsor and is followed by a 
presentation of the analysis of the systems 
engineering group. Following discussion, the 
program director makes the disposition, 
which can include acceptance, rejection, or a 
requirement for further analyses or informa- 
tion. Following an acceptance, the Program 
Requirements Document should be changed 
immediately. Regardless of the nature of the 
decision, the affected elements of the pro- 
gram organization need to be informed im- 
mediately. Affected elements outside the 
program should also be informed in a timely 
manner but only after an appropriate strate- 
gy is developed. 

One of the chief difficulties associated 
with this change control activity is that 
events that impact the top-level program re- 
quirements can occur at any place, at any 
time and at any level in the program, and 
there is a natural tendency to try to fix a 
problem at its source without passing on 
information. Several things can be done to 
alleviate this difficulty as it relates to the 
activities of the top-level systems engineer- 
ing group. Individuals in the group must 



attend design reviews and other program 
reviews associated with all the program ele- 
ments. They must be able to have free infor- 
mation exchange with other program and 
project personnel and to accompany them on 
visits to contractors when the occasion 
demands. These activities are best accom- 
plished if the group and its members operate 
with a low profile. They should not give or 
imply directions or conclusions in discus- 
sions with program and project people. All 
direction as a result of their work should 
come from the program director. Naturally, 
these individuals must be able to request 
and analyze program documentation, but all 
such activities should be done in a way to 
maintain good rapport with other groups 
working in the program. 

Top-level Program Requirements in 
Previous Programs 

In general, most of NASA's past major pro- 
grams have successfully met their program 
objectives and must have fulfilled their pro- 
gram requirements. Some brief observations 
of the results obtained during some of the 
previous manned programs may provide use- 
ful insight into future programs. Although 
the very early programs were not explicitly 
divided into program phases, in retrospect, it 
is possible to discuss them within a phased 
context. 

The Mercury Program 

The Mercury program objective was to place 
a manned spacecraft in orbit around Earth 
and return safely. In pre-Phase A, several 
winged (lifting) configurations were studied 
as well as the so-called "capsule." The cap- 
sule was selected on the basis of greater 
technical simplicity and limitations on 
launch vehicle payload capability. In Phase 
A, in addition to developing the spacecraft 
systems specifications, safety requirements 
were emphasized, including the proper posi- 
tioning and support of the crew to handle 



111 



NAL MONOGRAPH SERIES: SYSTEMS ENGINEERING PAPERS 



launch and reentry accelerations, which 
were demonstrated on a centrifuge; the con- 
cept of a system to escape from the launch 
vehicle if necessary; and the layout of a 
worldwide tracking and monitoring network. 
In Phase B, a full-scale demonstration of the 
reentry heat protection system was conduct- 
ed, and the results produced minor design 
changes. The concepts of flight control and 
recovery were evolved, including a mission 
control center and flight controller deploy- 
ment to remote sites, worldwide communica- 
tion for near real-time surveillance of the 
missions, and recovery procedures involving 
ship deployment. 

The spacecraft configuration and specifi- 
cations proved to be satisfactory although 
considerable development problems were 
encountered. The biggest systems engineer- 
ing problem was associated with the lack of 
appreciation of the difficulties in conducting 
factory and preflight checkout. The checkout 
required more or less continuous human 
presence in the extremely confining interior 
of the spacecraft, producing wire breakage 
and other damage. These conditions were 
severe enough to curtail the flight program, 
although six manned flights were made, 
building up to a duration of approximately 
one day in orbit. 

The Gemini Program 

The pre-Phase A activity concentrated large- 
ly on correcting some of the basic problems 
encountered in Mercury, i.e., a Gemini 
spacecraft design that had most of the equip- 
ment outside the pressure vessel and was 
also checkable from the outside, allowing a 
relatively clear cockpit area. The spacecraft 
was enlarged to provide for a two-man crew, 
but the basic external configuration and heat 
protection system of the Mercury spacecraft 
was retained. 

Most of the Phase A activity involved 
defining the mission objectives, in support of 
Apollo, and the related program require- 
ments associated with rendezvous and long 



duration flight, e.g., the Atlas-Agena target 
vehicle, orbit maneuvering system, rendez- 
vous radar, fuel cells, and the cryogenic 
storage of hydrogen and oxygen in a super- 
critical state. Again, considerable develop- 
ment problems emerged, largely associated 
with the newer systems, such as ablative 
thrusters and fuel cells. Problems were also 
encountered in the flight program. The ini- 
tial rendezvous exercise revealed inadequate 
attention to mission design, which was later 
corrected, and several classes of rendezvous 
were successfully demonstrated. The extra- 
vehicular activities revealed deficiencies in 
training, and neutral buoyancy simulation 
was introduced late in the program. 

One significant systems engineering 
achievement emphasized the checkout 
systems and checkout procedures, and the 
delivery of flight ready spacecraft. To gain 
confidence, many of the checkout personnel 
at the Cape were sent on temporary duty 
(TDY) to the factory to participate in the 
factory checkout of the early spacecraft. This 
approach allowed the ten manned flights to 
take place on about two-month cycles and 
contributed immensely to the on-time 
launches required for rendezvous. 

The Apollo Program 

The Apollo Program was characterized by a 
disjointed definition program. Because of the 
obvious schedule pressures, certain contracts 
involving Phase B-type effort were let before 
either the mission design or the lunar 
landing mode had been selected. For exam- 
ple, the command and service module con- 
tract was awarded while questions about the 
use of Earth orbit rendezvous, lunar orbit 
rendezvous, and the so-called direct ascent 
were still being debated. Sufficient pre- 
Phase A effort was completed to enable a 
decision to go with the lunar orbit rendez- 
vous route in the spring of 1962, but the 
Phase A work on the lunar module, even 
when accomplished in-house on a highly ac- 
celerated schedule, did not allow the lunar 



112 



THE SYSTEMS ENGINEERING ROLE IN TOP-LEVEL REQUIREMENTS 



module contractor to be selected until nearly 
a year after the selection of the command 
and service module contractor. This situa- 
tion proved to be very distracting to the 
latter and resulted in major inefficiencies in 
the contracted effort caused by premature 
work force buildup. 

What saved the situation was the main- 
tenance of simple interfaces between the two 
spacecraft. In fact, not much more than a 
docking interface existed; however, there 
was also an important structural interface 
recalling that service module propulsion was 
used to place the docked configuration in 
lunar orbit. No support was required be- 
tween the two spacecraft except status moni- 
toring, and no commonality of systems was 
specified, although by some rationales, this 
approach appears inefficient. The simple 
system organizational and programmatic 
interfaces obtained greatly benefited the 
program. It was also the approach taken in 
connection with other elements of Apollo. 

The operational phase of the Apollo pro- 
gram provides good illustrations of systems 
capability extension and mission extensions. 
The major extensions to the lunar surface 
stay-time of the lunar module is an example. 
The decision to accomplish this was made 
about the time of the first lunar landing, and 
a Headquarters systems engineering group 
provided the impetus for the validation. An- 
other capability extension was the addition 
of the lunar rover contract, awarded about 
six years after the Apollo start but before the 
first lunar landing. Both these added capa- 
bilities greatly enhanced the lunar surface 
science and exploration aspects of the Apollo 
program. 

The Skylab Program 

The definition activities of the program that 
ultimately became Skylab proceeded in what 
must be described as a highly confused state; 
most of the program objectives and user- 
oriented program requirements, however, 
remained stable for the entire duration of the 



program. The program first known as Apollo 
Applications started out as a series of single- 
mission flights involving a larger number of 
scientific and technical experiments. This 
program concept was the basis for approval 
in the President's budget for FY 1968. About 
the same time, a command decision was 
made to incorporate these experiments in a 
concept known as the "wet workshop," in 
which a spent upper stage of the Saturn V 
would be left in orbit, purged, occupied and 
outfitted to perform the experiments. Many 
believed the concept could not work, but the 
program proceeded to preliminary design 
and, in many cases, detailed design. In the 
spring of 1969, a decision was made to go to a 
"dry workshop" wherein all the flight hard- 
ware elements would be assembled and 
checked out on the ground and launched us- 
ing the first two stages of the Saturn V as the- 
launch vehicle. It took another four years of 
design and development to bring the pro- 
gram to flight readiness. The flight program 
was quite successful in the accomplishment 
of the many experiments. The data obtained 
from a large solar telescope, for example, the 
Apollo Telescope Mount (ATM), was regard- 
ed as outstanding by the scientists involved. 
This capability was included in the earliest 
program requirements. 

Concluding remarks 

This paper has endeavored to highlight the 
importance of generating top-level program 
requirements at an early stage in the pro- 
gram evolution or Phase A definition phase. 
These requirements should include all the 
factors involved in meeting the program- 
objective(s) and should be stated with clarity 
so a determination can be made as to wheth- 
er they can or are being met. Depending on 
the nature of the program, these require- 
ments can relate to uses of a capability, a 
mission objective or other factors, including 
a simple hardware demonstration such as a 
test of a new instrument. It is critical to 
understand whether specific performance 



113 



NAL MONOGRAPH SERIES: SYSTEMS ENGINEERING PAPERS 



requirements are to be met or only a demon- 
stration of capability is entailed, for the 
latter provides more flexibility for program 
adjustments. 

The establishment of program require- 
ments usually requires input and involve- 
ment of people both inside and outside of the 
program organization. Determination of just 
what disciplines are involved is important, 
particularly for the users and operators. 

Validation of the top-level program 
requirements is a systems engineering func- 
tion. At the outset, the systems engineering 
organization works with entities responsible 
for generating the requirements in an 
iterative process to assure their validity. 
This activity continues throughout the life of 
the program because of unforeseen events 
that impact the program effort. At times, 
this will necessitate changes to top-level 
program requirements. Changes should be 
under formal change control, and the sys- 
tems engineering organization operating at 
the top of the program organization struc- 
ture should be responsible for the validation 
effort. Systems engineering is a program- 



distributed activity that allows the top-level 
systems engineering organization to be rela- 
tively small because it depends on others for 
most of the required analysis. It should oper- 
ate with a low profile. 

Past programs serve to illustrate the 
range of program requirements consider- 
ations and the associated systems engineer- 
ing effort. In the early manned programs, 
safety was a dominant consideration. Exper- 
ience in these programs showed that 
preflight checkout is an important consider- 
ation, as is mission design, training, and 
simulation, all of which can impact the hard- 
ware design. 

The top-level program requirements and 
the associated systems engineering activi- 
ties should obtain and maintain simple 
interfaces between program elements, even 
though this produces some apparent pro- 
gram inefficiency. At least one past program, 
Skylab, has shown that top-level program 
requirements can be maintained even when 
considerable fluxing occurs with regard to 
the hardware and mission design. 



114 



COST CONSIDERATIONS IN THE SE PROCESS 



The Importance of Cost Considerations in the tf$$r?& 
Systems Engineering Process ^ 

by John D. Hodge 



// 



One of the most vexing aspects of managing 
large programs within NASA (or any other 
high technology government programs) is 
how to allocate program funds in a way that 
is best for the program. One of the major 
reasons is that the role of cost changes 
throughout the phases of the program. An- 
other reason is that total cost is not all that 
easy to define; yet another is that funding, 
which is based on annual appropriations, is 
almost never consistent with fiscally effi- 
cient program spending rates. The net result 
is that program costs almost always escalate 
and inordinate amounts of time are spent 
controlling costs at the expense of maintain- 
ing performance or schedule. 

Many studies have been performed to try 
and understand this problem. They show 
that program costs will escalate by at least a 
factor of three, from approval to completion. 
The studies suggest a number of guidelines 
that should be followed if costs are to be kept 
down, including clear definition of require- 
ments, stable management and strong cen- 
tral control. Unfortunately, these factors are 
not always under the control of the program 
manager. 

This paper examines the question of cost, 
from the birth of a program to its conclusion, 
particularly from the point of view of large 
multi-center programs, and suggests how to 
avoid some of the traps and pitfalls. Empha- 
sis is given to cost in the systems engineer- 
ing process, but there is an inevitable 
overlap with program management. (These 
terms, systems engineering and program 
management, have never been clearly de- 
fined.) In these days of vast Federal budget 
deficits and increasing overseas competition, 
it is imperative that we get more for each 
research and development dollar. This is the 
only way we will retain our leadership in 



high technology and, in the long run, our 
way of life. 

Basic Principles 

The principles are simple. First, define very 
carefully what it is you are trying to do. 
Check everything you do against that base- 
line, even if it has to be changed, and resist 
change once the decisions have been made. 
Second, break up the program into manage- 
ably sized chunks of deliverables that can be 
measured in terms of cost, schedule and per- 
formance, and define the interfaces between 
the chunks. Third, continuously assess the 
risks to success as the program proceeds, and 
modify only as necessary. 

REQUIREMENTS TRACEABILITY 

Most studies have shown that the primary 
reason for cost escalation is that not enough 
time or resources are spent in defining the 
program. It is clear that you cannot control 
what you have not or cannot define. It is dur- 
ing this period that some of the most elegant 
systems engineering should be performed, 
especially in understanding the cost of every 
requirement and its systems implication. 
Even if the definition is adequate during the 
early phases of the program, it is imperative 
that great vigilance be exercised in main- 
taining the baseline definition of the pro- 
gram and the fundamental reasons for doing 
the program. This process establishes a 
small but influential part of the program 
office, preferably within the systems engi- 
neering organization, dedicated to the trace- 
ability of requirements and to ensuring that 
a clear path exists from program rationale to 
program requirements to systems require- 
ments to systems design. Too often, once a 



115 



READINGS IN SYSTEMS ENGINEERING 



design has been established, changes are 
proposed and enacted that bear little rela- 
tionship to the original premises of the 
program. As will be discussed later in this 
paper, there are many reasons for change, 
but where possible, changes should be con- 
sidered during the formulation of the pro- 
gram and not later when the program struc- 
ture is in place and the program is in 
progress. Change is almost always costly; 
requirements traceability provides a bul- 
wark against which the program manager 
and the systems engineer can stand and 
defend. 

Baseline Cost, Schedule and 
Performance 

The three main parameters in the control 
process — cost, schedule and performance — 
are the program manager's bread and butter. 
Again, program definition is vital and neces- 
sary from the very beginning. It may be 
argued that clear definition is not possible, 
particularly early in the program; never- 
theless, an approved, traceable baseline, al- 
though it may alter, must be known at any 
given time, and must include everything in 
the program. The "I forgots" can kill you. 

The key to success in handling these 
three parameters is to manage the balancing 
act between them. Cost, schedule and perfor- 
mance are usually dependent variables and 
at various times, one or another may assume 
greater or lesser importance. A single vari- 
able, however, should never be changed 
without knowing the impact on the other 
two. Within the NASA culture, performance 
is generally the predominant factor, and 
schedule is a distant second. Cost tends to be 
considered mostly in the context of the annu- 
al appropriation, but from the point of view 
of the program manager, all three param- 
eters must be defined and approved continu- 
ously, which is a function of the systems 
engineering process. 



Program Risk Analysis 

In recent years, especially since the Chal- 
lenger accident, program risk analysis has 
come to be used largely in the context of crew 
safety, but this is only a part of program risk. 
Basically, program risk analysis assesses the 
probability of meeting requirements as 
changes occur. A number of analytical tools 
now available can be used to understand the 
relationships between cost, performance and 
schedule. Again, a small group within the 
systems engineering organization should be 
dedicated to understanding the impact of 
any change on all three parameters. Armed 
with this information, risk can be reduced in 
many ways. Adding more money, reducing 
the performance requirements, or extending 
the schedule are most often used. A compe- 
tent systems engineer will know the rela- 
tionships between these three variables and 
the impact of any situation on the total pro- 
gram. 

The Role of Cost in Phased 
Procurement 

The most common form of procuring high 
technology capability within the Federal 
Government is known as phased procure- 
ment. The theory behind this procurement 
method is that commitment to the program 
gradually increases with time and in dis- 
crete stages. Within NASA, there are four 
standard phases; others are beginning to 
creep in as the ability to establish new pro- 
grams becomes more difficult and the dura- 
tion and cost of operations becomes a more 
significant part of total program costs. The 
role of cost is different in each of the phases. 
The phases are: 

Pre-phase A: This is a very unstruc- 
tured period that examines new ideas, 
usually without central control and mostly 
oriented toward small studies. This period 



116 



COST CONSIDERATIONS IN THE SE PROCESS 



can last for a decade or more and produces 
the list of ideas and alternatives from which 
new programs are selected. 

Phase A: Sometimes called the feasibil- 
ity phase, this is a structured version of the 
previous phase. Usually a task force or pro- 
gram office is established, and multiple con- 
tracts will be awarded. The goal of this 
phase, which may last for several years but 
usually is limited to one or two years, is to 
decide whether a new program will be start- 
ed and what its purpose and content should 
be. This phase represents less than one per- 
cent of the total program costs. Nevertheless, 
it is largely a systems engineering effort and 
sets the stage for everything that follows. 

Phase B: Sometimes known as program 
definition, this phase is the most important 
in establishing the basic parameters of the 
program. By the time this phase is finished 
(a period of two or three years), the program 
rationale, cost, schedule, performance, man- 
agement style and the most likely technical 
solution will have been established. This 
phase usually involves multiple contracts to 
establish a variety of ideas and a competitive 
environment, should the program proceed. 
Cost is continuously assessed as a function of 
design solutions relative to basic require- 
ments. Studies indicate that from five per- 
cent to ten percent of the total program costs 
will need to be expended if control is to be 
maintained over the program during Phases 
C and D. 

Phase C/D: Originally separate phases, 
this period covers design, development, test 
and evaluation. Contracts may be open to all 
qualified bidders or only to those involved in 
the previous phase. Although competition is 
not usually open between Phases C and D, 
commitment to Phase D depends on a suc- 
cessful and acceptable design. In past pro- 
grams, two-thirds of the total program cost 
was expended during this period. The sys- 
tems engineering role has begun to shift 



toward systems specification and systems in- 
terfaces. The secret to cost control is a sound 
definition of end items and their interfaces 
with a tight hold on changes. 

Phase E: In most past programs, the op- 
erations costs were less than 20 percent of 
the total cost. This was because there was a 
definite end to a relatively short-term pro- 
gram. In recent years, particularly in the 
manned programs, the length of the oper- 
ational phase has increased significantly. In 
the case of the Shuttle, it could be conceived 
as indefinitely long. For this reason, life cy- 
cle costs should be a major consideration 
from the beginning. 

SELLING THE PROGRAM 

The definition of a new start within NASA 
varies by program and organization but can 
generally be said to occur at the beginning of 
Phase B. Prior to that time, the program 
manager is selling the program. The total 
expenditure of funds during the selling peri- 
od is usually far less than one percent of the 
final program costs; this is, however, when 
the basic parameters of the program are es- 
tablished. It is a time of building constitu- 
ents both inside and outside the Agency. 
Assuming that a feasible technical solution 
is available and an acceptable management 
scheme can be provided, much of the debate 
about whether a program should be approved 
centers largely around the question of cost. 
Of course, with only preliminary designs 
available, only cost estimates can be made 
and these are obtained from standard cost 
models. 

Cost Estimating 

During Phase A of the program, when the 
most rudimentary designs are available, it is 
essential that program cost estimates are 
made before the program start can be autho- 
rized. Estimates are made using cost models 
that have been developed on the basis of past 



117 



READblGS IN SYSTEMS ENGINEERING 



experience on similar programs. These 
models are among the most arcane devices 
invented by engineers, so a few words on how 
they work are appropriate. 

Past experience is captured by document- 
ing the cost of each system on the basis of 
weight. Regression analysis is performed to 
determine a straight line log relationship. 
Once the weight of the system has been esti- 
mated, the cost can be determined. This esti- 
mate is multiplied by a complexity factor to 
allow for the risk associated with the select- 
ed technology and may vary from as little as 
0.50 to 2 or more. This is repeated for each 
system, and the total becomes the baseline 
cost. This total is multiplied by a factor to 
allow for systems engineering and testing by 
the prime contractor. This is known as the 
"prime wrap" factor and is again determined 
based on all relevant past experience. All 
prime contractor estimates are added and 
then multiplied by a second factor known as 
the "nonprime wrap." This is the cost of gov- 
ernment work. Finally, a reserve factor is 
used to allow for problems during the pro- 
gram. There are separate cost models for 
manned and unmanned programs, which are 
significantly different. In general, for the un- 
manned programs, about 40 cents of every 
dollar goes to hardware, and in the manned 
programs, about 20 cents. 

These cost models pose a great many 
problems. First, they are normalized on the 
basis of weight. Clearly this is not valid in 
all cases, particularly structure. Second, 
they do not explain why the costs are what 
they are. Factors such as management style, 
procurement strategy and test philosophy 
are not differentiated. Third, they include all 
past experience, including errors and over- 
runs. In this respect, these cost models 
assume no learning curve. As it was in the 
beginning, is now, and forever shall be! They 
must therefore be used with great caution. 
From the systems engineer's point of view, 
these cost models can be used to assess the 
relative costs of various design solutions; on 



ah absolute basis, however, they are of little 
uk'e. 

So far we have been able to make a tenta- 
tive estimate of the cost of the flight system. 
To this must be added the cost of new facili- 
ties, including launch, test beds, flight oper- 
ations, networks and data reduction, among 
other factors, and finally the cost of oper- 
ations. 

It is at this point that the program man- 
ager faces the first dilemma: What should be 
included in the program cost? That sounds 
like a simple question, but it is complicated 
by the fact that not all costs are under the 
control of the program manager nor is he or 
she responsible for justifying all of the asso- 
ciated appropriations. For example, launch 
costs are provided by the Office of Space 
Flight, network costs are provided by the Of- 
fice of Operations, and civil service costs are 
provided by the research and program man- 
agement fund managed by the Office of the 
Comptroller. New buildings are provided un- 
der the construction of facilities budget. In 
addition, most new program managers are 
surprised to find that a tax based on the 
number of civil servants working on the pro- 
gram varies from Center to Center, and nei- 
ther the number of people nor the level of tax 
is under the control of the program manager. 
Taxation without representation! Despite 
this dilemma, the systems engineer should 
include all of these factors in the cost esti- 
mate because the chosen design will affect 
all of them; overall program costs are as im- 
portant to the Agency as direct program 
costs. 

Program costs tend to be presented as 
only those costs that are under the control of 
the program manager. No matter how much 
this limitation is stated in presentations, it 
is assumed that it is the total program cost 
(especially when it is a popular program) 
that has the support of the Executive branch, 
the Congress and other constituencies. It is 
no wonder that the average program in- 
creases in cost by a factor of about three from 



118 



COST CONSIDERATIONS IN THE SE PROCESS 



the time of approval to completion and that 
most program managers during this period 
are accused of everything from naivete to 
self-deception to outright lies. There is the 
added ethical question that if all costs were 
presented, the program would not be ap- 
proved! 

DEFINING THE PROGRAM 

This phase of the program, usually known as 
Phase B, will take from one to two years. The 
purpose is to take the various concepts con- 
sidered in Phase A and select a single valid 
solution. By the time Phase B is over, a clear 
set of requirements should be available with 
a complete set of functional specifications 
and a cost estimate based on preliminary de- 
sign concepts rather than on cost models. 
These are primarily produced by the systems 
engineering organization and include at 
least one preliminary design and selected 
technologies with well-understood risks as- 
sociated with those technologies. Don 
Hearth, who recently retired from NASA as 
director of the Langley Research Center, per- 
formed a study on how much this phase has 
cost for various past programs as compared 
to the success of the program in later phases. 
Success was measured as the ability to main- 
tain performance, schedule and cost as deter- 
mined at the end of Phase B. He concluded 
that the most successful programs spent 
between five percent and ten percent of the 
total program cost in Phase B. The scope was 
limited to unmanned programs, but the ra- 
tionale can reasonably be extended to man- 
ned programs. 

Apart from establishing a credible func- 
tional system specification, it is essential to 
determine the management structure, the 
procurement strategy and a baseline cost for 
the life of the program, including the cost of 
operations. Once again, the primary method 
for cost estimating is the cost model, but 
there should be sufficient detail available to 
check the model with bottom-up costs based 



on feasible design solutions. The systems 
engineer is responsible for comparing these 
two cost estimating techniques. It is unwise 
to proceed to the next phases unless some 
bottom-up cost estimating has been per- 
formed. 

Perhaps the most important product of 
this phase is a complete work breakdown 
structure. Again, this is largely the responsi- 
bility of the systems engineering organiza- 
tion. The axiom to be followed is, "You 
cannot control what you have not defined." 

Work breakdown Structure 

Too often a program will be approved with- 
out a well-established work breakdown 
structure (WBS) describing the whole pro- 
gram, which inevitably results in large cost 
overruns. The WBS is the basis for the pro- 
curement strategy and often for the manage- 
ment structure. Without it, program changes 
will take place after the contractors are in 
place and have to be paid. Overlaps between 
contracts, as well as missing elements and 
contract changes, are always expensive. 

The following simple rules have to be fol- 
lowed: 

1. Each element of the WBS should contain a 
deliverable that can be defined. 

2. The sum of the WBS elements must be the 
total program. (Note that a given program 
manager may not have the responsibility for 
all elements, but they should each be defined 
and allocated.) 

3. Each deliverable should be accompanied 
by a cost and a schedule. The cost should in- 
clude a reserve based on the estimated risk 
associated with that element, and the cost 
should be allocated to that element. 

As simple as these rules sound and as much 
as NASA requires contractors to adhere to 



119 



READINGS IN SYSTEMS ENGINEERING 



them, the internal track record is dismal. We 
can go a long way toward containing costs if 
discipline is established early and main- 
tained. 

One last word of caution. A WBS element 
should never be established on the basis of 
function or organization. These elements are 
not end items. Other mechanisms exist for 
identifying these elements, which in general 
could be defined as program overhead and 
not entirely the responsibility of the program 
manager. They should be recognized for 
what they are and identified, but they should 
not be included in the WBS. 

Managing the Program 

We have now reached the time in the pro- 
gram when promises have been made, deals 
have been struck, and the program has been 
approved. All that remains is to deliver. A 
custom within NASA stipulates that new 
managers are installed with the belief that 
the skills required to sell a program and to 
define it are different than those required to 
run it. Certainly some changes can be ex- 
pected, but I believe that such changes are 
better if they occur sometime after a phase 
has been entered and the basic management 
structures have been established. What the 
program needs at this time is ownership of 
the concept, and changes in management 
will usually result in program changes that 
inevitably will lead to increased costs. This 
is particularly true of the systems engineer- 
ing group that has carefully balanced the 
requirements against the design and is fa- 
miliar with the "why" of a decision as well as 
the "what." So far the total expenditure has 
been relatively low, but once the contractors 
are onboard and the manpower begins to 
build up, costs can escalate at an alarming 
rate. In a very short time, increases or de- 
creases in performance, extensions or reduc- 
tions in schedule, and decreases in annual 
funding will all increase cost. 



Design to cost. There is much talk about 
design to cost but very little action, and for 
this there are a number of reasons. Earlier, I 
mentioned that within NASA there is a ten- 
dency to order the three variables by perfor- 
mance first, schedule second, and only then 
worry about cost. So by tradition, cost tends 
to be put on the back burner. One of the rea- 
sons for this is that during the Apollo pro- 
gram, the cost function was transferred to 
the budget and program control groups. In a 
program where the technical problems were 
so difficult and the budgets were ample, this 
was understandable, but this is no longer the 
case. This situation resulted in a shift away 
from making the design engineer account- 
able for cost as well as performance and 
schedule. The second problem occurs when 
the cost is not allocated at the WBS element 
level, where it can readily be traded against 
performance and schedule and easily traced. 
I believe that cost must be allocated to the 
lowest possible level (a little scary for the 
program manager), but unless this is done, it 
will be impossible to hold the designer ac- 
countable and unlikely that overall costs 
will be held in check. The third problem is 
that in an organization that prides itself on 
technical excellence, it is very difficult not to 
make things a little better; consequently, 
there are always plenty of ideas around. The 
credo of the systems engineer should there- 
fore be: "The better is the enemy of the good." 

Design to life cycle cost. Over the past 
decade, the operational costs of NASA pro- 
grams have steadily risen as a percentage of 
total program costs. This is largely due to the 
fact that programs have a longer life in the 
operational phase. Whereas 20 years ago 
operational costs amounted to no more than 
20 percent of costs, they are now approach- 
ing half of the NASA budget. It is time to 
place design to life cycle cost on an equal 
footing with design to cost. The dilemma is 
that a design that allows low-cost operations 



120 



COST CONSIDERATIONS IN THE SE PROCESS 



will usually demand higher development 
costs and in turn, this means larger front- 
end program costs. It is essential that the 
systems engineer make these assessments. 
The simplest thing for a program manager to 
do is walk away from this dilemma and let 
the operations people worry about it later. 
As this is becoming an overall problem for 
the Agency, the ability to make new starts 
will depend on the ability to ensure that a 
sufficient percentage of the budget is avail- 
able for operations. Unfortunately, it is 
difficult to get enough operations people to 
participate early in the program, but I be- 
lieve it is essential. Some kind of veto power 
should be established when it comes to mak- 
ing design decisions; too many program 
managers do not feel responsible for oper- 
ations costs and perhaps, what is worse, are 
not held accountable for it. Let there be no 
doubt that operational costs are unaccepta- 
bly high. An operational concept must there- 
fore be developed early enough in the pro- 
gram to have an effect on the design process. 

Change control. Once a program is under- 
way, the program manager's responsibility 
is controlling change, which is inevitable. 
Earlier I said that you cannot control what 
you have not defined. It is equally true that 
you cannot control changing something that 
is not defined. First know what it is! A com- 
plete WBS with allocated schedule and cost 
is, once again, the key. Change requests 
must not be limited to solving a technical 
problem. They must be accompanied by cost 
and schedule impacts and, just as important, 
life cycle cost impacts. In addition, there is 
always a rippling cost impact caused by 
change. Other WBS elements may be affect- 
ed, including items in different contracts or 
in totally different NASA codes, or line 
items. For these reasons, change must be as- 
sessed at the systems engineering level as 
well as at the WBS level. Perhaps the over- 
riding rule is that changes should be difficult 
to approve but easy to implement once the 
decision is made. 



Managing cost reserves. A qualified cost 
estimator would not let a program get start- 
ed without making provision for cost over- 
runs or reserve. The many uncertainties in a 
development program make it essential. An 
analysis of past programs allows a fairly 
accurate estimate to be made of what is a 
reasonable total amount as a percentage of 
total costs, assuming that the programs are 
similar. Determining how and when the al- 
lowance should be allocated is much more 
difficult. One school of thought says that 
reserves should be held at the highest level 
in the program and applied only to correct 
unforeseen occurrences. The problem is that 
this tends to bail out poor performers. I be- 
lieve that the reserve should be determined 
based on the perceived risk of the element 
when the WBS is formulated. The manager 
of the element should then be held responsi- 
ble for the stewardship of the reserve. In 
order for this to work, some sort of reward 
system must be established for the manager 
who does not spend the reserve. In any case, 
it would be prudent to maintain some re- 
serve at the central level for those things 
that cannot be anticipated. Just to keep the 
system honest, a very simple tracking pro- 
gram can be established to follow the expen- 
diture of the reserves at the WBS element 
level after the fact. I would like to see an in- 
depth study done on this subject. 

Traps and Pitfalls 

So far we have talked about where cost fits 
into the program management and systems 
engineering processes. There are a few areas 
that may catch the program manager unpre- 
pared and a few ideas that may be used to 
make life a little easier in the future. It may 
not be possible to implement all of them, but 
it is worth a try. 

Buying in. If you are involved in the selling 
of the program, the easiest trap to fall into is 
underpricing the program. Despite stories to 
the contrary, I do not believe that this is a 



121 



READINGS IN SYSTEMS ENGINEERING 



matter of deliberate low bidding. Although I 
once heard a distinguished gentleman say 
that we do business the old fashioned way, 
we do underbid and make up on change re- 
quests. The fact is that every program man- 
ager I have ever met was convinced that he 
or she could do it for less than the past record 
would suggest. Unfortunately, this usually 
involves changing the way we do business. I 
believe that there are less expensive ways, 
but you should tackle this one at your own 
risk and only if you have the support of the 
very top of the organization. The systems en- 
gineer must be the conscience of the program 
manager during this period. 

Design to budget. Let us assume that we 
have completed a perfect Phase B and that 
everything is in place, including the rate of 
expenditure by year. It is a virtually certain 
that two things will happen. First, with elo- 
quent rationales and spreadsheets by the 
ton, the various element managers will find 
a need to increase their funding allocation. 
One favorite argument will be that the sell- 
ers of the program, who are no longer in 
charge, will be blamed for not understanding 
the problem. In addition, Congress may add 
a requirement or two. Second, the budget 
will be cut in the Agency, at the Office of 
Management and Budget (OMB), and finally 
in Congress. At this point, the intricate pat- 
terns of dependency between performance, 
cost and schedule begin to unravel. In the 
first year, this is not devastating because 
you can always delay bringing the prime 
contractors on board. But by the time they 
arrive, the trap has been set for the most in- 
sidious form of management, design to bud- 
get. Unfortunately, a fact of life is that very 
few research and development (R&D) pro- 
grams have multi-year funding, and annual 
budgets will be less than planned. The net 
effect is that program costs will escalate, and 
enormous pressures will attempt to bring 
down the annual funding. The first remedy is 
to stretch the schedule, and the second is to 
reduce the scope of the program. You will no 



doubt find yourselves in this position, and 
you will receive a great deal of advice from 
the nonparticipants, but you should beware 
of "descoping." A cursory examination of the 
cost models will show that in the manned 
programs, only 20 cents of every dollar go to 
hardware. (In the unmanned programs, the 
number is closer to 40 cents.) Once the man- 
agement structure is in place and the con- 
tracts have been awarded, virtually all of the 
other costs are fixed or very difficult to 
reduce. Take out all the content and the pro- 
gram cost will still be 80 percent of the 
estimate! The lesson is that if you are forced 
to remove content, you should be sure to take 
out every cent that is associated with that 
content: prime wraps, nonprime wraps, test 
beds, personnel, and, if necessary, the kitch- 
en sink. It will be difficult to find, but it will 
be worth the effort. If this were a mystery 
novel, it might well be called "The Case of 
the Missing 80 Percent." Where does it all 
go, and why is it only 60 percent for 
unmanned programs? Much of this is valid 
and accounts for systems engineering and 
integration at all levels of the program, 
including test and evaluation, operations, 
and many other things. But it also accounts 
for duplication of test facilities, overlaps 
between assignments, management style, 
inefficiencies and a host of hidden costs asso- 
ciated with maintaining the institutions 
that are often invisible to the program man- 
ager. The systems engineer is responsible for 
ferreting out the good from the bad. It is a 
simple fact that the first one percent reduc- 
tion in these wraps (80 percent to 79 percent) 
increases the amount of hardware by five 
percent (20 percent to 21 percent)! A 20 per- 
cent improvement in the wraps (80 percent 
to 60 percent) results in a doubling of the 
hardware (20 percent to 40 percent) or cut- 
ting the program costs in half for the same 
amount of hardware! "Thar's gold in them 
thar hills." 

The UPN System. The NASA budget is 
prepared and submitted using a system of 



122 



COST CONSIDERATIONS IN THE SE PROCESS 



breakdowns known as the unique project 
number (UPN) system. All parts of the agen- 
cy are required to report their annual needs 
on the basis of this system, including the pro- 
gram offices. From a program point of view, 
a fatal flaw in this process is the numbering 
system, which generally describes functions 
rather than end items and is therefore not in 
consonance with the principles of a WBS sys- 
tem. It is essential that the program man- 
ager be able to trace the equivalence of the 
UPN number and its corresponding WBS 
element. This will require a joint effort 
between systems engineering and the pro- 
gram control people. Without this traceabil- 
ity matrix, the program manager will not 
know what is being asked for or where the 
money is going. Too often the UPN number 
is perceived as directly equivalent to the 
WBS element, but this is very seldom the 
case unless the WBS is not end-item orient- 
ed. (The latter happens more often than it 
should.) One way to avoid this situation is to 
make the annual budget call for the program 
using the WBS system and then translate it 
to the UPN system for the purpose of aggre- 
gating the total NASA budget. I have never 
seen this happen. 

The cost of operations. I mentioned earlier 
that the costs of operations are now about 50 
percent of the NASA budget. This is partly 
due to the increase in the operational life of a 
program and to the fact that we have not 
learned to design systems for operability. It 
has not been necessary in the past. It is also 
true that the productivity of the operations 
infrastructure has not been high on the pro- 
gram manager's list. If we are to reduce total 
program costs, which are vital to the Agency 
and to the program, it is time to strike a new 
level of cooperation between these two nor- 
mally separate parts. The program and the 
systems engineer must assume a large part 
of the responsibility. 



THE INSTITUTION AND THE PROGRAM 

Although not directly related to the systems 
engineering process, a number of things bear 
directly on the program and have a major 
effect on the ability to perform the various 
program functions. These generally concern 
the relationship between the program and 
the institution. NASA was originally 
established using the resources of the Na- 
tional Advisory Committee for Aeronautics 
(NACA), an aeronautical research organiza- 
tion that was seldom involved in large 
development programs. The budget was rel- 
atively small, and there were few contrac- 
tors. In fact, all contracts were signed at the 
Washington office, the NACA equivalent of 
Headquarters. It quickly became apparent 
that, in addition to the research centers, a 
development center was needed. The God- 
dard Space Flight Center (GSFC) was estab- 
lished to perform this function. This was 
rapidly followed by the Lyndon B. Johnson 
Space Center (JSC) in Houston, the George 
C. Marshall Space Flight Center (MSFC) in 
Huntsville, and the Jet Propulsion Laborato- 
ry (JPL) in Pasadena. Almost immediately, 
GSFC and JPL became responsible for multi- 
ple unmanned programs, which were largely 
contained within a single Center, and JSC 
and MSFC became responsible for multi- 
center manned programs. In both cases, 
program offices were established and the 
Centers provided the resources, both person- 
nel and facilities, to support the program. 
With the exception of JPL, which was a fed- 
erally funded research and development 
center and operated outside the civil service 
system, all NASA personnel and basic facili- 
ties are funded separately from the programs 
in line items known as Research and Pro- 
gram Management (RPM) and Construction 
of Facilities (CoF). Program-specific facili- 
ties are funded by the program and these 
facilities are most often operated by support 



1 23 



READINGS IN SYSTEMS ENGINEERING 



contractors, also funded by the program. 
This system was established so that the pro- 
grams would be managed by government 
personnel who would rotate from program to 
program and carry their experience with 
them. This worked very well until the late 
1960s when the budget began to fall rapidly, 
and there was a significant reduction in 
NASA personnel. By the early seventies, 
both the budget and the number of personnel 
had been cut in half, but the number of 
Centers remained essentially the same. The 
cost of maintaining the institution could not 
longer be sustained by the RPM and CoF line 
items. The solution was to tax the programs 
based on the number of personnel that were 
applied to the program. Unfortunately, the 
program manager does not decide how many 
people should work on the program, which, 
by tradition, is the responsibility of the 
Center director. Neither does the program 
manager participate in determining the 
level of the tax. These decisions, again by 
tradition, are made by the comptroller. 

Maintaining the Institution 

Unless the basic system of funding personnel 
is changed, the programs will most certainly 
be responsible for funding some of the insti- 
tutional costs that are not related to the pro- 
gram; the RPM budget will never be allowed 
to grow to compensate for this. The question 
is rather how large the institution needs to 
be to support the program and how that deci- 
sion is made. I mentioned earlier that the 
WBS should represent the totality of the 
program and should always describe deliver- 
ables; this problem runs counter to that 
principle. I believe that the solution lies in 
accepting this cost for what it is, negotiating 
the level of tax with the program manager 
for the duration of the program, and taking 
it off the top each year. It may not be control- 
lable in the normal sense, but at least it is a 
known number. 

Personally, I believe that the Agency 
would be better served if the development 



centers were managed using an industrial 
funding system similar to JPL and many 
other government facilities, including the 
Navy labs. But until that happens, it will be 
necessary to find some balance between the 
institutional and program needs. 

Management Stability 

Every program will change management 
during its life cycle. The common practice in 
NASA has been to make these changes delib- 
erately between phases. It is not uncommon 
to see as many as four different managers 
during a program, including a specialist in 
closing off completed programs. The positive 
side to this is that it is possible to match the 
needs of each phase of a program to the 
special capabilities within the agency. The 
negative side is that each manager has a 
different style, each program has different 
management needs, and often these do not 
match when the change-over occurs between 
phases. One way is not always right and an- 
other always wrong, but each is different, 
and changes even in management style can, 
and usually do, increase the cost of the pro- 
gram. The secret then is to stick with a team 
as long as possible, particularly the systems 
engineering team, something that is easy to 
say and difficult to do in these times of 
declining internal expertise and increasing 
retirements. 

The Tyranny of Experience 

Too often, you will find resistance to change 
in the way things are done. "We have always 
been successful (measured by performance) 
doing it this way, and its very dangerous to 
change winning ways." "If it ain't broke, 
don't fix it." "You get no credit for an on-time 
failure." All true and at the same time, de- 
structive to valid new ways of doing busi- 
ness, especially when it comes to introducing 
more efficient or less expensive ways. When 
the space program started, we had no 
experience and what followed was the most 



124 



COST CONSIDERATIONS IN THE SE PROCESS 



innovative and exciting period in the history 
of high technology programs. But now we 
have all that experience, and it has become a 
burden. By all means, you should keep the 
wise heads around (they may still save you), 
but take advantage of the explosion in new 
technologies and capabilities, which allows 
for things that we could only dream of 30 
years ago. You should be careful before you 
introduce a change, but you should not dis- 
miss it out of hand. 

Does it Matter? 

We have been in the civilian space business 
for almost 40 years, and time after time we 
have shown that we can rise to any challenge 
and lead the competition, provided we have 
the resources. Time and time again the Fed- 
eral Government has provided the resources. 
We have been the envy of the world. We have 
written the book on the subject, both from a 
technical and a management sense. 

Until now, it was enough to know that we 
were the best. There was no established 
competition, most of the money was spent 
internally, and cost efficiency was second to 
performance. Some have characterized it as 
a Works Projects Administration (WPA) for 
the technologists! The problem is that in this 
era of budget deficits and trade deficits, 
there is not enough discretionary money to 
go around. Even without international com- 
petition, it would be imperative to get more 
out of our research dollars. The trouble is 
that we have learned profligate ways, as 
neither the government nor the contractors 
give rewards for cost efficiency. And while 



we were basking in this glory, the rest of the 
world has been catching up. They have been 
reading the book, and the competition, sup- 
ported by their governments, is getting good 
and fierce. 

But there is a difference; the competition 
believes that the space business is here to 
stay. I said space business, but I meant com- 
merce, and in commerce cost efficiency is 
paramount. Do we still want to stay at the 
top, or are we ready to leave it to the rest of 
the world? Are we prepared to do what is 
necessary to stay in the game? After all, it's 
only a space program. Does it matter? You 
bet! 

CAN ANYTHING BE DONE? 

In this paper, I have attempted to show 
where cost fits into the space program's engi- 
neering and management business. A combi- 
nation of things have placed cost at the 
bottom of the priority ladder except in mat- 
ters of the inexorable annual budget. There 
are many ways to improve cost efficiency, 
some of which are available to the program 
manager. In the long run, it will take a con- 
certed effort by all of us to make a difference. 
The Executive branch and Congress, togeth- 
er with industry and academia, must work 
as before, when we perceived that we were 
second. In the meantime, I hope that I have 
been able to give the budding systems engi- 
neer and program manager a few tips to do 
something about the problem of cost consid- 
erations. We can only do something about it 
if we want to! 



125 



USER REQUIREMENTS 

— ~~ _ ~ ~ ~ T»3^468 ? 

Systems Engineering and the User: Incorporation of 
User Requirements into the SE Process 5^-j / 

byJohnE.Naugle /^Tg 5"7y 

assure everyone— the scientists, the projectp 
management, the Center management and\ ' 
NASA Headquarters— the scientific objec- 
tives and requirements have been incorpo- 
rated into the systems engineering process. 

This paper is organized into four parts. In 
the Gestation Phase, I describe the process of 
starting a new mission and establishing its 
rough boundaries. Next I show how the sci- 
entific experiments are selected. Then we en- 
ter the Preliminary Design Phase, where we 
incorporate the scientist's instruments into 
the systems engineering process. Finally, I 
show how the Preliminary Design Review 
(PDR) assures NASA management and the 
scientists that the scientific requirements 
have been incorporated into the systems en- 
gineering process to everyone's satisfaction. 

Throughout I emphasize the dual role of 
servant and master that the systems engi- 
neer plays with respect to the scientist and 
the project manager. As servant, the systems 
engineer works to assure the scientists that 
the project will meet the requirements of 
their experiment and their instrument; as 
master, the systems engineer works to as- 
sure the project manager that the scientists 
and their instrument will meet the require- 
ments of the project. A glossary of terms 
appears at the end of this paper. 

I emphasize the need for the systems en- 
gineering process to consider all of the pieces 
of hardware that the mission will require 
and all the activities that must be conducted 
during the entire mission. It is easy, in the 
early phases of a mission, to focus on the 
spacecraft and the instruments and to ignore 
or push into the background those activities 
and facilities that will be needed later or are 
the responsibility of other offices. The associ- 
ate administrator for the Office of Space Sci- 
ence and Applications needs to know, before 
committing to undertake a mission, that the 



A scientific mission goes through two 
distinct stages, each with its own special 
requirements for systems engineering. A 
division director at NASA Headquarters, as- 
sisted by a program chief and a program 
manager, conducts the first stage. These 
three people, assisted by committees and 
working groups, define the mission, formu- 
late its objectives, establish its rough 
boundaries and manage the selection of the 
experiments. The division director practices 
a rough and ready kind of systems engineer- 
ing, balancing the desire of the scientist for 
the most complex sophisticated instrument 
possible against the desire of the Office of 
Management arid Budget and Congress to re- 
duce the NASA budget. If the division direc- 
tor's systems engineering is done well, the 
mission will be supported and scientific re- 
sults obtained. If, on the other hand, the sys- 
tems engineering is poor, the mission may be 
canceled either because the scientific com- 
munity concludes the scientific objectives do 
not merit the cost or because the Office of 
Management and Budget or Congress thinks 
the cost is too high. 

After the experiments have been selected, 
the action shifts from Headquarters to one of 
the NASA Centers, and the second stage be- 
gins. A project manager, assisted by a project 
scientist and supported by an engineering 
and a financial staff, is in charge of the sec- 
ond stage. The second stage begins with the 
preliminary design phase and ends when the 
last scientific paper has been published. All 
the hardware for the mission is constructed, 
tested and operated in the second stage. 

Systems engineers incorporate the scien- 
tists and their instruments into the systems 
engineering process during the preliminary 
design phase. At the conclusion of the 
preliminary design phase, the project man- 
ager conducts a preliminary design review to 

PRESIDING PAGE BLANK NOT FJLNfcD 



^U™~^w^>u^ui m*M 



127 



READINGS IN SYSTEMS ENGINEERING 



entire mission has been thought through, 
that the facilities will be available, and that 
the funding is adequate to procure all the 
flight and ground-based hardware and to pay 
for all the work that will be required. 

I arbitrarily end this paper with the PDR. 
Clearly there will be continuous interaction 
between the scientists and the systems engi- 
neers throughout the remainder of the mis- 
sion. However, the main purpose of the PDR 
is to see that the user requirements have 
been properly incorporated into the system. 
Other papers discuss the role of systems en- 
gineers in later phases of the mission. 

The Gestation Phase 

If we are to successfully incorporate user 
requirements into the systems engineering 
process, we need to know how NASA creates 
a new mission and establishes its principal 
boundaries; we need to know who selects the 
scientific instruments and when. 

New missions get started in a variety of 
ways. A person with a new idea may initiate 
a new space mission. A scientist at a NASA 
Center or a university may make a discov- 
ery, ask a new question or invent a new 
instrument. An engineer at a NASA Center 
or in industry may invent a new control sys- 
tem enabling more precise measurements to 
be made. A technology may mature. 

New missions have been started this way 
in the past, but now, more and more, new 
missions either come from a group of people 
convened by NASA specifically to think 
about new missions or are logical follow-ons 
to existing or completed missions. The 
Hubble Space Telescope was started as a 
logical step after the Orbiting Astronomical 
Observatories. Its scientific objectives were 
laid down in 1964 during a summer study 
conducted for NASA by the National Acade- 
my of Sciences Space Science Board. The 
Advanced X-Ray Astronomical Facility con- 
tinues the x-ray observations begun with 
Uhuru and High Energy Astronomy Obser- 
vatory. Ulysses continues the study of the 



Sun begun by HELIOS. Some missions are 
precursors to later more complex missions. 
Surveyor and the Lunar Orbiter were pre- 
cursors to Apollo. The Lunar Observer and 
the Mars Observer, in addition to increasing 
our knowledge of the Moon and Mars, will be 
designed to provide data needed to design 
manned lunar bases and manned missions to 
Mars. 

Applications missions result from a need 
for additional coverage, better resolution, 
more complete coverage of the electromag- 
netic spectrum or a new operational space- 
craft. 

Although there is no set process by which 
a new mission gets started, once it begins, 
there is a fairly predictable process by which 
it moves from concept to design to flight. 
Usually a new mission gets underway when 
a dedicated advocate devotes the time and 
energy required to get the idea accepted 
within NASA. This advocate may be located 
at a Center, a university, another federal 
agency, an aerospace company or in NASA 
Headquarters. The advocate prepares a 
rough design of the spacecraft and a list of 
potential instruments. With these in hand, 
the advocate buttonholes scientists, engi- 
neers, Center and Headquarters personnel to 
persuade them to become supporters of the 
mission. At a Center, the advocate may boot- 
leg some feasibility studies at the Center be- 
fore taking the concept to Headquarters. At 
some point, the advocate must describe the 
mission to the director of the appropriate di- 
vision in NASA Headquarters and persuade 
the director that NASA should undertake 
the mission. If it is an astronomy mission, 
the advocate must convince the director of 
the Astrophysics Division; if a planetary 
mission, the director of the Solar System 
Exploration Division; if an Earth science or 
applications mission, the director of the 
Earth Science and Applications Division. 
The director may ask the advocate and 
supporters to describe the concept to the ap- 
propriate NASA advisory committee or to a 
summer study sponsored by the Space 



128 



USER REQUIREMENTS 



Science Board. The director may ask a 
Center or a contractor to make a feasibility 
study of the mission before committing to the 
5- or 10-year effort that is required to get a 
new mission underway. The advocate may 
appeal to the associate administrator for the 
Office of Science and Applications to tell a 
reluctant division director to undertake the 
mission, but until the director is convinced 
that the mission is worth doing, it is almost 
impossible to get a new mission started. 

Once the division director becomes enthu- 
siastic about the mission, it will be incorpo- 
rated into the director's long-range plan, and 
the groundwork will be prepared for approv- 
al by NASA senior management, Office of 
Management and Budget and Congress. 
Once the division director includes a descrip- 
tion of the mission in the division's advanced 
program, the advocate's work is over; the 
mission takes on a life of its own. The divi- 
sion director provides funds for studies and 
for research and development and may pro- 
vide funds to several scientists to begin work 
on potential instruments for the mission. 

Applications missions are started by an 
agreement between the division director at 
NASA Headquarters and the division direc- 
tor's counterpart at the National Oceanic 
and Atmospheric Administration, or which- 
ever agency needs the mission. They agree 
that the mission has merit and that they 
should begin to jointly plan for the mission. 
Agreements are made as to what research 
and development will be conducted, who will 
conduct it, and which agency will pay for it. 
They will produce a mutually acceptable 
plan of action by which they will seek ap- 
proval and funds. 

SETTING THE BOUNDARIES 

The scientific or applications objectives 
establish some but not all of the boundaries 
of a space mission. Other factors, such as the 
kind of transportation or the funds available 
help set the boundaries. Nonscientific 
criteria may have influenced the scientific 



objectives themselves. The initial diameter 
of the Hubble Telescope, four meters, was 
chosen in the mid-sixties because that was 
the diameter of the largest spacecraft that 
could be put inside the shroud of the Saturn 
V launch vehicle. Later, the diameter was 
reduced to 3.2 meters to take advantage of 
existing manufacturing, test and calibration 
equipment. The broad boundaries of the 
Viking mission were set by the capability of 
the Titan launch vehicle. As a matter of fact, 
in its formative stage, Viking was called the 
Titan Orbiter-Lander Mission. An earlier 
Mars orbiter-lander mission, Voyager, had 
been planned for a Saturn V; this big 
Voyager was canceled by Congress because it 
was too large and too expensive and because 
the scientists involved would not support 
such an expensive mission at that stage in 
the exploration of Mars. The competition 
with the Soviets also helped set the bound- 
aries for Viking. The scientific returns from 
Viking had to be sufficient to justify the cost 
of the mission, even though the Soviets 
might land a spacecraft on Mars before 
Viking got there. National needs— foreign 
policy, security, development of new technol- 
ogy and the maintenance of an institution or 
a capability— may influence the size, scale 
and timing of a mission. For a decade scien- 
tists unsuccessfully tried to persuade NASA 
to start a mission to study the interplanetary 
medium near the Sun. After President 
Johnson offered to undertake a joint space 
mission with Germany, it took NASA just 24 
hours to establish the HELIOS Mission to 
make a close fly by of the sun. The need to 
test the Titan IIIC launch before the launch 
of the Viking mission dictated that HELIOS 
would use the unproven Titan IIIC rather 
than the existing Atlas-Centaur. 

The actions of the members of Congress 
as they review, authorize and appropriate 
funds for a mission may help establish the 
boundaries of a mission. A key chairperson 
or a powerful committee member may decide 
that a particular mission is worth $500 
million but not $750 million; the chairperson 



129 



READINGS IN SYSTEMS ENGINEERING 



may decide to support a mission if it will in- 
crease employment or prevent the closure of 
a facility in the chairperson's district. 

Purists may argue that systems engi- 
neering should focus on technical constraints 
and need not take into account nebulous 
political and managerial constraints. Unfor- 
tunately, such constraints have been with us 
since the first time two people joined togeth- 
er to accomplish a task neither could do 
alone. Incorporation of such constraints into 
the systems engineering process is just as 
important as incorporating the purely tech- 
nical constraints. The division director, 
however, must keep the political and techni- 
cal constraints separate and should never 
attempt to justify a political constraint with 
some flimsy technical justification. If this 
happens, the rest of the participants in the 
mission will become confused and the 
division director will lose credibility. If the 
participants are kept straight, then later, if 
relief is needed from some such constraint, 
the division director will know who must be 
persuaded to get relief and the kind of justifi- 
cation that must be prepared. 

In the early days of NASA, with a power- 
ful administrator and with space exploration 
a major national goal, a project manager 
could ignore factors other than the scientific 
and technical requirements. Today, the as- 
sembly and maintenance of the necessary 
support for the mission are so difficult that 
these other factors may become as impor- 
tant, if not more important, than the re- 
quirements derived from the objectives of the 
mission. 

Out of this combination of political and 
technical considerations, the major bound- 
aries are set for a mission. The launch vehi- 
cle is selected, the project management 
center is picked, the trajectory and a 
tentative launch date identified, and a rough 
idea formed of the kind and number of 
instruments that will make up the payload. 
The availability of transportation and the 
support of the Office of Operations is estab- 
lished. A rough cost estimate is made. 



The Role of the Payload and the 
Technical Working groups 

As soon as the broad boundaries of a mission 
are established and the division director is 
confident about obtaining approval, the 
groundwork begins for selecting principal 
investigators — the scientists who will per- 
form the mission experiments. To make the 
selection, the division director first needs to 
know how many and what kind of instru- 
ments can be placed on the spacecraft, an 
analysis accomplished by two working 
groups: a Payload Working Group and a 
Technical Working Group. The Payload 
Working Group consists of NASA and aca- 
demic scientists from the scientific disci- 
plines involved in the mission, and the Tech- 
nical Working Group of system engineers 
and discipline engineers representing all the 
engineering disciplines and subsystems re- 
quired to design, build and operate the 
spacecraft. Working together, these two 
groups will design a trial payload that will 
accomplish the scientific objectives of the 
mission and a spacecraft capable of support- 
ing that payload. In this joint activity, we 
begin to incorporate the user requirements 
into the systems engineering process. 

The trial payload and the spacecraft 
emerge through an iterative process. The 
members of the Payload Working Group se- 
lect a trial payload — a group of instruments 
that accomplish the objectives of the mission. 
In assembling this trial payload, the Payload 
Working Group may invite scientists to come 
to a meeting to describe instruments they 
hope to fly on the mission. They may invent 
new instruments that are needed to accom- 
plish the objectives. The Payload Working 
Group will estimate the weight, volume, 
power and communication needs, and specify 
the orientation and stabilization require- 
ments for each instrument. One or more 
members of the Technical Working Group 
will attend the meetings of the Payload 
Working Group to help them develop the re- 
quirements and to design the spacecraft and 



130 



USER REQUIREMENTS 



bring back to the Technical Working Group a 
better understanding of the payload that is 
emerging. 

Meanwhile, the Technical Working 
Group will use the scientific objectives and 
broad constraints of the mission and design a 
hypothetical spacecraft for the mission. The 
Technical Working Group then takes the 
first trial payload prepared by the Payload 
Working Group and integrates it into the 
spacecraft. The two groups then hold a joint 
session where the Technical Working Group 
reviews the fit between the payload and the 
spacecraft, and the descriptions of changes 
that must be made either in the spacecraft or 
in the payload to make them compatible. 
Additional power may be required, the struc- 
ture of the spacecraft modified, or one or 
more instruments may have to be redesigned 
or eliminated. At the conclusion of the joint 
meeting, the two groups agree on the actions 
each will take during the next iteration with 
the mutual objective of making the payload 
and the spacecraft compatible. The Payload 
Working Group refines the payload and the 
Technical Working Group refines the design 
of the spacecraft. They meet again, review 
their progress, and decide on the next course 
of action. 

After a year or so of joint effort and two or 
three such iterations, a spacecraft and a 
payload will emerge that are satisfactory to 
both groups, the scientific community, the 
division director, the program manager, the 
program scientist and to senior NASA man- 
agement. The division director and the pro- 
gram scientists are now ready to select the 
actual scientists, and their instruments, for 
the mission. 

SELECTION OF THE SCIENTIFIC 
EXPERIMENTS 

The associate administrator for the Office of 
Space Science and Applications selects the 
scientists who do research in space. The divi- 
sion director, using an ancient procedure 
established in 1960, is in charge of all the ac- 



tivities associated with the selection process. 
People sometimes ask why the experiments 
are selected by an official at NASA Head- 
quarters rather than by one at the NASA 
Center that will manage the project. Others 
ask, why not use the instruments selected by 
the Payload Working Group for the trial pay- 
load and avoid all the time and energy that 
goes into the NASA selection process? Why 
NASA Headquarters, why not the National 
Academy of Sciences Space Science Board? 
These are good questions, and in some cases, 
the answer is easy: the particular method 
has been tried and found not to work; in oth- 
ers, the answer is not obvious and some ex- 
planation is necessary. 

History shows that the nation needs a 
vigorous broad-based space science program 
that involves many academic scientists. 
Academic scientists are a fertile source of 
new ideas, and their involvement rapidly 
disseminates the knowledge and experience 
gained in the space program to the next gen- 
eration of scientists and engineers. In addi- 
tion, the participation of academic scientists 
and their graduate students helps assure a 
continuing supply of space scientists and 
aerospace engineers. Academic scientists 
also form a strong, vociferous lobby for the 
NASA space science program. 

History also shows that NASA needs 
competent, creative scientists at its Centers 
to help conceive and design new missions 
and to work with the academic scientists 
who participate in NASA's missions. 

The academic scientists and the NASA 
scientists at the Centers fiercely compete for 
the right to conduct investigations on NASA 
missions. If an official at the Center respon- 
sible for the mission selected the principal 
investigators, then the academic scientists 
would feel that the Center scientists had an 
unfair advantage. The NASA scientists 
would be more familiar with the mission and 
therefore able to prepare better proposals. In 
addition, they would be colleagues of the 
Center people handling the selection. If the 
Space Science Board, made up entirely of 



131 



READINGS IN SYSTEMS ENGINEERING 



non-NASA scientists, handled the selection, 
then the NASA scientists would feel that 
academic scientists had an unfair advan- 
tage. By mutual agreement between NASA 
and the Academy, NASA scientists cannot 
serve on the Board because they would be 
providing advice to themselves. 

NASA procedures were formulated to re- 
duce the fears of these two groups of scien- 
tists and to encourage them to participate in 
NASA's space science program. NASA pro- 
vides a competitive process that assures 
equal access to NASA's space science mis- 
sions for all scientists, whether they are at 
universities, NASA Centers or in industry, 
and whether they are domestic or foreign 
scientists. Administrative scientists at 
NASA Headquarters, who are no longer con- 
ducting research and hence have no conflict 
of interest, conduct the selection process. 

The selection process proceeds through 
three stages. The first stage, the creation of a 
trial payload and the design of the space- 
craft, was discussed above. Next NASA 
issues an Announcement of Flight Opportu- 
nity (AFO) to scientists to inform them that 
NASA intends to proceed with the mission 
and invites them to submit a proposal to 
conduct experiments during the mission. 
After the proposals are submitted, they are 
evaluated, and a final selection is made by 
NASA Headquarters. 

The Announcement of Flight 
Opportunity 

As soon as the division director is reasonably 
sure that the mission will be approved by 
NASA senior management and by Congress, 
he or she will issue an AFO. The AFO speci- 
fies the objectives of the mission and invites 
scientists to propose investigations. It gives 
the ground rules for the proposals and the 
deadline for their submission. 

The AFO is a very important document. 
Several (sometimes 100 or more) teams of 
scientists will spend several months prepar- 
ing their proposals. Each team consists of 



scientists, engineers and financial analysts 
who use the information in the AFO to pre- 
pare the scientific, technical and financial 
parts of their proposals. Their written pro- 
posal is the final and generally the only 
opportunity they have to persuade NASA to 
select their experiment. (Sometimes com- 
peting scientists are invited to brief the re- 
viewers.) NASA bases its selection on the 
written proposal. Once the procedure is 
completed and the experiments are selected, 
it is almost impossible for a dissatisfied 
scientist to overturn the decision. Once the 
selections are made and contracts awarded, 
the principal investigator's team is legally 
obligated to produce the instrument, conduct 
the experiment and publish the results. 
NASA is legally obligated to provide funds 
and space on the spacecraft and to conduct 
flight operations and provide data to the in- 
vestigator. 

Careful preparation of the AFO is essen- 
tial. Large amounts of time and energy are 
required to prepare and evaluate the propos- 
als. If the information in the AFO is 
inadequate or wrong, experimenters may be 
discouraged from competing, or experiment- 
ers with instruments not suitable for the 
spacecraft may be selected, which can lead to 
costly overruns or schedule slips. 

The preliminary systems engineering 
done by the Technical Working Group and 
the Payload Working Group plays a crucial 
role in the preparation of the AFO. The AFO 
contains a description of the trial payload 
and the spacecraft generated by the two 
working groups. The AFO specifies the sub- 
systems planned for the spacecraft in suffi- 
cient detail so that the proposers can design 
their instruments to function in harmony 
with subsystems. The AFO must specify any 
special requirements for the instruments 
such as the need to keep electromagnetic 
interference, nuclear radiation levels or 
outgassing below specified levels. The ther- 
mal characteristics of the spacecraft are de- 
scribed, and the thermal specifications that 
the instruments must meet are included. 



132 



USER REQUIREMENTS 



The AFO specifies the date the proposals 
must be returned and in some cases limits 
the number of pages of a proposal to avoid 
getting lengthy proposals loaded with ex- 
traneous information. 

EVALUATING THE PROPOSALS 

The scientists send their proposals to the di- 
vision director at NASA Headquarters who 
is responsible for the mission. After receipt 
of all proposals, the division director forms 
two groups to assist in the evaluation. The 
first group, chaired by the program scientist, 
consists of scientists who are peers of those 
proposing experiments and who will evalu- 
ate the scientific and technical merits of the 
proposals and assign them a priority for 
inclusion in the mission. This group of scien- 
tists must be free of any legal conflict of 
interest with respect to any of the proposals, 
which is the reason why they cannot be cho- 
sen until all the proposals are in. The second 
group consists of engineers at the project 
management Center similar in membership 
to the Technical Working Group (in many 
cases it will be the Technical Working 
Group). This group will examine all the pro- 
posals to see if the instruments proposed are 
compatible with the spacecraft and judge 
whether the proposer has the team and the 
facilities required to carry out the investiga- 
tion. 

As soon as the division director has the 
proposals, copies are sent to both groups. 
After the two groups complete their work, 
they send the results of their evaluation to 
the division director. If an otherwise high 
priority investigation is incompatible with 
the spacecraft, the division director may ask 
the project team to conduct a short study to 
determine whether the instrument or the 
spacecraft can be modified to make the two 
compatible and, if so, to prepare an estimate 
of the costs involved. 

After receiving the evaluation made by 
the scientific working group and the project 
team, the division director and the chief 



scientists prepare a list of the principal 
investigators who they think are the best 
qualified to accomplish the objectives of the 
mission. Their selection is based on, and 
must be consistent with, the evaluations of 
the scientists and the project team. The divi- 
sion director is free to choose between two 
competing proposals that have been given 
the same priority by the scientists but is not 
free to pick a proposal that was given a lower 
priority. In other words, the division director 
must select a principal investigator whose 
proposal was placed in Category I by the 
scientific working group rather than pick an 
investigator whose proposal was placed in 
Category II, even though the Category II 
experiment might be cheaper or easier to 
integrate with the spacecraft. The instru- 
ments of the principal investigators selected 
must be certified compatible with the space- 
craft or the division director must have the 
results of a study that shows that the instru- 
ment or the mission can be modified to make 
the instrument compatible. Since each of the 
investigators selected has proposed a specific 
instrument, in the process of selecting the 
investigators the division director has also 
selected the suite of instruments that will 
make up the payload for the mission. 

After completing the list of principal 
investigators and the justification for their 
selection, the division director takes the 
recommendations to the members of the 
Space Science Steering Committee for their 
review and recommendation. 

the role of the space science 
Steering Committee 

The Space Science Steering Committee is 
composed of the directors and the deputies of 
each of the program divisions in the Office of 
Space and Applications. Traditionally, if the 
director is an engineer, the deputy is a scien- 
tist and vice versa. Thus the Space Science 
Steering Committee consists of roughly 
equal numbers of scientists and engineers 
and is capable of reviewing the merits of 



133 



readings in systems engineering 



investigators, the selection procedure, and 
all other technical and managerial aspects of 
the mission. It is chaired by the chief scien- 
tists in Office of Space Science and Applica- 
tions and reports directly to the associate ad- 
ministrator for that Office. 

The Space Science Steering Committee 
reviews the investigations that have been 
selected and the process by which they were 
selected. It reviews the investigations for 
their scientific and technical merit and for 
their compatibility with the spacecraft. If 
there are any objections or reservations 
raised by anyone about the payload, the 
Space Science Steering Committee reviews 
those objections. Normally the investigators 
chosen by the division director are accepted; 
however, if a member of the Steering Com- 
mittee objects to a selection or questions the 
selection process, then the Committee may 
send the division director back to prepare a 
different version of the payload. 

The Space Science Steering Committee 
serves as the court of final review for a pay- 
load. By its acceptance of the principal inves- 
tigators and their instruments, it certifies 
that, up to this stage, the user requirements 
have been properly incorporated into the sys- 
tems engineering process for the mission. 
After the members of the Committee com- 
plete their review, the chairperson sends 
their recommendations to the associate ad- 
ministrator of the Office of Space Science and 
Applications who approves the investigators. 
After approval of the investigators by the 
associate administrator, the only way to 
change an investigator or an instrument is to 
appeal over the head of the associate admin- 
istrator, to the deputy administrator or the 
administrator of NASA. Only once in the 
past 30 years has the decision of an associate 
administrator been reversed. In that case, 
NASA modified its selection procedure to 
facilitate the selection of investigators for 
the Apollo-Soyuz Mission. The chairperson of 
the Space Science Board objected to the 
change; NASA redid its selection and fol- 
lowed the normal procedure. 



The Associate administrator's 
Approval 

-i 

After the associate administrator approves 
the principal investigators, each of them is 
sent a letter to inform them of their selection 
and to give them any guidelines or qualifica- 
tions that come from the selection process. 
For instance, only a part of the investigator's 
proposal may have been approved or the 
investigator may have agreed to provide en- 
vironmental data to other investigators on 
the mission to aid them in the interpretation 
of their data. Funding for the mission may be 
limited; the associate administrator may 
direct each investigator to control costs very 
carefully and request that some aspect of the 
investigation be modified or excluded if it 
becomes apparent that the costs will exceed 
the funds allocated for the investigation. If 
the interest in the mission is high and the 
funds are limited or the resources of the 
spacecraft, such as the weight, power and 
telemetry, are very constrained, the associ- 
ate administrator may give provisional ap- 
proval to one or more investigators pending 
an analysis by the project to determine if the 
resources are available. 

The associate administrator's letter to a 
principal investigator is an informal con- 
tract between the associate administrator 
and the principal investigator that obligates 
the investigator to devote the time and ener- 
gy required to accomplish the objectives of 
the investigation. It obligates the associate 
administrator to proceed with the mission 
and provide the resources and assistance 
that the principal investigator will need. 

At the same time the letters are sent to 
the principal investigators, the associate ad- 
ministrator also sends a letter to the director 
of the Center responsible for managing the 
project. This letter notifies the director of the 
investigators selected and the qualifications 
or guidelines that have been given. The 
letter is accompanied by the authorization 
and transfer of funds that enable the project 
team to negotiate contracts with and fund 



134 



USER REQUIREMENTS 



the work of the principal investigators. This 
contract should provide for the support of the 
principal investigator and specify the work 
to be done during design, manufacture, pre- 
flight testing, operations, analysis of the 
data and publication of the results. The fun- 
ding for data analysis is normally carried in 
a separate line item in the Space Science 
budget and is transferred to the Center 
through a separate channel at a later date. 
Regardless of how the funding for the oper- 
ational phase is handled, the associate ad- 
ministrator should require that the project 
team provide for data analysis and publica- 
tion of the results in these contracts with the 
principal investigators. The incorporation of 
the user requirements into the systems engi- 
neering process will not be complete unless 
all phases of the mission are considered, 
including data analysis, interpretation and 
publication of the results. 

The Space Science Steering Committee's 
review and the associate administrator's ap- 
proval of the principal investigators com- 
plete those phases of the mission that are led 
by the division director at NASA Headquar- 
ters. Once the investigators have been 
selected, the focus of the work shifts from 
Headquarters to the Center, where the pro- 
ject manager and the project scientist take 
over the technical and scientific leadership of 
the mission. They are responsible for the 
final steps in the incorporation of the users 
requirements into the systems engineering 
process. 

assessment of the principal 
Investigators 

When the associate administrator for the 
Office of Space Science and Applications 
selects the principal investigators and au- 
thorizes the Center to negotiate contracts 
with them, the responsibility for working 
with the scientists is transferred from the 
division director and the program scientists 
at Headquarters to the project manager and 
the project scientists at the Center. Receipt 



of the letter triggers an intensive assessment 
by the project manager of each investigator 
and of the status of each instrument. This 
assessment should be completed prior to the 
beginning of preliminary design activity. 

The assessment is conducted by a team 
appointed by the project manager. The team 
consists of several engineers from the Cen- 
ter. A key member of the project manager's 
review team is the project scientist, who, 
among other tasks, serves as the communi- 
cation link between the investigators and 
the project team. 

THE ROLE OF THE PROJECT SCIENTIST 

The Center director, with concurrence of the 
Office of Space Science and Applications as- 
sociate administrator, appoints the mission's 
project scientist. This project scientist has a 
powerful role during a scientific mission, 
quite different from that of the project man- 
ager and, at this stage, equally important. If 
the project scientist and the project manager 
have a conflict they cannot resolve and that 
may affect the mission's scientific outcome, 
the project scientist is expected to carry the 
case to Center management and, if it is a 
good case, to prevail. 

The project scientist should have as vest- 
ed an interest in the scientific success of the 
mission as the one who conceived the mission 
or as an investigator on the mission. As an 
experienced space scientist and person who 
has conducted investigations in space, the 
project scientist should understand what 
information the project needs from the prin- 
cipal investigator in order to conduct the 
mission and should be able to accurately 
communicate those requirements, and the 
reasons for them, to the scientists. The pro- 
ject scientist should understand the techni- 
cal requirements submitted by the principal 
investigators and be able to communicate 
them to the project. In addition, the project 
scientist should be able to judge which of the 
requirements of the principal investigator 
are mandatory and which are only highly 



135 



Readings in systems engineering 



desirable so that the resources of the project 
are not squandered. Conversely, the project 
scientist should be able to sort out the highly 
desirable from the mandatory requirements 
of the project manager so that unnecessary 
constraints, reporting requirements or re- 
views are not placed on the principal investi- 
gators. Clearly, the project scientist must 
have the confidence of the project manager 
and the investigators on the mission in order 
to succeed. The assessment of the principal 
investigators provides an excellent opportu- 
nity for the project scientist to become a reli- 
able representative of the scientists to the 
project team and of the project team to the 
scientists. 

People ask, why all this concern about the 
communication channel between the project 
and the investigators? Why can't the project 
manager deal with the investigators just as 
one would with the person responsible for 
any other subsystem on the spacecraft? 
Early experience in space science showed 
that a project manager who was not a scien- 
tist, or who did not have a strong competent 
project scientist working with him or her, 
usually got into one of two kinds of trouble. 
Either the project manager regarded the 
scientists as all powerful and gave in to all 
their whims, thereby driving the costs of the 
mission out of sight, or the project manager 
regarded the scientists as overly bright 
children and overrode their legitimate re- 
quests, thus causing their instruments to fail 
or forcing the scientists to complain to Cen- 
ter management or NASA Headquarters and 
try to get the project manager replaced. 

Fact Finding 

The initial assessment of each principal in- 
vestigator by the project team is the most im- 
portant part of the incorporation of the user 
requirements into the systems engineering 
process of a mission. The primary purpose of 
the assessment is to determine the technical 
requirements of the instruments and their 
compatibility with each other and with the 



spacecraft and the operational equipment. In 
addition, it provides the project manager 
with the first opportunity to determine the 
experience and capability of each principal 
investigator and of the team, and to assess 
whether the investigator's institution can 
and will provide the support that will be 
needed. 

The assessment begins with "fact find- 
ing," a systematic effort by the review team 
to collect information about the investiga- 
tors. The team conducts its review at the in- 
vestigator's institution, rather than bringing 
the investigator and the team to the Center. 
A visit to the institution enables the review 
team to not only examine the laboratory 
model of the instrument, but also to review 
the calculations and test results that support 
the design. The team can review the facili- 
ties that will be available to investigators to 
develop, test and calibrate the flight instru- 
ments. If the investigator plans to have most 
of the work done by a contractor, then the 
review team conducts a similar review at the 
contractor's plant. 

The review should cover all the elements 
that are required by the investigator to com- 
plete the objectives of the experiment. By 
"all the elements," I mean all the pieces of 
hardware, all the facilities, all the testing 
gear that will be required, and all the work 
and the people that will be required to enable 
the investigator to design, build, test and fly 
the instrument. In addition, the review 
should identify all the computers, all the pro- 
grams and all the software that the investi- 
gator will require to analyze the data and 
publish the results. The review should cover 
the entire mission, from design and develop- 
ment, to testing and calibration, to place- 
ment of the published results and of the data 
in the archives. The plans, scheduled actions 
and funding requirements as a function of 
time are key elements to be reviewed. The 
impact of project requirements on the inves- 
tigator or the instrument should be covered 
in the review. Throughout the review, its 
two-way nature must be emphasized. The 



136 



USER REQUIREMENTS 



purpose of the review is to determine what 
the investigator requires of the project and to 
inform the investigator of the requirements 
of the project. 

The review begins with information and 
data collection by the team. The team must 
collect information on the technical re- 
sources on the spacecraft that the instru- 
ment requires such as weight, telemetry, 
band width, volume, power, commands and 
thermal control. 

The team must collect data on the engineer- 
ing constraints imposed by the instrument 
on the spacecraft, including but not limited 
to: 

Location of the instrument 

Look angle and field of view 

Pointing and stabilization required 

Operational requirements 

Special treatment during testing, launch, 

and operations 
Limitations on vibration and shock 
Limitations on stray electromagnetic 

fields 
Limitations on material surrounding the 

instrument 
Limitations on outgassing. 

The team needs to know the facilities 
that will be required by the instrument and 
their availability, either at the investigator's 
institution, the contractor, or at the field 
center or its contractors, including but not 
limited to: 

Vacuum chambers 
Shock and vibration tables 
Solar simulators 
Computers 

Special test and calibration facilities 
Special data handling and analysis 
facilities. 

The team must collect information and plans 
for the funding, manpower and management 
capability that will be required by the inves- 



tigator at the host institution and by the 
project team to monitor the work of the 
investigator. 

Obviously, not all of this data will be 
available at this first review. However, 
where information is not available, the need 
should be established and the project man- 
ager and the principal investigator must 
formulate a mutually acceptable plan as to 
who will generate the information and on 
what schedule. 

This initial data gathering phase pro- 
vides an excellent opportunity for the project 
manager and the systems engineers to assess 
the capability of the principal investigator 
and the team. NASA policy makes the prin- 
cipal investigator, responsible for all phases 
of the investigation, beginning with the de- 
sign of the instrument, continuing through 
to the delivery of a calibrated, tested and 
flight worthy instrument, and culminating 
in the publication of the results. During the 
review, the principal investigator should 
demonstrate understanding and the ability 
to discharge this responsibility and should 
be able to describe how to conduct the day- 
by-day work of the team. The principal 
investigator should state whether the day- 
by-day work of the team will be under the 
investigator's direction or whether a man- 
ager will be appointed to direct the work. If a 
manager is appointed, do the principal inves- 
tigator, the manager and the project 
manager all understand the limits of the 
authority of the manager? What decisions 
can be made by the manager and which ones 
must go to the investigator? Has the investi- 
gator delegated sufficient authority to the 
manager so that decisions can be made and 
the work can be kept on schedule? How does 
the principal investigator plan to oversee the 
work of the manager? Does the investigator 
plan to attend certain key reviews to see how 
things are going? Will the manager give 
weekly reports? 

The project manager and the principal 
investigator should agree on which reviews 
the investigator will attend and which can 



137 



READINGS IN SYSTEMS ENGINEERING 



be delegated to the manager. They also need 
to agree on how they will resolve disputes 
that will arise between the principal investi- 
gator's manager and the project manager. 

If the principal investigator plans to han- 
dle the day-to-day operations, another set of 
questions needs to be asked. Is the investiga- 
tor prepared and able to spend the time and 
energy to handle the daily work? Is the in- 
vestigator prepared to travel to the Center or 
to a contractor when reviews must be held 
and decisions need to be made? Is the investi- 
gator prepared to give up other research dur- 
ing the development of the instrument? 

Appointing a good project manager is 
generally better for the investigator and the 
team. The project manager can concentrate 
on the daily activity of managing the team 
and the investigator can focus on meeting 
the requirements that will be levied by the 
project manager and the team. 

The review team needs to ask other ques- 
tions. Is the investigator's team adequate for 
the task? Have they planned their work and 
laid out a sensible schedule? Are they cooper- 
ative and forthright about the status of their 
instrument? Are the kinds of engineers and 
technicians that will be needed either on the 
investigator's team or at the contractor? Has 
the investigator done a good job estimating 
the costs as a function of time? Has a reserve 
been allowed for unforeseen problems, and if 
so, have criteria and a schedule been laid out 
for its use? Any weakness in planning or 
management at this stage, if not corrected, 
will inevitably result in more serious prob- 
lems later in the project. 

The analysis of the strengths and weak- 
nesses of a principal investigator's team 
serves an important function in the incor- 
poration of the user requirements into the 
systems engineering process. If an investiga- 
tor has a competent team and adequate 
facilities and equipment, the project man- 
ager can reduce the monitoring require- 
ments for that investigator. The investigator 
can reduce the time allocated for testing and 
integration and may waive certain tests. On 



the other hand, if the investigator has a 
weak team or inadequate facilities, then the 
project manager has to lay out a project plan 
and a schedule that takes this weakness into 
account. Additional money must be set aside 
to cover overruns. Provisions for additional 
monitoring must be made and additional 
time for testing and integration must be 
allowed. An engineer from the project may 
be assigned to aid the investigator. The in- 
vestigator is placed on the list of the project's 
"Top Ten Problems," thereby alerting the 
Center management and Headquarters of 
the problem. Any management or technical 
problems unearthed in this initial assess- 
ment should be treated just as thoroughly 
and just as promptly as the failure of any 
subsystem would be treated later in the 
schedule. Prompt action at this stage will 
prevent many hardware problems from aris- 
ing later when there is less time and less 
money to resolve them. 

The review of each principal investigator 
culminates in the negotiation of a contract 
between the Center and principal investiga- 
tor, whereby the investigator is to produce a 
flight instrument using funds provided by 
the Center. At the conclusion of the assess- 
ment process, a principal investigator will 
have two contracts: one with the associate 
administrator of the Office for Space Science 
and Applications to accomplish the objec- 
tives of the experiment proposed, and the 
other with the project management center to 
produce an instrument that is ready for 
flight. A principal investigator who thinks 
that a Center decision will jeopardize the 
investigation has the right to appeal the 
decision directly to the associate administra- 
tor of the Office for Space Science and Appli- 
cations. This appeal channel is rarely, if 
ever, used. 

The Systems Engineering Process 

Once the review team has completed its fact 
finding and its assessment of the investiga- 
tor's capability, the systems engineers are 



138 



USER REQUIREMENTS 



ready to complete the conventional systems 
analysis of the system. The information the 
review team has collected enables them to 
incorporate the user requirements into that 
process. 

By this time, all the broad boundaries of 
the mission are established; the investiga- 
tors have been selected, a preliminary design 
of the spacecraft is available, the transporta- 
tion system is specified, the total cost of the 
mission has been set (or a ceiling placed on 
the total cost) and a preliminary launch date 
scheduled. 

If there is no hard fast launch date, then 
the launch schedule may become a variable 
in the systems analysis and shifted forward 
or back to reduce costs or improve the scien- 
tific return of the mission. If it is a planetary 
mission, however, the launch date is not a 
variable but is rigorously set by planetary 
dynamics; the role of the systems engineer is 
to identify the decisions that must be made 
and the actions that must be taken to assure 
the sanctity of that launch date. 

In the case of a high priority scientific 
mission, such as Viking or the Hubble Space 
Telescope, the scientific objectives may be 
the primary constraint. The systems engi- 
neer can adjust the launch vehicle, the 
launch date and the total cost to meet the 
scientific objectives. 

For most missions, however, the primary 
constraints will be technical and financial. 
The launch vehicle may be specified; there 
may be a cap on the funding, certain subsys- 
tems may be specified and in many cases the 
spacecraft itself will be specified. In such 
highly constrained missions, the only vari- 
ables the systems engineer has to work with 
are the number and complexity of the scien- 
tific instruments that can be accommodated. 
For such highly constrained missions, the 
associate administrator of the Office of Space 
Science and Applications will usually select 
a core payload that is certain to be accom- 
modated and then add one or more in- 
vestigations to be included if the systems 
analysis shows they can be accommodated. 



In this highly constrained case, the systems 
engineer takes the requirements of the core 
payload and the existing constraints 
and.working closely with the project scien- 
tist and the principal investigators, makes a 
number of tradeoff studies to determine the 
maximum number of investigations that can 
be accommodated and the maximum amount 
of scientific information that can be collect- 
ed. 

The objective of the systems engineering 
effort at this stage is to plan the entire mis- 
sion, establish the specifications for the in- 
struments and the spacecraft, lay out a 
schedule for all the activities of the mission, 
establish milestones for completion of major 
activities, schedule the testing and integra- 
tion work, set a launch date, estimate the 
cost and lay out a funding plan for the entire 
mission. The systems engineers identify any 
technical conflicts that exist between instru- 
ments or between an instrument and the 
spacecraft. Where they find conflicts, they 
identify the options available to the project 
to solve them, conduct tradeoffs between the 
options and recommend the option that they 
think will produce the greatest scientific 
return for the lowest cost. 

As the systems engineers conduct their 
analyses, there is a continuous iteration pro- 
cess that takes place throughout the project 
and among the investigators. Different loca- 
tions of the instruments on the spacecraft 
are studied and discussed with the investiga- 
tors to determine which are best. Tradeoffs 
may have to be made between the value of 
adding an investigation and adding more 
power or more telemetry bandwidth for the 
core payload. In rare instances, the systems 
analysis may show that additional resources 
are available on the spacecraft; then trade- 
offs are made to determine how to allocate 
the resources among the investigators to bet- 
ter accomplish the scientific objectives. 

Many complicated tradeoffs are made at 
this stage in a project. As an example, sys- 
tems engineers working closely with the 
project scientist and the investigators may 



139 



READINGS IN SYSTEMS ENGINEERING 



conduct tradeoffs to determine how much 
data processing should be done on board by 
each instrument, thereby increasing the 
weight and power required by the instru- 
ments but reducing the complexity of, and 
the weight and power required by, the com- 
munications system of the spacecraft. 

Mutually acceptable schedules for the use 
of common ground facilities such as shake 
tables, vacuum chambers and calibration 
equipment are worked out between the pro- 
ject, the investigators and the persons re- 
sponsible for those facilities. A detailed 
schedule of all the tests, calibration runs and 
flight operations is established with each in- 
vestigator. These schedules, as emphasized 
repeatedly in this paper, should carry 
through flight operations and data analysis. 
Only by doing this can a systems engineer be 
sure that all the requirements of the scien- 
tists have been incorporated into the mission 
plan. By forcing the occasionally unwilling 
investigator to sit down and think through 
the entire experiment, the systems engineer 
may bring to the surface a major technical 
problem or an inadequate cost estimate. 

Once the entire mission is laid out, the in- 
vestigators accommodated, their expenses 
estimated and a launch date established, the 
systems engineer must estimate how much 
and what kind of resources need to be re- 
served for unanticipated problems. Extra 
slack time must be placed in the schedule to 
accomplish unanticipated work. The systems 
engineer must reserve some weight, power 
and communications capability for shortages 
that will inevitably arise. Funds to cover 
overruns must be reserved and a schedule by 
which the funds are to be released must be 
prepared. If there is no schedule for the re- 
lease of reserve funds, then they may all be 
used up in the early months of the project, 
leaving nothing for the major problems that 
will occur later. 

The project manager and the overseers at 
the Center and Headquarters should exam- 
ine any deviation by an investigator from the 
planned use of the reserves with the same 



care they would examine an instrument that 
is not meeting its design specifications or its 
milestones. Such a deviation in the rate of 
use of reserves may identify a weakness in 
the investigator's team or in the design of 
the instrument early in the development 
cycle. If the project manager takes prompt 
action when an unexpected use of the re- 
serves is first seen, technical or schedule 
problems that may occur later in the devel- 
opment phase can be eliminated or reduced. 

At this time, the project manager estab- 
lishes another important policy — how the 
information about the reserves will be treat- 
ed. The project manager can choose to oper- 
ate somewhere between two extremes: 
"everything on the table" or "hold all the 
cards close to the chest." In the first extreme, 
everybody in the project is informed, includ- 
ing all the subsystem managers, all the 
principal investigators and the contractors, 
exactly what the reserves are, who is holding 
them and the schedule for their use. At the 
other extreme, the project manager treats 
the reserves as highly classified information 
known only to the project manager and possi- 
bly some of the senior management. Both 
extremes have worked. The choice largely 
depends on the experience and personality of 
the project manager and NASA's current 
management philosophy. A new, insecure or 
weak project manager may want to keep this 
information confidential to help control the 
project. A more confident project manager 
may choose to operate an open system. If a 
project manager chooses to operate an open 
system, there must be a willingness to accept 
a high level of acrimony in the project. A 
principal investigator fighting a weight 
problem or overrunning the budget will eye a 
compatriot's reserve and scheme to get it. On 
the other hand, by operating in an open 
manner the project manager may create a 
more healthy climate of trust between the 
investigators and the project team and 
thereby discover problems earlier than if all 
the reserves are kept secret. Sharing knowl- 
edge of the problems and the reserve being 



140 



USER REQUIREMENTS 



maintained can help a project manager pro- 
mote teamwork on the project, raise the mo- 
rale, and encourage the investigators to 
carefully manage their reserves. On the oth- 
er hand, if NASA's current policy is to pull 
all identifiable reserves into a Headquarters 
reserve to be held by the comptroller, then 
project managers will instinctively bury any 
financial reserves somewhere in the project. 

Ultimately, the user requirements will be 
assimilated into the systems engineering 
process, the preliminary designs will be com- 
pleted, the schedules established, and the 
rate of expenditure established. When this is 
done, the project is ready for its first major 
design review, the preliminary design re- 
view. 

PRELIMINARY DESIGN REVIEW 

The Preliminary Design Review (PDR) ends 
the preliminary design work, and completes 
the incorporation of user requirements into 
the systems engineering process. All aspects 
of the mission and all future activities re- 
quired to accomplish the mission should be 
planned by this time. 

The choice of a chairperson for the PDR 
depends upon the complexity, cost and 
national interest in the project. The division 
director may chair the PDR of a routine, 
small scientific project. The associate admin- 
istrator for the Office of Space Science and 
Applications will chair the PDR of a larger, 
more complex mission. The administrator or 
deputy administrator of NASA may chair 
the PDR of a large, complex, costly, highly 
visible mission such as the Hubble Tele- 
scope, or Earth Observing System. The 
chairperson should be someone who thrives 
on crowds and controversy and has a vast 
curiosity about the mission and a penchant 
for uncovering unforeseen or concealed prob- 
lems. The chairperson should use the PDR to 
identfy and resolve any issues that the pro- 
ject team or the investigators may have over- 
looked or may be trying to avoid. 



The good chairperson goes around the 
room after the discussion of a controversial 
item and questions the key people involved 
to see if they all understand and agree on the 
project's plan. The chairperson of the PDR 
cannot be a "shrinking violet" or an introvert 
(at least not during a PDR). 

The project manager conducts the review. 
Attendance from Headquarters includes, but 
is not be limited to: the associate administra- 
tor for the Office of Space Science and Appli- 
cations or a designee, the division director, 
the program manager, the program scientist, 
the financial analyst, the NASA comptroller 
or the designee, and the associate adminis- 
trators for the Offices of Space Flight and 
Operations or their designees. Someone from 
the Office of International Affairs attends if 
there are foreign investigators or if it is a 
joint mission with another country. Atten- 
dance from the Center will include the direc- 
tor, the financial analysts, representatives of 
the engineering disciplines and the systems 
engineers. All the principal investigators 
attend. Senior people from the major con- 
tractors also attend. If the PDR is for an 
applications mission, then senior people from 
the agency who will use the system will 
attend. 

The chairperson expects the project man- 
ager to present a clear, concise statement of 
the overall objectives of the mission. If there 
are other nonscientific objectives for the 
mission — if, for instance, one of the objec- 
tives is to test a new subsystem, a new space- 
craft or a new tracking system — then the 
project manager is expected to clearly specify 
the relationship and priorities between those 
other objectives and the scientific objectives. 
The chairperson should make sure that all 
objectives are clear, understood and agreed 
to by the attendees. 

The project manager should present a 
complete schedule, extending from the PDR 
through the Critical Design Review, on 
through development, testing and calibra- 
tion of the instruments and continue on to 



141 



READINGS IN SYSTEMS ENGINEERING 



launch operations, data analysis and publi- 
cation or use of the results. Slack time should 
be clearly shown. Even though detailed 
plans for operation and data analysis may 
not be complete at this time, the systems 
engineering process should have produced a 
list of the facilities required and a schedule 
for their use. Very often, the examination of 
the mission's schedule at the PDR will un- 
cover potential conflicts for the use of facili- 
ties or an underestimate of the cost of some 
phase of the mission. 

The chairperson reviews the status of 
each instrument. Ideally, the review of an in- 
strument will consist of two parts, a presen- 
tation by the principal investigator followed 
by the project scientist's assessment of the 
status of the instrument. The principal in- 
vestigator should describe the experiment, 
its objectives and how they relate to the 
objectives of the mission. The principal in- 
vestigator should describe the instrument, 
show the schedule and slack times, and 
present a cost breakdown and a funding 
schedule. The investigator should identify 
any issues with the project manager, includ- 
ing any foreseeable technical and procure- 
ment problems, and list the top four or five 
problems. The project scientist should then 
give the project's view of the status of the 
instrument and should state whether the 
project agrees with the status as presented 
by the investigator. The project scientist 
should present any concerns the project has 
about the principal investigator, the team, 
the institution or the contractor. 

This review by the project scientist at the 
PDR should not lead to a confrontation be- 
tween the principal investigator and the pro- 
ject scientist or the project manager; through 
earlier discussions, each should be aware of 
what the other intends to say; each should be 
aware of the concerns of the other and at the 
review they should present a jointly devel- 
oped plan to solve the problems that exist. 
The project manager and the principal inves- 
tigator should understand and accept the 
actions that the other intends to take to 



resolve the problems. If the investigator has 
only a tentative approval to fly on the mis- 
sion, then the actions and milestones should 
be specified that will lead to final acceptance 
or rejection. 

The project manager or the manager's 
designee should review the status of the 
other elements of the mission, their sched- 
ules and problems. If the cost or configura- 
tion of a subsystem is being determined by a 
requirement of a particular investigation, 
that fact should be presented so that senior 
management and the principal investigator 
can decide whether the particular aspect of 
the investigation merits the additional cost 
or complexity. 

The project team should present an over- 
all assessment of the instruments and their 
interaction with each other and with the 
subsystems on the spacecraft. The project 
manager may elect to divide the experiments 
into two groups: one group consisting of 
those investigations in which the design of 
the instrument is on schedule, within bud- 
get, and the investigator is not in need of 
careful monitoring; the second group consist- 
ing of those instruments that have major 
problems, that will require careful monitor- 
ing and perhaps even a backup instrument. 

The project manager should review the 
status of the resources available to the pro- 
ject, the reserves that are being held and the 
schedule for their release. At the conclusion 
of the PDR, the project manager should 
identify the top 10 problems for the overall 
project and describe plans to resolve them. 

At the conclusion of the PDR, all the 
participants — Headquarters, Center man- 
agement, the project team, the principal 
investigators and the subsystem managers — 
should all understand and accept the status 
and requirements of the investigations 
scheduled for the mission. The principal 
investigators should agree with the status of 
their experiment as presented, and they 
should understand and be prepared to accept 
the requirements and meet the schedules 
that have been placed on them by the project. 



142 



USER REQUIREMENTS 



Once the actions that were assigned to the 
project and the investigators by the PDR 
have been completed, the requirements of 
the investigators should be incorporated into 
the systems engineering process. The project 
team and the investigators are then ready to 
proceed with the detailed design and manu- 
facture of the instruments and the space- 
craft. 

The majority of the systems engineering 
effort required to incorporate the user re- 
quirements should be complete at this time. 
Normal project management and engineer- 
ing techniques should be adequate to com- 
plete the integration of the investigators into 
the mission. There will, however, be a 
continuing need for systems engineers to 
support the project team. No matter how 
good and how complete the systems engi- 
neering effort has been, and how carefully 
the PDR is conducted, problems will still be 
encountered in the instruments or in the 
subsystems and changes will have to be 
made. The systems engineer will have to 
trace the impact of those changes through 
the system, identify the problems that are 
created and provide the options for their 
solution. Inevitably, there will be a shortage 
of resources available — additional power or 
weight required — and the systems engineer 
will have to assess the system to see how the 
resources can be found and analyze the im- 
pact of using those resources. Occasionally, 
excess resources will become available; the 
systems engineer will have to examine these 
extra reserves and determine how they can 
best be applied to enhance the quality of the 
mission. 

As the work progresses, the engineers 
will eventually understand the instruments 
and their spacecraft, their designs will be 
frozen, all the options will be eliminated and 
the systems engineer will no longer be need- 
ed. Sometime before this stage is reached, 
the good systems engineers will become 
bored and will move on to a new system with 
new challenges. 



GLOSSARY 

Mission. An effort to increase human knowl- 
edge that requires the launch of one or more 
spacecraft. A mission begins with the initial 
concept and concludes with the publication of 
the results. 

System. All the tasks and all the equipment, 
both ground and space based, required to ac- 
complish a mission. 

Systems engineering. The systematic 
planning activity that begins with the mis- 
sion objectives and the requirements of the 
scientists and turns them into specifications 
for hardware and facilities, conducts tradeoff 
studies between competing subsystems, ana- 
lyzes the interaction between the subsys- 
tems to eliminate unwanted interference, 
and prepares schedules, cost estimates and 
funding plans. 

Program. The formulation and documenta- 
tion of a mission prepared by NASA Head- 
quarters and used to obtain authorization 
and funding from Congress to conduct the 
mission. 

Project. All the equipment produced or pur- 
chased by, and all the activity conducted and 
directed by, a NASA Center to accomplish a 
mission. 

Division director. An individual at NASA 
Headquarters responsible for a group of re- 
lated scientific programs. 

Program manager. A person, usually an 
engineer, at NASA Headquarters in charge 
of a program. A program manager reports to 
a division director. 

Program scientist. A scientist at NASA 
Headquarters responsible for formulating 
the scientific objectives of a program. A pro- 
gram scientist reports to a division director. 



143 



READINGS IN SYSTEMS ENGINEERING 



Project manager. The person, usually an 
engineer, at a NASA Center who is responsi- 
ble for the success of a project. The project 
manager reports to the senior management 
of the Center. 

Project scientist. The scientist at a NASA 
Center responsible for accomplishing the 



scientific objectives of a project. The project 
scientist reports to the senior management 
of the Center. 

Principal investigator. A scientist, select- 
ed by NASA Headquarters, to conduct an 
experiment during a mission. 



144 



SE&I PROCESSES 



N83-24688 

Systems Engineering and Integration Processes 
Involved with Manned Mission Operations $/* V 

by Eugene F. Kranz and Christopher C. Kraft 



/SBS8£ J3L 



The quality of the systems engineering and 
integration (SE&I) process determines the 
viability, effectiveness and the survivability 
of major NASA flight programs. In mission 
operations, SE&I is the process by which the 
technical, operational, economic and politi- 
cal aspects of programs are integrated to 
support the program objectives and require- 
ments consistent with sound engineering, 
design and operations management princi- 
ples. 

Major flight programs involve operation- 
al, cost, and political elements and priorities, 
international prerogatives, and often poorly 
focused utilization requirements, in addition 
to traditional technical trades, technology 
utilization, and interface definition and con- 
trol. This combination demands an effective 
SE&I process that spans and involves all 
these elements. 

SE&I, therefore, is a distributed process 
that involves the structuring and integrated 
management of a program within and be- 
tween the program, project and technical 
levels, with a life cycle consistent with the 
program phase. SE&I must anticipate pro- 
gram needs by providing clear technical 
assessments, trades and alternatives aimed 
at satisfying the program objectives and 
requirements. 

This paper will describe the key princi- 
ples and processes used within mission oper- 
ations, emphasizing the pre-mission prep- 
aration activities most useful for describing 
the principles of an effective SE&I process. 

Early Development of Mission 
Operations 

The development of mission operations capa- 
bilities for manned space flight involved a 
rapid evolution from the traditional method 
of aircraft flight test operations used during 



the early Mercury program to the mature 
and structured process used for Apollo. The 
flight experience of the Mercury program re- 
vealed the need for a deeper knowledge of 
spacecraft systems by flight operations 
teams. It further indicated a need for 
systems documentation tailored to the opera- 
tor's real-time task. By the completion of 
Mercury, a systems handbook had been 
developed as an "on-console," real-time docu- 
ment for flight systems data. Direct commu- 
nication was established between the operat- 
ing team and the manufacturer so that any 
additional systems data needed during the 
course of the mission could be obtained. This 
communication also provided a means for 
getting engineering judgment on operational 
trades, whenever time permitted. The flight 
rules became the focus of operational poli- 
cies. 

The Gemini program required the devel- 
opment of the trajectory capabilities needed 
for rendezvous and docking, as well as a 
guided reentry capability. These require- 
ments established the linkage between tra- 
jectory; guidance, navigation and control 
(GNC) systems; and propulsive consumables. 
The Gemini extravehicular activity (EVA) 
increased awareness of the relationship be- 
tween crew, the task and the working envi- 
ronment. 

During Apollo, science became the final 
mission component supported by the oper- 
ations teams. The Apollo operations team 
worked in an integrated fashion on all issues 
involving flight systems, flight design, 
science and manned operations. 

It was during the Skylab program that 
the first formal and broad-scale application 
of the mission operations (SE&I) process 
emerged to support the early flight system 
hardware and software design. During the 
Skylab design reviews, many of the review 



145 



READINGS IN SYSTEMS ENGINEERING 



item discrepancies (RIDs) revealed the need 
for much closer relations between systems 
design and operational utilization. 

The multiple Skylab systems elements, 
combined with the broad spectrum of scienti- 
fic objectives and the complexity of manned 
and unmanned flight, required an early and 
effective relationship between flight systems 
designer, scientist-user and mission oper- 
ations. A Johnson Space Center (JSC) oper- 
ations team and a Marshall Space Flight 
Center (MSFC) engineering team joined to 
conduct a series of systems operations com- 
patibility assessment reviews (SOCARs). 
During these and all subsequent reviews, the 
Skylab systems and software handbooks pro- 
duced by mission operations were used as the 
baseline reference documentation for the 
SOCAR. These documents were also used by 
the JSC and MSFC teams for the flight phase 
of the program. Skylab real-time operations 
demonstrated the effectiveness of this rela- 
tionship between the JSC and MSFC teams. 

The mission operations team supported 
the design and development phase of the 
Space Shuttle program at the program and 
project levels and helped develop operational 
workarounds for flight systems and software 
deficiencies that could not be corrected be- 
fore the flight test phase of the program. 

Mission Operations Structure 



management, avoiding conflicting priorities 
and providing leadership focus. The only 
exception is a Flight Design and Dynamics 
Division (FDDD), which provides integrated 
flight design for the Shuttle and all pro- 
grams using Shuttle services. 

Each division is responsible for integra- 
tion within its work area and provides 
mission operations representation to the 
project-level boards. Program-level boards 
are generally supported through the Flight 
Director Office, by the Operations Division 
and by the FDDD. Integration between pro- 
grams is accomplished by the MOD assistant 
directors for the Shuttle and for the Space 
Station. 

In addition to the internal integration 
process, each division generally has a hori- 
zontal integration responsibility that identi- 
fies, collects and documents the capabilities 
and constraints imposed by other elements. 
This integration process frequently incorpo- 
rates participants external to mission oper- 
ations (for example, participants from the 
program and the project), as well as the 
flight system contractor and the payload 
user. In most cases, this is accomplished by 
mission operations directed panels that are 
chartered by the program. 

Introduction to Mission Operations 
SE&I 



The Mission Operations Directorate (MOD) 
at the Johnson Space Center is highly inte- 
grated and structured around the principal 
skills needed for mission preparation, plan- 
ning, training, reconfiguration, facility de- 
velopment, facility operations and real-time 
flight operations. 

Each mission operations element consists 
of a single functional discipline, e.g., mission 
design, flight systems, reconfiguration, 
training, etc. Usually each organizational 
element is structured to provide dedicated 
support to either the Shuttle or Space Sta- 
tion. This is believed to be the best way for 
assuring accountability in individuals and 



This paper will discuss three mission oper- 
ations functions that are illustrative of the 
key principles of operations SE&I and of the 
processes and products involved. 

• The flight systems process was selected to 
illustrate the role of the systems product 
line in developing the depth and cross- 
disciplinary skills needed for SE&I and 
providing the foundation for dialogue 
between participating elements. 

• FDDD was selected to illustrate the need 
for a structured process to assure that 
SE&I provides complete and accurate 



146 



SE&I PROCESSES 



results that consistently support program 
needs. 
• The flight director's role in mission oper- 
ations was selected to illustrate the com- 
plexity of the risk/gain tradeoffs involved 
in the development of the flight tech- 
niques and flight rules process as well as 
the absolute importance of the leadership 
role in developing the technical, oper- 
ational, and political trades. 

Flight Systems Division SE&I 

The early Mercury program employed a mix- 
ture of operations and engineering personnel 
to support the real-time operations. Later, 
flight experience established the need for a 
full-time systems operations team. The need 
for an integrated compilation of flight sys- 
tem data usable by the crew and ground 
team for real-time operations led to early 
versions of the systems handbooks that are 
the foundation for today's handbooks. Rudi- 
mentary integrated schematics were used for 
Gemini, but with the Apollo program came 
more complex inflight computing capability. 
Consequently, the schematics were expand- 
ed to define the computer interfaces and used 
significantly more of the vehicle design and 
performance data base within the schematic 
notes. 

As mentioned earlier, the schematics 
were used for the first time to support the 
Skylab critical design reviews and the 
SOCAR. During these reviews, program and 
project management recognized that the sys- 
tems operations teams and the systems 
handbooks were an SE&I asset. The modu- 
larity of the Skylab elements, along with the 
integrated nature of the systems, established 
the pre-mission role for the systems hand- 
books to support the flight system design 
review process as an integrated activity. The 
usefulness of the handbooks in addressing 
integrated systems issues was thus formally 
established. For the Apollo Soyuz Test Pro- 
gram (ASTP), and the Shuttle and Spacelab 
programs, the preliminary version of the 



mission operations schematics were complet- 
ed prior to the flight system critical design 
review (CDR) and were used as the founda- 
tion for the mission operations assessments. 

The Systems Handbook Today 

Mission operations schematics are developed 
by the controllers to a common set of internal 
drafting standards and conventions and use 
the design engineering drawings, vendor 
schematics and software source code. For the 
Shuttle, operations personnel were required 
to develop Houston Aerospace Language/ 
Shuttle software language skills as a job 
requirement. Permanent, prime contractor, 
in-house and in-plant support assures the 
flow of the raw design data and provides the 
communications conduit between the sys- 
tems operations personnel and the prime 
contractor design engineers so they can ad- 
dress questions as they arise. After the STS- 
51L accident, all handbook schematics were 
expanded to provide direct traceability to 
design drawings by title, drawing number, 
revision and date. 

The systems controllers who develop the 
schematics derive significant training from 
using design data and translating this data 
into an operationally useful format. The 
schematic development and the integration 
of data from supporting systems and subsys- 
tems provides independent validation of the 
system design intent. In particular, it identi- 
fies issues where the integrated design may 
have compromised the program intent. The 
drawing configuration control process re- 
quires verification by section and branch 
chiefs and final approval by the division 
chief. Formal reviews are conducted before 
major handbook releases. As a result, the op- 
erator and the supervisory chain derive a 
training benefit from the systems handbook 
process. 

The systems handbooks are used by 
crews, flight directors, training instructors 
and mission operations payload support per- 
sonnel. They are a formal portion of training 



147 



READINGS IN SYSTEMS ENGINEERING 



documentation and are carried in the Shuttle 
flight data file. The schematics support 
airborne system troubleshooting and provide 
a common base for the crew and the ground 
to discuss suspected problems and follow-on 
actions. They provide the basis for MOD dis- 
cussion with the contractor engineering 
team and with the mission support team. 

Flight Procedures. The development of the 
systems handbook provided the foundation 
for the development of flight procedures. 
Three basic categories of flight procedures 
are developed: the operations checklists, the 
pocket checklists and the malfunction proce- 
dures. 

The operations checklist procedures allow 
the crew and ground systems operations to 
accomplish a planned activity and are nor- 
mally developed as blocks of integrated sys- 
tems activities; for example, aligning the 
inertial measurement unit. Procedures de- 
velopment requires intimate familiarity 
with the system; its interfaces, controls, and 
displays; and with the intended task to be 
accomplished. Operations checklist proce- 
dures cross all systems and technical disci- 
plines, and as a result of their development, 
provide another level of systems integration 
and design validation. Procedures associated 
with an Orbital Maneuvering Subsystem 
burn, for example, involve loading the ma- 
neuver targets into the computer, selecting 
and configuring engines for the burn, acti- 
vating the correct digital autopilot, selecting 
displays, and specifying of data to be record- 
ed. 

Pocket checklists are emergency proce- 
dures based on the operations checklist. The 
term "pocket" is used because the checklists 
must be readily available for critical mission 
phases and are sized to be carried by the crew 
in the pockets of their flight suits. 

The pocket checklist procedures define 
the steps to be taken when an unplanned 
event occurs. These procedures address 
critical failures and are flight-phase unique. 
They require knowledge of system perfor- 



mance limits, crew capabilities, failure 
modes, and crew and ground response times. 
The emergency procedures therefore provide 
a bridge from operations checklist proce- 
dures into options that allow the crew to con- 
tinue the current flight phase with modifica- 
tion, to reconfigure to recover capabilities, or 
to utilize an alternate capability. Figure 1 is 
a typical procedure used during powered 
flight for a main B undervolt condition. 

The final type of flight procedures devel- 
oped by the controllers are the malfunction 
procedures (MALS), which are used when 
time is available to troubleshoot, locate and 
define the boundaries of problems that occur 
inflight. To solve the problem, the crew and 
ground use the full range of instrumentation 
available and any visual or external cues 
available. The procedures are developed in a 
logical format using a series of "if," "and," 
and "or" statements. Warning notes are pro- 
vided, as well as permissive steps when 
ground and crew consultation is required pri- 
or to continuing the procedural sequence. 
These procedures have allowed the correct 
isolation of the majority of inflight problems 
for the Shuttle program. 

A final category of flight procedures con- 
cern payload operations and involve multiple 
flight elements. 

Flight Systems Organizations. Since 
Gemini, the MOD flight systems organiza- 
tions have been structured to address a 
complete space system. Examples include 
command service module, lunar module and 
Shuttle. Each section within an organization 
has responsibility for an assigned system, 
with its subsystems, software, instrumen- 
tation, display, crew controls, command 
controls, procedures, mechanical, power, 
cooling, and thermal and consumable inter- 
faces. During the Skylab program, each or- 
ganization also had to know about inflight 
maintenance and support logistics. 

The systems organizations of the MOD 
participate in flight systems design via for- 
mal membership on the working groups, 



148 



SE&I PROCESSES 



Flight 
Rqmts 



De sign 
Constraints 



Orbiter/ Payload 
Mass Properties 




Orbiterand 
Payload 
TLM/CMD Rqmts 



Payload 

Onboard Display 
Rqmts 

Payload 
Model Rqmts 



Figure 1 MOD Production Process Overview (L-Time in Months) 



panels and boards established by the pro- 
gram office. During the early design phase, 
they establish the data base for the develop- 
ment of schematics and procedures for the 
flight controllers. Because of this, direct con- 
tractor liaison is maintained within the 
MOD systems organization and in-plant. 

Development of the mission product line 
by the systems flight controllers increases 
their skills and knowledge. In addition, the 
product line focuses the operations assess- 
ments of overall flight system architecture 
and provides the foundation for subsequent 
steps. Finally, as a recognized product, it is 
used by several groups in support of their 
individual responsibilities. Program SE&I 
products typically must exhibit the same 
characteristics — they must pass the value- 
added test. 

The systems operations contribution to 
the early design and eventual operation of 
the flight system has been essential in assur- 
ing safe, effective and functional system 



capability for space flight. The perspective of 
the systems operator provides the cross- 
disciplinary assessment needed to assure ef- 
fective overall systems engineering and 
integration. This perspective is the corner- 
stone of the real-time capability of the man- 
ned spaceflight operations team. 

Flight Design Division SE&I 

The flight design process involves the inte- 
gration of payload and engineering require- 
ments with mission objectives to form an 
integrated mission design. The flight design 
must satisfy both Shuttle system design and 
payload design constraints while considering 
the additional constraints imposed in consid- 
eration of safe mission conduct and mission 
success. 

The flight design process is a critical node 
in the Shuttle mission preparation process. 
In addition to flight design, the process 
provides initialization data for the ground 



149 



READINGS IN SYSTEMS ENGINEERING 



ENGINEERING 
CYCLE 



1st 
STAGE 
TDDP 



SUPER 
TAPE 



I-L 
CR 



SDTF 



MMU ENG 
Rl CYC 



ENG 
RFIT 



CIR 



TDDP FOP 



351 323 309 288 



I-L 
RDY 



228 



I-L 
APPR 



SMS 
DATA 



260 



214 186 
193 
221 



SMS 
MCC 



ENG 

CYC 

STAND 

ALONE 



161 



77 



FLT 
RFIT 



LO 



42 



70 



175 



FLIGHT 
CYCLE 



ASC 

FREEZE 

PT 



1st 
STAGE 
TDDP 



FPSR 



I-L 
CR 



FOR 



284 270 



TDDP 



FOP 



SUPER 
TAPE 



I-L 
RDY 



228 207 179 140 



I-L 
APPR 



109 



I-L 
APPR 



FLT 
ALT 
MMU 

ORBIT 
RFIT 



88 



FLT 
CYC 
SMS 
DATA 

FLT 
RFIT 



70 



LO 



42 



242 



136 



91 



77 



57 



12 11 10 9 

Time prior to launch, months 



Figure 2 Flight Design Template 



facilities, Shuttle primary and backup soft- 
ware, flight and payload planning, and real- 
time decision support products. 

Within the flight design and dynamics 
discipline there are three mission phase ana- 
lysis and design work areas — ascent, orbit 
and descent — and one functional area — real- 
time operations. The FDD, working in 
coordination with other mission operations 
elements, establishes and integrates the 
propulsive and non-propulsive consumables, 
abort propellant dump analysis, and manip- 
ulator requirements and analysis into the 
overall flight design. The overall integration 
of activities supporting a mission is provided 
by a flight design manager. 



The flight design process acquires a vast 
amount of input data from a wide variety of 
sources. The input data for the early phase of 
the program is typical specification data, but 
during the operational phase of the program 
it becomes highly flight specific and fre- 
quently component specific. A good example 
would be constraints for engine throttling 
related to a specific Space Shuttle Main 
Engine turbo pump. 

Flight Design Cycles. The flight design 
process has three principal cycles designed to 
satisfy the requirements and lead times of 
the many users. The conceptual flight profile 
cycle provides the program office with data 



150 



SE&I PROCESSES 



for making commitments to the payload 
customers and assessing the overall suitabil- 
ity of the operations flight design approach. 

The engineering cycle supports the ini- 
tialization of the engineering and test facili- 
ties as well as the initial shuttle mission 
simulator (SMS) training load. The flight 
cycle supports MCC and SMS initialization 
for final training and operations, Kennedy 
Space Center (KSC) Launch Processing 
System checkout and launch support, God- 
dard Space Flight Center network support, 
and range safety. The flight design cycles are 
under review to determine if a single cycle 
could be used to satisfy all user require- 
ments. This latter objective requires signifi- 
cant standardization within the program, 
improved and timely provision of payload 
specific data and significant training stan- 
dardization. 

Flight Design Documentation. The flight 
design process is the last of the mission oper- 
ations processes to be documented as a 
structured flow from the conceptual phase 
through the delivery of the launch-loads 
used for flight. The full documentation of 
these processes is now contained in 22 vol- 
umes of flight design handbooks. Documen- 
tation was undertaken to serve four distinct 
objectives: (1) document the corporate mem- 
ory of this process before it is lost; (2) estab- 
lish an error- and omission-free process, 
necessary because of the critical nature and 
use of the flight design products; (3) support 
the design of an integrated computing sys- 
tem as an aid to support the flight design 
process; and (4) assure consistent design and 
rationale between similar missions. 

The two years after the STS-51L accident 
were used to safe the flight design system, 
document the process and initiate a multi- 
year plan for code conversion, consolidation, 
documentation and configuration control of 
all applications software. Process flow charts 
were developed for every activity involved in 
the flight design analysis and production 
activity. 



The flight design handbooks developed 
during recent years have documented the 
flight design SE&I process and, to a great 
extent, represent the structure and relation- 
ships that must exist to incorporate integrat- 
ed trajectory design into any space program. 
These documents are invaluable examples of 
the structure and approach needed for fur- 
ther space exploration activity. They also 
provide a good textbook for personnel in- 
volved in SE&I management to describe the 
relation between trajectory, systems, soft- 
ware and objective data. In addition, they 
define input/output requirements, integra- 
tion nodes, audit points and interfaces to 
external elements for data acquisition and 
transfer. 

An Illustration of the Flight Design Pro- 
cess. The integration of the constraints im- 
posed by the flight system, environment, 
payload and operations in the determination 
of the launch window will be used to illus- 
trate one aspect of the flight design process. 

The launch window is the time period 
that the Shuttle should launch to achieve 
precise program requirements. This activity 
is described in the flight design handbook via 
three processes that satisfy Shuttle and 
payload requirements. These processes are 
further combined and iterated to develop the 
integrated launch window. This initial step 
of the process provides input data for subse- 
quent planning involving deorbit opportuni- 
ties, sequence of events, pointing, thermal 
assessments and so forth. 

The constraints imposed in launch win- 
dow determination represent the broad 
range of considerations faced by the flight 
designer in this task. Where practicable, 
priorities are established to assist the flight 
designer. The actual development of the 
launch window analyses is governed by a 27- 
page procedure within the flight design 
handbook. 

Flight design is an essential element for 
space flight. The documentation of this pro- 
cess captured what was in the minds of the 



151 



READINGS IN SYSTEMS ENGINEERING 



talented and imaginative individuals work- 
ing in this field, and provided the definitive 
text for future flight design work for space 
exploration. 

For the Space Station Freedom program, 
MOD has developed process flow charts for 
all functions that describe the input/output 
activities within mission operations and be- 
tween mission operations and the Level II 
program elements, MSFC, KSC, GSFC and 
international partners. These flow charts de- 
scribed interfaces, product exchanges and 
work templates. They were used to define the 
roles and mission boundaries needed for sus- 
tained and effective relationships between 
participants. Documentation of the SE&I 
process is absolutely essential to clear and 
effective role and responsibility definition, 
and is a primary step in minimizing jurisdic- 
tional battles between SE&I elements. 

Flight Directors SE&I 

The mission operations SE&I process uses 
the Flight Director Office to provide the top 
level, multidisciplinary integration, risk/ 
gain assessment and validation of the inte- 
grated mission preparation. 

Flight directors are selected from the 
ranks of MOD personnel. Selection is based 
on leadership, technical abilities, stability 
and judgment as established by their perfor- 
mance during flight operations. They are 
already intimately familiar with the operat- 
ing disciplines, interfaces, flight and ground 
systems capabilities, crew capabilities and 
the mission risk/gain process. The challenge 
for the flight directors is acquiring and 
maintaining the clear perspective needed for 
multidisciplinary technical, operational and 
political trades and leading the many di- 
verse elements to operationally correct risk/ 
gain decisions. 

The lead flight director is central to the 
process for the assigned missions. 

Pre-CDR Support. Support to a program 
from the Flight Director Office is initiated 



between the preliminary design reviews 
(PDRs) and CDRs. This phase is character- 
ized by major tradeoffs between program 
requirements, flight system design, crew and 
ground and customer roles, schedule and 
cost. During this period the flight director, 
supported by all mission operations ele- 
ments, refines the operating concepts and 
leads the operational trades involving auton- 
omy, fault tolerance, crew and ground func- 
tions, and flight design and payload suppor- 
tability. As flight system design becomes 
more focused during this period, the program 
costs and the real world design trades con- 
verge and program tradeoffs must be imple- 
mented. As a result, the mission operations 
integration process is initiated to provide the 
program and project managers with a clear 
understanding of available options. The op- 
tions are generally provided by in the form of 
operations compatibility studies, similar to 
the SOCARs described previously, or in the 
form of an integrated mission design assess- 
ment. 

CDR Support. The CDR support to the 
program from the mission operations team is 
significantly different because of the avail- 
ability of the mission operations flight 
systems handbooks and the increased knowl- 
edge of the team. The operations team has 
acquired significant experience in working 
with the program and project as a member of 
the change control board (CCB) and through 
the CCB processes. The CDR represents a 
milestone for reassessing the design and is 
frequently the first time that the maturity of 
the software begins to approach the maturity 
of the hardware. 

The principal contribution from mission 
operations during this time is in the detailed 
operational suitability assessments. These 
assessments concern the mission suitability 
of the flight system design and involve pro- 
gram requirements, hardware and software 
design, mission design, and crew and ground 
capabilities. Through these assessments the 
preliminary risk/gain trades and fault down 



152 



SE& I PROCESSES 



options are established, operating philos- 
ophies are defined and mission options ascer- 
tained. Within mission operations, the CDR 
is not a discrete process. It is considered one 
of the many milestones of a process charac- 
terized by an increasing involvement by 
operations personnel in the change boards 
and control mechanisms established by the 
program. The involvement extends to the 
flight preparation period, which has two dis- 
tinct processes and products representative 
of the flight director's role in the mission 
operations SE&I. These processes involve 
flight techniques and flight rules. 

Flight Techniques. The initial flight tech- 
niques process was developed, and since 
Apollo, has been chartered by the Level II 
program. The process was established to 
address the growing complexity of the inter- 
action between flight software, flight system 
and flight objectives. This process provided 
the technical focus for the operations, engi- 
neering and contractor teams to address the 
use of the as-built flight system, the soft- 
ware, and the crew and ground capabilities 
in accomplishing flight objectives. During 
Apollo, the ground system, flight procedures 
and flight software were the only elements 
that could be readily changed within cost 
and schedule considerations. The flight tech- 
niques process, assisted by Draper Laborato- 
ries and the operational vehicle and software 
developers, established virtually all of the 
navigation capabilities for Apollo. They 
developed the technique for the Apollo 12 
pinpoint landing and were a principal contri- 
butor to the Apollo 13 return. 

The product line of the techniques process 
is initially the series of detailed meeting 
minutes, which provide the basis for flight 
procedures and the rationale for the majority 
of the flight rules and mission design con- 
straints. The flight techniques process pro- 
vides the integration of the knowledge base 
available on the flight system to drive flight 
designs, procedures and flight rules. 



Flight Rules. Flight rules are the funda- 
mental risk/gain policy document for mis- 
sion conduct. The "flight rules outline 
preplanned decisions to minimize the 
amount of real-time rationalization required 
when non-nominal situations occur from the 
start of the terminal countdown through 
crew egress." 

The most complex, difficult and critical of 
the integration processes provided by the 
Flight Director Office is flight rules develop- 
ment. Flight rules used today trace their 
beginnings to aircraft flight tests. Rudimen- 
tary guidelines were provided for the flight 
test pilots relative to test conditions, and go- 
no-go criteria were provided for test continu- 
ation or termination. Similarly, during 
Mercury the rules for selected systems fail- 
ures were also a simple set of go-no-go crite- 
ria involving powered flight abort and 
mission continuation or termination. Rules 
also addressed the control center, network 
and flight instrumentation requirements. 
Today's flight rules involve sophisticated 
risk/gain trades across redundant systems, 
multiple mission phases, engineering and 
payload objectives, and crew and controller 
capabilities. They also reflect and tradeoff 
the payload objectives, crew adaptation and 
flight system survivability in defining mis- 
sion duration for off-normal conditions. 
Additionally, they clearly define the respon- 
sibilities of key personnel implementing 
flight operations. 

While the rules are infinitely more com- 
plex, the principle of the rules remains the 
same; that is, "to establish the risk versus 
gain trades" before the mission, utilizing the 
full range of operational, program and engi- 
neering judgment available in the pre- 
mission environment. 

To assure complete visibility to all trade- 
offs involved in the flight rules, rule ratio- 
nale, techniques data and Systems Oper- 
ations Data Book (SODB), references are 
contained in the published rules. The SODB 
and its variants were developed during 



153 



READINGS IN SYSTEMS ENGINEERING 



MISSION OPERATIONS TEAM 
FUNCTION/CONCEPTS OPS INTEGRATION 
CONTROL CENTER & TRAINING 
RECONFIGURATION & TRAINING 
INTEGRATED FLT DESIGN REQUIREMENTS 
OPERATIONS PLANS 
ODF 

FLIGHT & GROUND OPS DOCUMENTATION 
CREW. FLIGHT CONTROLLER. & SUPPORT TEAM 
TRAINING 

- SIMULATORS 

- INTEGRATED SIMS 
FLIGHT DESIGN/PERFORMANCE 
MMDS 
l-LOADS 
FACILITY DE5IGN/M40/ANDSUSTAINING ENGINEERING 



N5TS/SSF PROGRAM OFFICE 
LEVEL II HARDWARE AND SOFTWARE DECISIONS AND 5CHEDULES 
I . 



I 

INTEGRATION AND OPERATIONS 



• OVERALL PROGRAM INTEGRATION 
5CHEDULE5 

• FLIGHT PREPARATION SCHEDULES 

-MANIFEST DEFINITION 
-PAYLOADS SUPPORT 
- PIP/ANNEX REQUIREMENTS 
-LANDING/ABORT SITES 

• VEHICLE AND CARGO KIT SCHEDULES 



FLIGHT 5VSTEMS PROJECTS OFFICE 

HARDWARE AND SOFTWARE 
SCHEDULES 

- ORBITER S CARGO 

CONFIGURATION DEFINITION 



• INTEGRATED SAFETY/HAZARD ASSESS 

• OVERALL SCHEDULING 

• MCC/POCOSSCC RECONFIGURATION 

• SMS/SSTF RECONFIGURATION 

• FLIGHT SOFTWARE RECONFIGURATION 

• FLIGHT AND OPERATIONS DIRECTORS 

• FLIGHTCONTROLLERS-U.S & INTERNATIONALS 
ROBOTICS AND EVA OPS SUPPORT 

• CONSUMABLES 

• REAL-TIME 5UPPORT 

• MISSION RISK/GAIN POLICY 




FLIGHT CREW OPERATIONS DIRECTORATE 

• CREW ASSIGNMENT 
CREW AVAILABILITY 

• CREW CAPABILITIES 5 CONSTRAINTS 

• CREW OPERATIONS REQUIREMENTS 



USER/CUSTOMER; POIC 

• USER INTERFACE SUPPORT 

- PIP/ANNEX REQUIREMENTS 

- SAFETY REVIEWS 

- HARDWARE/SOFTWARE DELIVERIES 

• TESTANDCHECKOUTSCHEDULE 
COORDINATION - INCLUDING END-TO- 
END TESTING 

- OPERATIONS SUPPORT AND 
PROCEDURES INPUTS 

- CUSTOMER PROVIDED TRAINING 
-SIM SUPPORT 

• INTERNAL SCHEDULES 



KSC 

LAUNCH & FLIGHT OPS COORDINATION 

- FLIGHT SYSTEM AND CARGO 
PROCESSING 

- VEHICLE TEST AND CHECKOUT 

- CARGO TEST AND CHECKOUT 
-ENO-TO-END TESTING 

- PAD SUPPORT SCHEDULING 

• NASA INTEGRATED CONTROL OPERA- 
TIONS A LAUNCH COMMIT ASSESSMENT 

• TURNAROUND SUPPORT 



5CF/POCC/ESC/POIC 

• COMMUNICATION AND DATA 
REQUIREMENTS 

-JOINT5 OPS PROCEDURES 

• INTERNAL CHECKOUT SCHEDULE 

• NETWORK INTERFACE TEST SCHEDULES 

-SIM SUPPORT 

-SUPPORT TO OTHER PROGRAMS 

• END-END TESTING 

• DATA REQUIREMENTS 



Figure 3 Mission Operations Integration 



Gemini by mission operators with support by 
the prime contractor for the purpose of docu- 
menting the performance capabilities and 
limitations of the flight system. Since 
Apollo, the SODB has been maintained by 
the prime contractor, with mission oper- 
ations as the primary user. 

The leadership function provided by the 
flight director, using the flight techniques 
and flight rules process, provides the focus 
for the integration of flight-specific work 
within mission operations. 

The rules and rationale section in the all- 
flights document is almost 900 pages. The 
flight-specific annex published for each 
mission is about 70 pages. It is provided to 



address the flight-unique objective and 
payload risk/gain trades for each specific 
mission, flight objective and payload ele- 
ment. 

Flight directors, like program and project 
managers, depend on a matrix structure of 
organizations to accomplish their responsi- 
bilities. The flight directors are consistently 
successful because their roles are well 
defined, and because the integration tech- 
niques are facilitated by the MOD organiza- 
tion structure as well as by clearly defined 
product line and support processes. These 
characteristics must exist to successfully 
cope with the complex issues imposed by all 
mission elements. 



154 



SE&I PROCESSES 



Principal Requirements of an 
Effective SE&I Process 

The mission operations elements, processes, 
and products are oriented to the singular ob- 
jective of safe and successful manned flight 
operations. The spacecraft on the drawing 
board, like the ship in a harbor, is a safe 
ship, but that is not what spacecraft and 
ships are for. The mission operations job is to 
take the spacecraft from the harbor of the 
drawing board into space, accomplish a mis- 
sion and then safely return the spacecraft to 
Earth. 

In recognition of this responsibility, the 
mission operations processes are structured 
to assure effective policy, objective, system 
and operations integration. Within this 
framework, complex risk/gain trades are 
conducted and validated at all levels, culmi- 
nating in a completely independent and 
dynamic assessment and stress test during 
the integrated training process. 

The mission operations process can illus- 
trate the principles necessary to a successful 
SE&I. It is believed that these principles are 
useful to other SE&I elements that have the 
responsibility for NASA flight programs at 
the project and program level. 

1. SE&I must have necessary roles and 
missions that are clearly defined by the pro- 
gram and implemented by the project and 
technical organizations. 

SE&I is necessary because the integra- 
tion processes needed to address the techni- 
cal, operational, political and economic 
aspects of major programs are complex. 

The value-added principle is the basic 
test that should be used in determining role 
and mission assignments. 

SE&I by its nature will be controversial 
and participating elements may stonewall 
the process. When this occurs, the program, 
project or technical manager must quickly 
and personally address the issue, establish a 
program position and demand the support 
required. 



2. SE&I must utilize the existing capabil- 
ities of organizations. 

SE&I is the "integration" of the techni- 
cal, operational, economic and political as- 
pects needed to support a major program. 
The broad range of work, skills required and 
complexity of issues virtually precludes the 
development of a single SE&I organization 
for a major program. SE&I responsibility 
must be distributed to be successful. 

3. SE&I elements must recognize and ac- 
cept that major and complex programs will 
involve technical, operational, political and 
economic needs. 

Major programs must address and sup- 
port the needs of the various constituencies 
involved in establishing the program and 
must consider all of the economic issues 
involved in program development and 
operations. This recognition is essential if 
NASA and its contractors are to develop a 
more flexible and responsive approach to 
program management. 

4. SE&I must have a process-based struc- 
ture and a defined product line and life cycle. 

The complexity of SE&I requires a struc- 
tured process to assure all interfaces are ad- 
dressed, proper responsibilities assigned, 
and SE&I is effectively mechanized. SE&I 
requires a solid grasp of all the elements to 
be brought together, where the elements 
logically come from, where they fit in the 
sequence, what the end product is and what 
the alternatives are. 

SE&I can be accomplished by a few gifted 
people for a limited time, but without 
structured processes, SE&I will become 
inefficient, outputs will not meet schedule 
commitments, "more integration resources 
will be needed, and the downward spiral will 
begin." SE&I is not provided by massive ap- 
plication of resources. It comes about by 
structured processes that clearly establish 
the roles and responsibilities of the support- 
ing elements and use them effectively. 

The SE&I process definition is also used 
to establish the product line of participating 



155 



READINGS IN SYSTEMS ENGINEERING 



elements and define input/output require- 
ments. This product line must be phased to 
the life cycle of the program. 

5. SE&I leadership must exist within all 
elements of the SE&I process structure and 
must be clearly recognized and accepted by 
the assigned individuals and their organiza- 
tions. 

Accepting an SE&I leadership role is to 
recognize and accept conflict, particularly in 
the project and technical organizations. 
Organizations assigned an SE&I role must 
recognize and accept the technical, oper- 
ational, political and economic implications 
of the SE&I role. SE&I must address the 
needs of the program, which must supersede 
the needs of individuals and organizations. 



SE&I within NASA's flight programs is a 
constantly evolving and complex process 
involving many conflicting requirements 
that must be brought together to support 
program needs throughout the program's life 
cycle. An SE&I process that is effectively 
structured with distributed responsibilities 
will support program needs and recognize 
many of the prerogatives of the existing 
NASA elements. Each complex program, 
however, will have some elements that do 
not fit neatly into the existing NASA 
infrastructure because of economic, political 
or other considerations. SE&I will always be 
controversial, in structure and in implemen- 
tation. 



156 



SYSTEMS ENGINEERING FOR OPERATIONAL SUPPORT SYSTEMS 



N 9 3 -34J/6 a 

Systems Engineering Considerations for / 6 $$gf 



Operational Support Systems 

by Robert O. Aller 
Operations support as considered here is the 



infrastructure of people, procedures, facili- 
ties and systems that provide NASA with 
the capability to conduct space missions. 
This infrastructure involves most of the 
Centers but is concentrated principally at 
the Johnson Space Center, the Kennedy 
Space Center, the Goddard Space Flight 
Center, and the Jet Propulsion Laboratory. 
It includes mission training and planning, 
launch and recovery, mission control, track- 
ing, communications, data retrieval and 
data processing. 

Operations support of NASA's space 
flight systems during the 1960s and the 
1970s was associated with operations char- 
acterized as Research and Development. 
Flight programs were a single flight of 
limited duration or a series of flights to ob- 
tain specific data or to demonstrate an oper- 
ational capability. This required operational 
support systems to be reactive and respon- 
sive to relatively short duration programs. 

In the past ten years, this has continued 
with some notable exceptions. With ad- 
vances in space and data technologies, the 
demonstrated capabilities and advantages of 
space operations and the increased cost and 
complexity of space systems has led to longer 
duration and repetitive flight programs. Sys- 
tems engineering of operational support sys- 
tems must accommodate this evolution and 
the increasing operational nature of NASA. 

The need for systems engineering is criti- 
cal to NASA in its preparations for conduct- 
ing operations in the late 1990s and into the 
next decade. The planning and implementa- 
tion of the operational support systems for 
this era are under way. Proper systems 
engineering is vital to the development of 
each new system, as well as to a "total sys- 
tems engineering" of the functionality and 
interfaces of the entire operational system. 



Implementation, integration and transition 
of these major changes to the Agency's oper- 
ational capacity require significant manage- 
ment attention. To assure NASA's future in 
research, development and operations, this 
system must be implemented successfully 
and designed to minimize NASA's operation- 
al costs. 

Total Systems engineering 

The need for incorporation of systems engi- 
neering concepts and discipline is much 
broader for operations support systems than 
the hardware and software systems for 
which it is normally considered. As noted, 
operations support is an infrastructure of 
people, procedures, facilities and systems. 
Although systems engineering is routinely 
applied to each new system, the major prob- 
lems often occur between systems and 
frequently among people, procedures and fa- 
cilities. A disciplined systems engineering 
approach formulating each of these elements 
in the establishment of the "system" cannot 
be overemphasized. NASA has learned many 
times that good system contractors do not 
necessarily nurture good operational person- 
nel and technicians nor do they necessarily 
develop usable maintenance procedures. Ex- 
perience has also shown that facilities not 
adequately analyzed in conjunction with the 
planned utilization of the facilities require 
constant modification to meet operational 
needs. In considering support capability, 
each of the infrastructure elements requires 
analysis and carefully managed selection 
and attention. 

An organizational tier of system analysis 
from the whole to each element can be ap- 
plied in a macro sense to assure consider- 
ation of both technical and nontechnical 
systems. A macro analysis of the system 



157 



NAL MONOGRAPH SERIES: SYSTEMS ENGINEERING PAPERS 



involves many considerations; two nontech- 
nical areas that have often caused problems 
are inadequately skilled personnel and un- 
derdesigned facilities. 

The nature of operations support requires 
a spectrum of talents and skill levels. Most 
newly developed systems have not properly 
analyzed the experience and skill mix need- 
ed nor the number of personnel required, 
which varies from skilled flight controllers to 
maintenance and repair technicians. Too of- 
ten a process to analyze the system operation 
and system maintenance and repair require- 
ments is not properly developed in advance, 
resulting in an operations team that is un- 
dersized and underskilled. 

A second issue is simply undersizing 
facilities. While managers operate on the 
"nature abhors a vacuum" principle and 
insist that each square foot of a new facility 
needs clear functional definition, too often 
new facilities are found to be inadequately 
sized even before they are put into operation. 
This is particularly true with new operation- 
al systems. Facilities should be designed to 
accommodate the unforeseen. Quite often the 
unforeseen is a result of an incomplete 
analysis of the operational and system 
requirements prior to facility design, but 
also new requirements will emerge. A contri- 
buting difficulty is NASA's facility approval 
process, which is instituted before a reliable 
utilization analysis is available. It is prudent 
to provide capacity for some growth to ac- 
commodate new requirements. 

Another nontechnical factor that is of 
increasing importance to NASA is life cycle 
costing (LCC). NASA has not traditionally 
incorporated LCC as a critical selection, de- 
sign or engineering process. The elements 
critical to LCC have all been managed and 
considered, but an LCC process has not been 
established within NASA or by NASA's con- 
tractors as a routine process. LCC was used 
as a contract selection factor by NASA for 
the first time in 1988 with the selection of 
the second Tracking and Data Relay Satel- 
lite System (TDRSS) Ground Terminal. It is 



rare that a contractor has an established 
technique to trade and iterate design cost 
against operations costs. LCC needs to be a 
driving discipline to assure that the costs of 
operating the increasingly more sophisticat- 
ed flight systems can be controlled. The 
flight systems of today are projected for 15- 
20 years of operation. This demands that the 
operational support systems be analyzed and 
designed to minimize LCC, or the cost of op- 
erations will increasingly erode NASA's re- 
sources for new development capacity. 
NASA and its contractors should establish 
more sophisticated models of development, 
operations and maintenance costs that will 
provide more reliable data for conducting 
operations cost trades against alternative 
system designs. 

Systems Engineering and 
Operational Support Systems 

Systems engineering for operational support 
systems follows the traditional disciplines 
applied to the development of major flight 
systems. Operational support requirements 
need to be translated into performance pa- 
rameters and configurations through multi- 
ple iterations to optimize system design. The 
purview of systems engineering includes 
requirements definitions and verification, 
system analysis and design, integration 
planning, requirements control, configura- 
tion control and testing. 

While similar to the design and develop- 
ment of major flight systems, the emphasis 
of the systems engineer for operational sup- 
port systems is generally to provide generic 
support to an aggregate of flight programs 
and the increasing necessity to provide sys- 
tems with extended operational usefulness. 
This operational longevity can be attained 
by systems capable of accommodating 
change while continuing to provide service. 
The Deep Space Network operated by Jet 
Propulsion Laboratory and the Goddard 
Space Flight Network are excellent exam- 
ples of major systems that have provided 



158 



SYSTEMS ENGINEERING FOR OPERATIONAL SUPPORT SYSTEMS 



space flight program support with tracking 
and data retrieval service for 30 years, all of 
the while undergoing changes to provide 
support for increasingly complex missions. 

In addition to providing generic support 
to many users, a vital characteristic of sup- 
port systems is operability. The focus in the 
vehicle development community is principal- 
ly directed toward designing a system that 
optimizes performance; the operations com- 
munity's focus is directed more toward an ef- 
fective and efficient operation of the system. 
Operability emphasizes ease of operation, 
resistance to system problems and failures, 
maintainability, reparability, simplicity, ef- 
ficiency, capacity for growth and modifica- 
tion, and accommodation of users. 

These two features, multiple program 
support and system operability, are key to 
assuring the proper systems engineering of 
operations support systems. They are 
historically the most difficult to sustain as 
cost and schedule pressures frequently tend 
to compromise the system's range of utility 
and operability. 

REQUIREMENTS, EVALUATION, 
VERIFICATION AND CONTROL 

Operations systems development is general- 
ly driven by new, expanded or improved 
support service required by new flight pro- 
grams or expanded program objectives. The 
systems engineer needs to challenge user 
requirements to assure the "real" needs are 
not sacrificed at the expense of low priority, 
highly demanding requirements. Occasion- 
ally, requirements are driven by the fact 
that new technology is available and not 
that it is essential (or even desirable) for 
effective operation. The systems engineer 
must consider the broad base of program 
users and not provide a narrow focus of 
support that overly complicates or ignores 
operations of the aggregate of users. 

While sharply defining real needs, it is 
equally critical to consider the potential to 
provide for future capacity. In the informa- 



tion age, the computer (including software), 
communications, and electronics industries 
have developed new technologies and capa- 
bilities often before a flight program's sup- 
port requirements are established. The 
incorporation of these new services needs 
careful examination and scrutiny; when 
these new services clearly enable future or 
expanded programs, however, the operation- 
al community should provide them to 
enhance future operations. An example of 
capability beyond defined need was clearly 
incorporated in the TDRSS program in 1975. 
The TDRSS provides capacity and data rates 
that will meet the requirements of the 1990s 
and well into the next century. It has also 
enhanced flight control concepts by greatly 
increasing the capability to access and con- 
trol spacecraft. If phasing in of added capa- 
bilities can be accommodated, it will permit 
smoothing of resources and help the budget- 
ing process. 

Another important consideration of the 
systems engineer in the evaluation of sup- 
port requirements is the impact these 
services will impose on the user. The goal is 
always to limit the interface restrictions 
imposed on the user program. Two of NASA's 
major operating systems have caused major 
constraints in their use. The Shuttle Pro- 
gram has imposed major safety and integra- 
tion complications on deployed payloads and 
the TDRSS program has imposed scheduling 
and radio frequency interface constraints 
that have been restrictive to some users. 
Some of these constraints with both the 
Shuttle and the TDRSS were intrinsic to 
their operational concepts, but some were 
avoidable, had operability and utilization 
been more completely evaluated. 

When developing systems such as the 
Shuttle and the TDRSS that represent a 
major departure in operating concepts and 
expansion of the operational envelope, the 
systems engineer needs to broaden analysis 
to the entire mission or spectrum of missions 
to better define and limit the major compli- 
cations to system operations and utilization. 



159 



NAL MONOGRAPH SERIES: SYSTEMS ENGINEERING PAPERS 



NASA's experience with both of these pro- 
grams has clearly indicated much more ef- 
fort is required to operationally understand 
the implications of their use. This experience 
should be understood and applied in the de- 
velopment of the Space Station, the Earth 
Observation System, and their associated 
support systems in consideration of their 
broad utilization objectives. 

Requirements verification and control is 
generally practiced with all new develop- 
ments, but control can be difficult to sustain 
throughout an extended development of an 
operational support system and its oper- 
ational life. Unfortunately, the nature of 
flight programs is to evolve operational sup- 
port requirements and occasionally to trans- 
fer capabilities planned for the flight system 
as requirements to the ground support sys- 
tems. Careful monitoring and control of 
these requirements is essential, particularly 
in the development of software support sys- 
tems. Requirement changes will constantly 
occur, however, and an efficient process to 
identify, approve and control requirements is 
vital. Clear and precise interface definition 
is necessary to enable this control. A detailed 
knowledge of the flight programs that intend 
to use the support system, as well as an un- 
derstanding of other related support systems 
(operational support systems rarely provide 
the total functional support services), is re- 
quired for effective requirements control by 
the systems engineer. Interface definition 
and control are essential to maintaining 
requirements control. 

System Architecture and Software 
Design 

For those operational systems that contain 
standard computers and specialized soft- 
ware, which are a majority of the ground 
systems, a special subset of systems engi- 
neering must be performed to obtain the op- 
timum hardware and software combination. 
The selection of the wrong hardware may 
result in software needs that are difficult 



and expensive to develop. Similarly, less 
expensive hardware solutions may be possi- 
ble when the full range of software abilities 
is considered. (The designer must always 
bear in mind, however, the probable need for 
system expansion, which may make the 
selection of a more complex hardware ele- 
ment the prudent choice since software modi- 
fications are generally less costly than 
computer replacement.) This analysis of 
system architecture may involve the estima- 
tion of size, complexity and structure of the 
software needed for a series of mainframe 
computers. 

Management and the systems engineer 
must realize the definition, design and 
implementation of major software packages 
require the same systems management 
disciplines and controls as do hardware 
components. Because software code can be 
easily erased or changed, it does not follow 
that changes should be considered any more 
lightly than they are for hardware. The 
flexibility associated with software is its 
greatest asset, but if not well managed and 
controlled, it becomes its greatest problem. 
Although software design has made aston- 
ishing progress over the years, software 
development remains a significant problem 
to most major systems. The inability of 
management to accurately predict software 
costs, delivery schedules and performance 
has consistently been a severe problem in the 
development of major operational systems. 

Long-range Requirements 

An area often inadequately considered in 
the design of a support system is its capacity 
for future modification and upgrade as new 
technology becomes available and as re- 
quirements change over time. Many systems 
must continue to provide services while 
undergoing these modifications. Proper con- 
sideration for redundancy and capacity can 
greatly alleviate future expense and compli- 
cations. Making assumptions regarding 
future support requirements can lead to a 



160 



SYSTEMS ENGINEERING FOR OPERATIONAL SUPPORT SYSTEMS 



system design that reasonably accommo- 
dates alternative future growth require- 
ments. Designs that fail to gracefully accom- 
modate change are limited and will lead to a 
dead end. 

While the Deep Space Network and the 
Goddard Space Flight Network have effec- 
tively accommodated change, the initial 
design of the TDRSS ground station failed to 
properly consider the long-term need to mod- 
ernize and upgrade. This required extensive 
redesign and change at significant cost. A 
focus on the current needs may result in 
limited system utility, and pressures to 
implement the least cost system may con- 
strain future expansion and ultimately, be 
the least cost effective. 

The development of new features or major 
changes to operating systems is frequently 
implemented with new contractors. General- 
ly, if NASA and the systems engineer did not 
specifically assure that the original contrac- 
tor provided adequate hooks, the new con- 
tractor's implementation will be difficult and 
costly. The term "transition phase" is ap- 
plied by NASA to the period when an online 
system is undergoing change while continu- 
ing to provide support services. This is a deli- 
cate and challenging problem to the systems 
engineer and critical in the selection of an 
appropriate design. It is important that tran- 
sition be planned in conjunction with the 
design process and not after the design is 
established. 

In considering long-range requirements 
for operational systems, the type of system, 
the importance of support, and accessibility 
are major factors. These factors were central 
to NASA's decision and ability to sustain the 
Deep Space Network (DSN) and the Goddard 
Space Tracking Network over their extended 
lifetimes while undergoing numerous modi- 
fications and changes. The continuous avail- 
ability of these sites has been possible 
because of the redundancy within each 
ground station, a configuration of multiple 
sites (redundancy among the ground sta- 
tions), and their accessibility. The recent 



major rebuilding of the 240-ft. DSN antenna 
reflectors prior to the Uranus Encounter was 
feasible because each antenna was sequen- 
tially modified, and alternate antenna 
systems were available at each DSN location 
to provide continuous tracking support. 
Redundancy within the system— provided 
because of the critical nature of tracking and 
communications support — and ground sta- 
tion accessibility have been critical to 
NASA's ability to continuously operate these 
networks while modernizing their capabil- 
ities. 

When considering system changes, space- 
based operational support systems present a 
different challenge. Two major factors influ- 
ence the consideration to change— accessi- 
bility and cost. Cost is directly related to the 
lack of direct access. Accessibility is difficult 
at best and impractical for most. The Hubble 
Space Telescope is accessible at great 
expense by using the Shuttle but the TDRSS 
satellites are presently inaccessible. The 
systems engineering of space-born support 
systems must consider the criticality of the 
service to be provided, the longevity of the 
service (providing adequate redundancy and 
projected service requirements), and the lack 
of ready access to the system. Satellites can 
of course be replaced by an upgraded satel- 
lite; systems that use multiple satellites at 
multiple locations, however, such as TDRSS, 
require identical satellite configurations to 
provide orbital coverage as an effective oper- 
ational system. Spacecraft replacements are 
normally planned to sustain the system 
through its projected life with no ground in- 
terface and no service changes to the system. 

When new services become necessary, 
they are expensive and require an extended 
period to implement. A space-based system 
that consists of several satellites, such as 
TDRSS, requires a change to the services of 
each satellite in orbit to provide an effective 
orbital service to the user. This is consistent 
with the practice of upgrading all ground 
station locations to the same service configu- 
ration; the accessibility makes the upgrade 



161 



NAL MONOGRAPH SERIES. SYSTEMS ENGINEERING PAPERS 



of space systems more costly and requires a 
much longer time. 

NASA is now planning to modify the 
TDRSS with a higher data rate KA band 
service. The system and budget planning for 
this upgrade was begun in earnest in about 
1985, and it is anticipated the satellite fleet 
will not be in orbit until early in the next 
century, a 15- to 20-year period. The TDRSS 
will have been operating for 20 years or more 
by that time. A similar projection will mean 
the replacement system, Advanced TDRSS, 
will likely be operating to the year 2020 and 
perhaps beyond. It is clear this system will 
be as challenging as the original, with new 
problems replacing those resolved with 
TDRSS. The transition of replacing the 
TDRSS systems presents a significant new 
challenge not faced with initiating the origi- 
nal service. Providing systems engineering 
for the Advanced TDRSS to remain viable 20 
to 30 years in the future will tax any man- 
ager. Systems can no longer be replaced 
frequently or modified to meet individual 
program desires. Careful and complete sys- 
tem analysis and forward-thinking engineer- 
ing are essential to the establishment of 
durable, effective support systems. 

ASSURING OPERABILITY 

To succeed in developing a support system 
that meets the goals of operability — ease of 
operation, failure resistance, maintainabil- 
ity, efficiency, expandability and accommo- 
dation to users — requires continuous effort 
and emphasis by the systems engineer. An 
oversight and regular review from the opera- 
tor's viewpoint will contribute to success. 
Both the government and the contractors 
should provide an operational position with- 
in their program management structure that 
is responsible for maximizing the system's 



operability. Developments that continuously 
focus on the ultimate operation are consis- 
tently superior in performance and in total 
costs. 

The need for NASA to be alert to systems 
engineering is more prevalent now than ever 
before in NASA's history. The implementa- 
tion of new operating systems is planned 
throughout the 1990s to prepare the agency 
for managing the operations of complex, long 
duration and extremely high data rate pro- 
grams. The quantity of data the agency will 
be processing and managing in the later part 
of the decade was unimaginable in the 1960s 
and the 1970s. This data will be generated 
by programs that will be launched in a 
period when NASA will already be operating 
and supporting a complex array of flight 
vehicles. New ground systems, with evolving 
capabilities and changing interfaces, will 
come into operation almost continuously 
throughout this period. The complex nature 
of interaction among these systems demands 
a visibility and overarching control that can 
only be accomplished through a systems 
engineering network. Management and co- 
ordination of the individual systems is re- 
quired to assure total system functionality, 
interface definition, requirements control 
and the optimization of each system. 

NASA has done an excellent job for the 
past 30 years in providing an operations 
infrastructure that has met the demands of 
exploring space. The next 30 years of space 
operations are equally exciting but represent 
a far greater challenge. The quality of the 
systems engineering of the operations 
support team is critical to both the success of 
the nation's civil space flight programs and 
to sustaining a viable operational role with- 
in NASA. 



162 



POLITICAL AND INSTITUTIONAL FACTORS OF SE 



Political and Institutional 
Systems Engineering 

by John F. Yardley 

Most systems engineering courses and text- 
books discuss only the engineering aspects of 
the subject and are silent about the non- 
technical world's influence on the planned 
project. This approach, although entirely 
satisfactory for many engineering programs, 
including smaller NASA programs, leaves 
out a significant element affecting large 
NASA programs. Some traditionalists be- 
lieve these nontechnical aspects should not 
even be considered in the systems engineer- 
ing process. However, if we take the broad 
view that systems engineering should take 
into account all significant requirements in 
order to produce the proper end-product, 
then it should include consideration of those 
outside non-technical parties who can levy 
requirements on NASA programs. This pa- 
per identifies these elements, discusses their 
viewpoints and probable influence, and re- 
views some past case histories as illustra- 
tions of these problems. It also presents some 
suggestions for working with these non- 
technical groups, which ma} better achieve 
overall optimum systems engineering and 
integration (SE&I) solutions. 

THE NON TECHNICAL GROUPS 

There are many outside parties that provide 
inputs to NASA program requirements. 

The public at large can have a profound 
influence on whether large sums are appro- 
priated for NASA's major programs. They 
respond to NASA triumphs and disasters 
and are sensitive to NASA's role in projec- 
ting the American image around the world. 
Their influence is exercised by letters to 
Congress and the White House, by public 
appearances (interviews and speeches, for 
example), and through public opinion polls 



N 9 3 - #4 6^0 
Factors Affecting 

regarding the space program. All of these 
methods influence both the executive and 
legislative branches of our government. 

The President and his staff are very im- 
portant to NASA's programs. They must 
make a positive decision to include money for 
specific NASA programs in the budget re- 
quest before it is even considered by Con- 
gress. In these times of large government 
deficits, which makes starting new programs 
very difficult, NASA is pressured to cut back 
requirements and save money. This pressure 
even results in the stretch-out and cancella- 
tion of some ongoing projects. Sometimes in 
negotiations with the Office of Management 
and Budget, NASA is asked to choose be- 
tween programs. 

The Congress is one of the most signifi- 
cant groups that has a major impact on 
NASA's requirements. In addition to repre- 
senting their constituents' opinions, mem- 
bers feel it is their duty to closely watch the 
details of NASA's large programs. In the last 
several decades, they have acquired the tech- 
nical staff needed to exercise this detailed 
oversight. As a result, they are in a position 
to demand program requirement changes, 
and they have the appropriation muscle to 
back up their demands. 

The Department of Defense (DoD) and 
other national security agencies often get 
involved in NASA's programs because they 
have agreed to participate in a joint develop- 
ment or because they plan to use the end- 
product. They are involved in monitoring 
NASA's projects from a national security 
viewpoint, and they sometimes require 
changes in NASA programs if they see 
potential security problems. DoD is always 
included as a major player in any high-level 
White House space study or committee. 




163 



READrNGS TN SYSTEMS ENGINEERING 



Some NASA partisans feel that certain DoD 
offices take a biased view and try to reduce 
the NASA program so DoD can play a larger 
role in space study. 

Other executive departments substan- 
tially involved in NASA program matters 
include the State Department, the Com- 
merce Department, the Transportation 
Department, and the Office of Management 
and Budget. 

Government agencies and national com- 
missions that fact-find, study and advise the 
executive and legislative branches upon re- 
quest include the General Accounting Office, 
the Office of Technology Assessment, the 
National Academy of Sciences, the National 
Academy of Engineering, the National 
Research Council, the National Commission 
on the Challenger Accident, the Advisory 
Committee on the Future of the U.S. Space 
Program, and a number of other ad hoc com- 
mittees. 

International cooperation agreements 
often involve political considerations, and 
the foreign parties usually desire a part of 
the job that interfaces with many of the 
mainstream elements. If these agreements 
are not structured with the interface prob- 
lems in mind, they can have major effects on 
systems engineering. 

Scientific specialist groups feel they could 
more wisely spend the money appropriated 
for the large NASA manned space programs 
on their own research or on unmanned scien- 
tific space programs. This group sometimes 
works through "associations" seeking to 
plead their case in the media. 

Local communities near NASA centers 
often inject themselves into the process of 
dividing the program work between Centers. 
The actual division of work can have a sub- 
stantial effect on the efficiency of the collec- 
tive NASA effort and can make the systems 
engineering effort much more difficult than 
a distribution based on technical merits. The 
political realities usually result in a "techni- 
cally non-optimum" work split. 



Examples from the Past 

History provides examples of political and 
institutional influences that illustrate how 
these factors affect NASA's programs. After 
the first Sputnik launch, the basic thrust to 
start the space agency, as well as to initiate 
the Mercury Program, came mostly from 
Congress, with lukewarm support from the 
Eisenhower administration. NASA's foun- 
ding organizations, the National Advisory 
Committee for Aeronautics (NACA), was 
used as a technical staff; decisive actions 
were primarily political in nature. 

During the sixties, the Kennedy Admin- 
istration's decision to land astronauts on the 
Moon and return them safely was political; 
namely, to catch up with the Russians and 
get back U.S. world technological leadership. 
NASA provided a large part of the technical 
staff work, which consisted of preliminary 
analyses and estimated success probabil- 
ities. 

In the case of the Space Shuttle start deci- 
sion, interaction increased between systems 
engineering and the non-technical world. 
Richard Nixon had become President in ear- 
ly 1969, just a few months before the lunar 
landing. He requested the National Space 
Council to study and report on the options for 
the next phase of space flight and the long- 
term future. NASA was heavily involved in 
this year-long study. The report recommend- 
ed that development of a Space Station and a 
fully reusable Space Shuttle be undertaken 
in parallel as the next step in manned space 
flight and as the precursor of later lunar 
colonies and manned Mars expeditions. At 
this point, a political decision was made to 
continue study of the Space Shuttle but to 
defer the Space Station. Work then proceed- 
ed on the Shuttle with Phase A contracts and 
then Phase B contracts. It soon became 
apparent that the Shuttle development cost 
was more than double the original prelimi- 
nary estimates used in earlier decision 
making. Much interaction ensued between 



164 



POLITICAL AND INSTITUTIONAL FACTORS OF SE 



NASA, the Office of Management and Bud- 
get, and Congress, with NASA trying to get 
the added funding commitment. When this 
was not forthcoming, the program manage- 
ment exhorted the projects to reduce cost 
without changing the basic concept. 

After more work confirmed that the cost 
ceiling could not be achieved with the two- 
stage fully reusable Shuttle, it was finally 
decided by NASA management that the 
concept had to be changed in order to stay 
within funding limitations imposed by the 
Administration. Phase B contracts were 
extended, a major realignment of contractor 
teams was required, and the current Space 
Shuttle configuration (solid first stage, 
parallel burn) emerged. After the Apollo 
program and its blank check atmosphere, 
NASA was not used to this limited funding 
approach. 

This process left much to be desired from 
many points of view. It delayed the program, 
caused a lot of wasted effort, and contractors 
formed teams and wasted a lot of their dis- 
cretionary funds (estimated at $100 million). 
No one is to blame for this, since everyone 
was feeling their way in a new environment. 
A better process, however, would have been 
very worthwhile. 

In contrast to the Shuttle, the Space Sta- 
tion did have strong support from President 
Reagan. This support was not for short-term 
political gain but rather because President 
Reagan believed it was in the best long-term 
interest of the country, despite the fact that 
most of the President's cabinet members and 
his close advisors were against starting the 
space station (Hans Mark's book). 

The fragmented nature of the final Space 
Station hardware split between Centers 
resulted from an intense tug of war for 
appropriate shares of the program between 
the NASA Centers and their supporting 
political communities. Some NASA Centers 
felt that much of this struggle was for their 
very survival. Others in NASA felt this type 
of work distribution was necessary for broad 
Congressional support. While the final sys- 



tem is probably workable, it certainly is not 
considered optimum from a technical or effi- 
ciency viewpoint. 

MINIMIZING DISRUPTION FROM 
POLITICAL AND INSTITUTIONAL SOURCES 

We have identified many of the outside 
sources of SE&I requirements and have 
given some examples to illustrate how im- 
portant these inputs can be. Although most 
of these examples involve major program 
changes, many smaller requirements are 
questioned and changed. Now we will discuss 
methods of dealing with these inputs effi- 
ciently, minimizing disruption and avoiding 
adversarial relationships with these outside 
organizations. 

Good two-way communication between 
NASA and these outside groups is one of the 
major keys to negotiating proper agreements 
on these external requirements. In order to 
properly deal with these outside inputs, we 
need to know what new requirements they 
are considering before these requirements 
are placed on NASA as irreversible de- 
mands. If we wait until then, it is very 
probable that we will develop adversarial re- 
lationships with the requester who has "gone 
public" and will be embarrassed to lose the 
argument. This will make the requestor very 
difficult to deal with during subsequent 
negotiations. 

This means NASA must be organized and 
managed in a manner that facilitates com- 
munication of both internal and external 
pertinent information. 

Most of these outside inputs are discussed 
at lower levels during interface or coordina- 
tion meetings as "what if s." They rarely first 
surface at the NASA decision level in the 
program office or the SE&I management. 
This means that the lower-level NASA peo- 
ple interfacing with outside organizations 
must be trained to recognize these potential 
inputs at the beginning, and the overall 
NASA organization must have good commu- 
nications at all levels so these issues can get 



165 



readings in systems engineering 



to the appropriate level early, a strategy can 
be developed, special analyses can be per- 
formed, and contacts to discuss the issues 
can be planned. 

When preparing the material for discus- 
sion with the requester, NASA must be very 
careful to consider the requestor's point of 
view objectively and not just from the NASA 
parochial viewpoint of pure engineering 
ease, i.e., the "invented here" syndrome or 
the "bad for the Center" rationale. NASA 
must remember it is not the user or the own- 
er but rather the implementor of someone 
else's requirements. When presenting the 
material, NASA must be careful to avoid 
patronizing the requester. If the requestor 
senses a patronizing attitude, the relation- 
ship rapidly becomes adversarial. 

It is also important for NASA to advise 
and sell the appropriate outside groups on 
any requirement changes they feel are neces- 
sary before the action has been taken beyond 
the point of reasonable return. This is par- 
ticularly true when NASA wants to relax 
requirements that were important to outside 
groups once the program was begun. Many 
examples exist where Congress finds out 
after the fact that the program can no longer 
meet the planned launch rate or some other 
fundamental requirement, and the original 
"NASA promise" must be broken. This has a 
very negative effect on rapport with Con- 
gress, the scientific community or any other 
major stakeholder. It is therefore important 
to level with these outside groups as quickly 
as possible after deciding to revise a basic 
requirement. 

NASA must also develop harmonious re- 
lationships with the pertinent outside groups 
and individuals. This can be done, among 
other ways, using a network of committees or 
scheduled small meetings among selected 
individuals. The important thing is to plan 
for relationships and have the meetings reg- 
ularly. These meetings should be used to 
bring the groups up to date, to permit them 
to ask questions and critique the activity, to 
smoke out impending requirements, changes 



or additions, and to develop rapport. While 
doing these things, it is very important for 
NASA individuals to come across as open, 
forthright, and on top of their jobs. If the out- 
side participants sense ulterior motives that 
are not discussed, or evasiveness and bluff- 
ing, trust cannot develop. In fact, many of 
these groups currently have a "corporate 
memory," which includes perceptions of 
many NASA Center biases. These must be 
overcome by careful and fair negotiations, 
bending over backward to diffuse any biased 
reputation. 

NASA Centers have tended to think of 
many of these non-technical meetings as 
NASA Headquarters' responsibility (and a 
big, time-wasting nuisance), believing the 
Center's only role should be the engineering 
and management of the program. For NASA 
to do the most efficient and effective job, this 
concept must be changed. Whereas NASA 
Headquarters should participate in many of 
these contacts, the Center people who best 
know the subject and have prepared the 
material should present it. This is also an 
excellent training mechanism. The younger 
Center people will rapidly develop a much 
broader view of the outside world from inter- 
acting with NASA. Working with the 
centers in this manner, Headquarters also 
facilitates better internal communications. 

Interfacing with Congress presents some 
special problems, particularly when NASA 
is trying to sell them a new program. There 
are laws prohibiting government employees 
from lobbying, and the line between lobbying 
and briefing on the merits of a new program 
is somewhat blurred. NASA must use its leg- 
islative and legal offices to help the program 
people properly interpret the law. In all 
probability, NASA will not be able to com- 
municate with Congress on critical subjects 
in the manner and with the frequency they 
desire. 

An alternative to direct NASA communi- 
cation with Congress is for NASA to work 
with its contractors and keep them informed. 
The contractors are not bound by any laws 



166 



POLITICAL AND INSTITUTIONAL FACTORS OF SE 



against lobbying and can communicate more 
freely with Congress. The contractors will 
contact the appropriate Representatives and 
their staffs with their own messages, in any 
case. It is not necessary for NASA to direct 
them to lobby (this being illegal), but NASA 
should inform them of its position so that if 
the contractors do contact Congress, they 
have the correct information. 

On some past programs, all of the prime 
contractors informally worked together to 
keep Congress informed. One technique that 
has been popular with Congress is an "Infor- 
mation Notebook" on a given NASA pro- 
gram. This notebook is kept in the Congres- 
sional member's office for easy reference and 
is updated monthly, providing a useful 
monthly resource for informal discussions. 

NATIONAL STRATEGIC PLANNING FOR 
SPACE 

After the Apollo program and President 
Kennedy's clear mandate to land astronauts 
on the Moon and return in the sixties, the 
U.S. space program suffered from a lack of 
clear national goals and a strategic plan to 
achieve them. In the Apollo era, all of the 
diverse forces involved coalesced behind 
President Kennedy because they wanted to 
beat our superpower adversary, the U.S.S.R., 
in the technological war. Since that time, we 
have been unable to generate such a unify- 
ing environment. If this could be done, and a 
framework for future space activity could be 
agreed on in the form of a strategic plan, the 
problems of interfacing with the outside 
groups would be much easier. 

As of this writing, the Bush administra- 
tion has outlined a long-range plan for explo- 
ration that includes colonizing the Moon a 
and a manned exploration of Mars, which 
could form the framework for a good strate- 
gic plan. However, it must be accepted by 
these outside parties and backed with appro- 
priations by Congress before any plan can 
realistically be made. During this period of a 
growing national deficit, tensions in the 



Middle East, and the bail-out of the savings 
and loan industry, such an ambitious plan 
will be difficult to accomplish. 

SUMMARY AND CONCLUSIONS 

External groups have a significant impact on 
NASA's programs. Ten groups affecting 
NASA are identified, and examples are 
given for some of the them. Methods of deal- 
ing with these external inputs are discussed, 
the most important being good and open two- 
way communications and an objective atti- 
tude on the part of the NASA participants. 
The importance of planning ahead, of devel- 
oping rapport with these groups, and of effec- 
tive use of NASA contractors is covered. The 
need for an overall strategic plan for the U.S. 
space program is stressed. 

In order to obtain the broadest range of 
opinions on the political and institutional 
factors that affect systems engineering, the 
writer requested thoughts from a number of 
senior individuals who have been involved in 
the interfaces between NASA and the out- 
side world. 

In any subject as complex as this one, 
there are always some differences of opinion. 
The viewpoints expressed above are those of 
the writer and sometimes agree with the 
majority, and at other times do not. To pro- 
vide the reader with another viewpoint, an 
additional paper by David Wensley is repro- 
duced in its entirety in the appendix to this 
chapter. Mr. Wensley examines the subject 
through the eyes of a prime Space Station 
contractor executive. 

The author concludes that NASA does not 
pay sufficient attention to the impact of 
political and institutional factors in con- 
ducting its business and is being hurt by this 
attitude. NASA should therefore focus on 
working with these outside groups, adjust 
NASA policies and organizations to 
facilitate interfacing with them, and train 
NASA personnel to conduct themselves ap- 
propriately in this environment. 



167 



POLITICAL AND INSTITUTIONAL FACTORS AFFECTING SE 



Political and Institutional Factors Affecting 
Systems Engineering: an Industry Perspective 

by David Wensley 



The "nominal" or "idealized" systems engi- 
neering process must take into consideration 
the political and institutional factors that 
have become prevalent in the government 
funded and, to a certain extent, the privately 
funded civil space activity. Attempts to ig- 
nore these influences may result in delay and 
frustration of the systems engineering pro- 
cess. 

NASA programs are currently growing 
larger in scope, longer in duration and fewer 
in number. The increasing number of partici- 
pants includes NASA Centers, other U.S. 
agencies, international agencies and contrac- 
tors. NASA programs are also characterized 
by higher public visibility, and are more cost- 
ly and more politically sensitive. 

In this environment, the Congressional 
committees that appropriate and authorize 
budgets will demand more justification for 
expenditures, more political return from the 
investments and more oversight of ongoing 
activities. 

POLITICAL FACTORS 

Space projects have always been an instru- 
ment of domestic politics and a tool of politi- 
cal influence in international relations. As 
the scope and importance of these projects 
increases, we can expect more political influ- 
ence on the systems engineering process. 

The political influence may take any of 
several forms: 

• Geographical distribution of funds to gain 
political support. 

• Creation of international partnerships. 

• Insertion of technical requirements to 
satisfy strategic national goals. 

• Increased Congressional and Administra- 
tion involvement in the technical 
decision-making processes. 



PREGEDING PAGE BLANK NOT FILMED 



• Funding constraints used as a mechanism 
of technical and political control. 

An effective project management and 
systems engineering process must deal con- 
structively with these influences. They may 
affect program content, allocation of respon- 
sibilities, schedules, interface definitions, 
optimization and trade-off criteria, and tech- 
nical decisions. They may even affect mission 
definition, and they most certainly will affect 
funding availability versus time. Effective 
management must provide for flexibility to 
react to these influences without undue pen- 
alties on performance, cost or schedule. A 
constructive and cooperative relationship 
between the legislators and program man- 
agement can minimize the impact of these 
interactions on planned efforts. 

Many examples of the influences noted 
above can be cited in the Space Station Free- 
dom program, including: 

• Legislated use of a Flight Telerobotic 
Servicer to advance U.S. robotic technol- 
ogy- . x 

• Allocation of responsibilities to interna- 
tional partners. 

• Political influence on the work distribu- 
tion between NASA Centers. 

• Increased complexity of interfaces and 
management processes resulting from 
distributed responsibilities. 

• Funding constraints (fencing) in budget 
authorization bills. 

• Oversight committees and hearings to 
critique technical progress and to influ- 
ence resolution of technical issues. 

The systems engineering process must 
stand the tests of external review and cri- 
tique. The assumption that technical man- 
agement and decision making is part of an 



-'**Bi 



Ho 



i 



Wtt»c=p5 ? . j . 



■MUWUjujwWJ &*$: 



169 



READINGS IN SYSTEMS ENGINEERING 



immune internal process is, unfortunately, 
unrealistic. Techniques for effectively 
managing the external factors include: 

• Open communication between project 
management and stakeholders to under- 
stand needs and develop trust. 

• Realistic planning to support schedule 
and cost commitments. 

• Disciplined control of requirements to 
avoid unwarranted cost and schedule 
growth. 

• Effective use of risk management tech- 
niques to minimize iterations on design 
and testing. 

• Cost-effectiveness and life-cycle cost ana- 
lysis to substantiate trade decisions. 

• Early emphasis on operations, mainten- 
ance and logistical support to avoid un- 
predicted support costs. 

• Early constructive resolution of responsi- 
bility conflicts between NASA Centers 
and between NASA and international 
partners. 

These features are characteristic of tradi- 
tional management and represent the expec- 
tations of legislators and budget authorities. 
Deviations from these norms, especially if 
uncovered through Congressional or media 
probing, can be disruptive and potentially 
dangerous to the stability and continuity of a 
program. The systems engineering process 
can significantly reduce these risks by stay- 
ing on track and by making summary data 
available to project managers to use in open 
dialogue with legislators. 

Program changes are unavoidable, and 
systems engineering and project manage- 
ment must be equipped with the analytical 
tools to respond effectively to these changes. 
The ability to re-prioritize and reschedule ac- 
tivities rapidly and with reasonable accuracy 
is essential, especially in response to funding 
adjustments emanating from the annual 
budgetary process. More often than not, 
these events are unanticipated and result in 
traumatic and costly adjustments. A pre- 



planned strategy for deferral of less critical 
elements, retaining the systems engineering 
effort to establish interface requirements 
and essential design definitions, can mini- 
mize such effects. 

Institutional Factors 

Numerous institutional factors will affect 
the systems engineering process, principally 
those inherent in NASA and the participat- 
ing Centers. Examples include: 

• Accepted standards, design criteria, and 
specifications. 

• Design, management and operational 
preferences of the Center functional divi- 
sions. 

• Availability and preference for use of 
Center test facilities. 

• The organization and management struc- 
ture adopted for the program. 

• Traditional practices such as use of com- 
mittees, panels, boards, documentation 
formats and integration processes. 

• Use of support contractors to supplement 
NASA staff. 

• NASA and Center policies and priorities 
that may influence, for example, technol- 
ogy selections, responsibility issues and 
requirements decisions. 

The above considerations can have a 
major impact on systems engineering 
requirements derivations, trade studies, ar- 
chitecture and design selections, test plans 
and operational concepts. They will also af- 
fect the schedule and effort required to 
evolve the design baseline, to resolve inte- 
gration issues and to establish interface 
agreements. The potential magnitude of 
these effects dictates early planning for their 
accommodation in the systems engineering 
process. It is virtually pointless to embark on 
a systems engineering process that ignores 
these considerations. The institutional char- 
acteristics have evolved over time and are 
the product of many successes and failures. It 



170 



POLITICAL AND INSTITUTIONAL FACTORS AFFECTING SE 



is unlikely that personnel assigned to new 
projects will adopt practices that violate 
tradition. Contractor personnel should be 
prepared to adapt to customer preferences, 
but customer (NASA) personnel should be 
prepared to consider new alternatives as part 
of a continuous improvement process. 

The Search For Improvement 

Increased budget pressures and heightened 
concern for foreign competition create a 
demand for NASA to seek new methods of 
achieving quality and reducing costs. Indus- 
try is similarly under pressure in these areas 
and is rapidly adopting techniques such as 
Total Quality Management (TQM) princi- 
ples. NASA is beginning to apply TQM crite- 
ria in new procurements and has started to 
look for TQM opportunities within its organi- 
zational structure. Conversion to these prin- 
ciples represents a major cultural change 
and, in many respects, is contrary to recent 
trends within NASA. TQM teachings empha- 
size reduction in top-down management di- 
rection, preferring increased delegation and 
empowerment of the lower tier personnel. 
Since the Challenger accident, the tendency 
within NASA has been to increase manage- 
ment and technical oversight. In the Space 
Station Freedom program, for example, 
many layers of management and technical 
oversight exist within the Level II and Level 
III organizations above the prime contractors 
and their subcontractor teams. Although 
contractors are generally committed to cost 
and schedule objectives, their progress is of- 
ten controlled by the efficiency and speed of 
the NASA management and systems engi- 
neering processes and integration. If the in- 
volved participants agree that improvement 
is essential to create an environment of 
credibility and trust at the political level, 
recognition of these relationships can lead to 
constructive changes. 

Measurement of performance is essential 
in the search for improvement. Both NASA 



and contractors must be measured as ele- 
ments of a closed-loop process that affects the 
efficiency and quality of our space activities. 
The identification of improvement candi- 
dates should focus on the inanimate process, 
not on the organizations or people. This 
allows the people to conduct constructive 
problem identification and resolution with- 
out personal implications. 

Conclusion 

NASA stands at a crossroads. The opportuni- 
ties for space exploration and the exploita- 
tion of space attributes and resources have 
never been better. Public acceptance of space 
projects and reliance on space technology as 
a means to resolve worldwide environmental 
and resource issues have never been higher. 
Yet NASA lacks credibility with the legisla- 
tors of this country who are eager to voice 
criticism of NASA's planning and implemen- 
tation of space projects. Their depth of pene- 
tration into NASA's technical activities is 
increasing. Not only is the continuity of 
NASA funding at risk, the scope of NASA's 
responsibilities is also threatened. Transfer 
of responsibilities to other agencies and even 
the creation of new agencies is topical con- 
versation. Resolution of this dilemma 
requires more than a willingness to commu- 
nicate and to negotiate differences; it re- 
quires a change in the NASA management 
culture that recognizes the degree of matur- 
ity of the space industry. The mystery of 
discovery and the complexity of space tech- 
nology is no longer an adequate defense for 
cost or schedule overruns. Critics demand 
performance that meets expectations. NASA 
has the opportunity to lead the family of 
federal agencies in demonstrating fiscal 
responsibility combined with technical 
achievements. Systems engineering will be a 
major contributor to this success by provid- 
ing the guidance for timely decisions leading 
to effective project management. 



171 



OPTIMIZATION IN THE SYSTEMS ENGINEERING PROCESS 



Optimization in the Systems 

Loren A. Lemmerman 

The essential elements of the design process 
consist of the mission definition phase that 
provides the system requirements, the con- 
ceptual design, the preliminary design and 
finally the detailed design (Figure 1). Mis- 
sion definition is performed largely by oper- 
ations analysts in conjunction with the cus- 
tomer. The result of their study is handed off 
to the systems engineers for documentation 
as the systems requirements. The document 
that provides these requirements is the basis 
for the further design work of the design en- 
gineers at the Lockheed-Georgia Company. 

The design phase actually begins with 
conceptual design, which is generally con- 
ducted by a small group of engineers using 
multidisciplinary design programs. Because 
of the complexity of the design problem, the 
analyses are relatively simple and generally 
dependent on parametric analyses of the con- 
figuration. The result of this phase is a base- 
line configuration from which preliminary 
design may be initiated. 



N 8 3 - 2 4 ©#_£/ 
Engineering Process 

/5^sra3 
f- 7 

Preliminary design is far more complicat- 
ed, both because the analysis techniques are 
more complex, and also because these tech- 
niques require specialized knowledge. The 
objective of this step is to refine the design 
estimates made during conceptual design 
and to add additional detail to the descrip- 
tion of the configuration. At the conclusion 
of this phase, the aircraft is defined well 
enough so that a company can comfortably 
bid the cost of producing it. 

Detail design is largely mechanical in na- 
ture, and normally occurs after receipt of an 
order for production. This is not an area of 
concentration in this presentation, however. 

To provide a basis for amplification of the 
conceptual design process, look at Figure 2. 
The function of the conceptual design process 
is to conduct a multidisciplinary analysis of 
an aircraft to produce values of parameters 
that describe an aircraft. These parameters 
are top level descriptions that leave most of 
the actual configuration details undefined. 



Contracted 
Studies 



1-3 Years 



Mission 
Definition 



System 
Requirements 



1-2 Years 



Conceptual 
Design 



Market Research 
Operations Analysis 



Advanced Design 
Systems Engineering 



Proposal Contract 

Requested Award 



lYear 



Preliminary 
Design 



Aerodynamics 
Structures 
Propulsion 
Aircraft Systems 
Supportability 



Figure 1 Essential Elements of the Design Process 



PREGEDiNG PAGE BLANK NOT FILMED 




Detail 
Design 



-Manufacture 



Project Engineering 

Detail Design 

Stress 

Subsystems 

Weights 

Value Engineering 

Test 



wmm %mi 



173" 



READINGS IN SYSTEMS ENGINEERING 



However, implicit in this process is the 
trading of factors that relate to the perfor- 
mance of the configuration. The trades I 
mean are typified by the thinness of a wing 
desired by an aerodynamicist versus the 
thickness of a wing as desired by a structural 
analyst. 




Multidisciplinary 
Analysis 




Fuselage Dimensions 
Wing Dimensions 
Control Surfaces 



Figure 2 Conceptual Design 

Typical parameters defined at this stage 
are fuselage length and width, wing area, 
sweep, aspect ratio and, to a limited extent, 
control surface. 

In former times, conceptual design was 
manually directed and highly iterative. The 
process consisted of guessing an initial con- 
figuration, analyzing that configuration, and 
then systematically varying each of several 
design parameters to examine a design space 
within which manual optimization could 
take place. Normally the number of param- 
eters examined did not exceed four, because 
of the human limitations in absorbing more 
variations than that. There were several 
disadvantages to the former approach. This 
process was time consuming, fallible and 
tedious. It was time consuming because the 
answer depended on many executions of a 
computer code. It was fallible because the 
choice of the parameter variation to be exam- 
ined was entirely at the discretion of the 
designer. Thus, the quality of the answers 
was directly dependent on the skill of that 
designer. In addition, no one could be sure 
that a large enough design space had been 



investigated to ensure that a true optimum 
had been found. This old procedure was also 
tedious. All data had to be manipulated man- 
ually. Although this did provide useful in- 
sight to the designer, the cost was a further 
delay. Dozens of computer runs had to be 
scanned, the results judged for correctness, 
and the results plotted on carpet plots. Many 
hours of talented labor were consumed per- 
forming menial tasks. 




k Mission 



Guess at 
Initial 
Configura- 
tion 



Optimize 

Subject to 

Constraints 



Evaluate 
Configura- 
tion 



Figure 3 Preliminary Design 

The former process was basically elimi- 
nated at Lockheed-Georgia several years 
ago, in favor of the approach shown here, 
based entirely on numerical optimization. 
The new process is described schematically 
here (Figure 3). The former process was usu- 
ally completed in one day. Many of the man- 
ual actions have been eliminated. Now, a 
given study may consume as much time as 
formerly, but a much larger range of design 
variables has been included. 

Preliminary Design Process 
(Partial) 

The next step in the design process is pre- 
liminary design. This is the process, partially 
illustrated in Figure 4, by which the concep- 
tual design baseline is analyzed in greater 
depth to confirm the design or provide foun- 
dation for changing the design. This process 
is typified by the more or less simultaneous 
execution of many detailed design codes in 
several disciplines. Obviously, the communi- 
cation during the process is difficult, and the 
designs proposed by each discipline are fre- 
quently inconsistent. Iterative loops, while 
very common, cannot be represented because 



174 



OPTIMIZATION IN THE SYSTEMS ENGINEERING PROCESS 



Conceptual 
Desigii 



S/C 



Control 



Surface 



Surface 



Pressures 



Aero 



Engine 



Control 



Loads 



Structures 



Wing 



Weight Constraints 



Needs 



Propulsion 



Electronics 



Prop. Load 



Constraints 



Balance 



Figure 4 Preliminary Design Process 



of the indeterminate sequence of such iter- 
ation. 

As an example of the type of analysis con- 
ducted in this phase, consider aerodynamics 
for a moment. The codes frequently applied 
in this phase consist of full potential subsonic 
or transonic codes for configuration analysis, 
full potential codes for direct design, and 
Navier-Stokes codes for highly complex vis- 
cous flow analyses. As a result of the aerody- 
namic analysis done during this phase of 
design, the wing external contours are fully 
defined and more reliable estimates of the 
vehicle performance are available. Similar 
refinements and definition are added by each 
of the participating disciplines. 

The deficiencies of the current approach 
are immediately obvious. First and foremost, 
the result is a suboptimal configuration. 
Even though optimization may be used 
within isolated analyses, the difficulty of 
communication in real-time and the lack of 
available tradeoff criteria mean that no glo- 
bal, rigorous optimization occurs. 

I have already alluded to the use of opti- 
mization on individual analyses in this 
phase. Here are some examples of such opti- 
mizations. The aerodynamics discipline has 
been very active in developing optimization 
techniques for the design of wings in tran- 
sonic flow, largely based on FLO codes. These 



methods provide a wing shape, starting with 
a specification of a desirable pressure distri- 
bution. Using such methods, the wing con- 
tour and twist distribution may be calculated 

directly. 

Subsonic optimization techniques have 
generally been limited to the design of high 
lift systems. In this case, the optimal location 
of a slotted trailing edge flap can be found by 
optimizing on the axial force for the system 
and by using paneling methods for calculat- 
ing the flap system pressure distribution. 

Structural optimization has been done for 
minimizing structural weight, given loading 
conditions. In this case, the structure is mod- 
eled using finite element techniques, with 
element geometries such as thicknesses or 
cross sectional areas taken as design vari- 
ables. Another example of structural opti- 
mization is in the design of composite panels. 
The objective is to determine the ply orienta- 
tion to respond to specific loading conditions. 

If I were to summarize the preliminary 
design optimization work currently being 
done at Lockheed-Georgia, I would have to 
say that its use is relatively new, that it has 
been very well accepted, and that its use is 
certainly increasing. But this may eventual- 
ly become a severe problem for us, since the 
optimization is being applied to subprocesses 
within design. Worse yet, it is being applied 



175 



READINGS IN SYSTEMS ENGINEERING 



Optimizer w/ 
Constraints 



Evaluate 
Configuration 




Propulsion 



Figure 5 Proposed Preliminary Design Process 



to old design philosophies. The result has to 
be suboptimal designs. 

The preliminary design process is clearly 
another candidate for improvement by opti- 
mization. The technical challenge of this 
problem is much greater that that of the con- 
ceptual design process, but the potential pay- 
off is also much larger. The challenge comes, 
in part, from the large number of individuals 
and computer programs normally invoked at 
this design state, and the current dearth of 
technology available to solve the very differ- 
ent problems thus posed. 

One possible way to apply optimization in 
the preliminary design process is shown 
here. The fundamental idea is that candidate 
design parameters flow downward to the in- 
dividual analysis modules and the result of 
the analysis flows back up to the optimizer. 

Obviously, such a system is far from reali- 
ty. The technical challenges outweigh those 
of optimization itself. The analysis methods 
normally used in preliminary design are 
state-of-the-art methods that are time con- 
suming, user-sensitive and modeling sensi- 
tive. Because of this, not only will new 
optimization techniques be needed, but so 
will entirely new operational procedures. For 
example, optimization now is executed most- 
ly as a black box program. The analysis 
points provided by support codes are consid- 
ered to be correct and not subject to code 



sensitivities. In the preliminary design pro- 
cess illustrated here, the former approach 
clearly will not work. The new process must 
include a method for disciplinary engineers 
to examine the analysis code results as they 
are being generated to ensure that the opti- 
mized results are valid. When such an opti- 
mization method is available, however, I 
submit that the problem is far from finished. 
This is so because people inevitably are the 
designers, and the design techniques, wheth- 
er through optimization or not, must take the 
human element into consideration. 

Systems Engineering - a Definition 

To expand on this theme, let me begin be giv- 
ing you my orientation. I am in the Systems 
Engineering Department at Lockheed- 
Georgia. This gives a reasonable definition of 
what Systems Engineering means to us: a 
discipline that coordinates the engineering 
activities within large organizations to help 
produce a superior, cost-effective, timely 
product. By its very definition, it is a process 
of dealing with people in a large design op- 
eration. As such, our interest is not in the 
internal working of design codes, but rather 
in how individuals use given design codes to 
produce designs, and then how those indi- 
viduals transmit their information to other 
designers in the organization. 



176 



OPTIMIZATION IN THE SYSTEMS ENGINEERING PROCESS 



Let me present the four main tasks of the 
Systems Engineering operation. They 
involve the management of trade studies, re- 
quirements, interfaces and technical risk. 
Another way to express these four tasks is 
Communication, Communication, Communi- 
cation, Communication. 

Decisions are the design process. By its 
very nature, design requires definition of 
some configuration from an infinity of possi- 
bilities. The best design is some compromise 
of many and widely varying constraints. 
Many times the choices to be made are 
aesthetic, or subjective, or not amenable to 
computer analysis. In these situations, and 
sometimes even in well-defined engineering 
choices, trade studies must be performed that 
are outside the domain of the optimization 
process. 



Vehicle 

[ 









r 








1 










Self-contained 




External 






1 










1 




1 






Passive 




Active 






1 




1 








1 


r 














INS 




TR 





Figure 6 Hierarchy of Decisions to Select a 
Navigation System for an Airplane 

The illustration above (Figure 6) is a sim- 
ple representation of the decisions that 
might be made to select a navigation system 
for an airplane. These choices are displayed 
as a hierarchy, beginning with the top level 
vehicle considerations, and then working 
downward to finer levels of detail. Systems 
Engineering is responsible for generating 
such a trade tree to illustrate the decisions to 
be made, defining the design groups to be 



involved, coordinating the studies needed, 
and documenting the result. 

Some of the decisions illustrated in this 
trade tree are supported by optimized meth- 
ods. For example, the vehicle may be initial- 
ly sized with optimization, and components 
may also be designed with optimized meth- 
ods. Nonetheless, when design decisions are 
to be made, there is a high likelihood that not 
all the decisions will have been supported 
through optimization. The point is, optimiz- 
ation methods are embedded in the total 
design process, and this must be taken into 
account in the development of these optimiz- 
ation methods. 

This last feature is what I am trying to 
illustrate in Figure 7. Some decisions of the 
design process will be made within the opti- 
mization process. Some will not. But those 
that do not must have information available 
from the optimization to assist the manual 
decision-making process. This is true wheth- 
er the outside decision is being made concur- 
rently with the optimization or whether it 
lags the optimization by days, weeks or 
months. 

















Optimizer 










Vs. 








// 


w 


'1 


















NAV 

SYS 

























Figure 7 Trade Studies with Optimization 

The implication is that information more 
comprehensive than just the final optimized 
configuration must be provided and stored. 
Possible information needs include sensitivi- 
ties around the optimal point and the 
optimization history. In addition, it will be 
necessary to provide a way to interrupt the 
optimization process as it is occurring to 
input new information to the optimization 



177 



READINGS IN SYSTEMS ENGINEERING 



process and to influence, on the fly, the out- 
come. 

Requirements Flowdown 

Let me provide one more example, that of 
requirements flowdown. This is another ex- 
ample of the communication involved in the 
design process. In this case, the objective is to 
communicate to each individual designer the 
importance of design in meeting the top level 
performance requirements. This is done by 
analyzing the top level system requirements 
and assigning or allocating these top level re- 
quirements to the next lower level to deter- 
mine the drivers in the system. This process 
is repeated to successively lower levels until 
the final objective is accomplished. That is, 
the question "What is each individual's con- 
tribution to the total system performance?" 
is answered at the lowest logical level. 

A specific performance might be mainten- 
ance manhours per flight hour, or it might be 



minimum range requirements. Whatever the 
requirement, this process allocates it to the 
lowest level of the configuration, maintains 
the traceability to the top level requirement 
and assures that the total system require- 
ment will be met. 

The question is, "What is a proper alloca- 
tion?" If a top level requirement is rippled to 
the lowest level, which functional area 
should contribute what proportion to the 
final performance? If we rely on a optimiz- 
ation process that merely gives a final an- 
swer, we are blind. This is another case of not 
all functions being included in the optimiz- 
ation process. For these "outside" functions, 
we have no sensitivity information upon 
which to base realistic allocations. The actu- 
al situation might be as illustrated here, 
where the cost of attaining a given level of 
performance varies greatly from one disci- 
pline to another. I have used cost as the mea- 
sure, but I could have used any measure of 
merit. For the illustration I have given, the 



System Level 

Performance 

Requirements 



Allocatable between 
Elements 



Unique to 
Element 



Allocatable 
between Subsys 



Unique to 
Subsystem 



Allocatable 
between Comp 



Unique to 
Component 



Figure 8 Requirements Flowdown 



178 



OPTIMIZATION IN THE SYSTEMS ENGINEERING PROCESS 



Allocation 
1 



Allocation 
2 



Allocation 
3 



Allocation 
4 





PERF 



PERF 



PERF 




PERF 



Figure 9 Optimize Allocations 



optimal allocation of the requirement is that 
which simultaneously attains the top level 
system performance and minimizes the cost. 
In the future, our optimization processes 
must provide visibility for such data. 

I have attempted to illustrate that opti- 
mization has a role in our design process, 
both today and in the future. The benefits are 
well known already, but I believe that we are 
only seeing the proverbial tip of the iceberg. 

Optimization must, however, continue to 
be sold and this selling is best done by consis- 
tent good performance. For this good perfor- 
mance to occur, the future approaches must 
be clearly thought out so that the optimiz- 
ation methods solve the problems that actu- 



ally occur during design. The visibility of the 
design process must be maintained as fur- 
ther developments are proposed. Careful at- 
tention must be given to the management of 
data in the optimization process, both for 
technical reasons and for administrative 
purposes. Finally, to satisfy program needs, 
provisions must be included to give data to 
support program decisions, and to communi- 
cate with design processes outside of the opti- 
mization process. 

If we fail to adequately consider all of 
these needs, the future acceptance of optimiz- 
ation will be impeded. We simply cannot 
allow that to happen. Optimization is too 
important. 



179 



SKYLAB 1 



N9 3-.2 4S92 
The Initial Flight Anomalies of Skylatb r 5/^-iH 

-17. 

suited from a failure of communications 



By the NASA Investigation Board 



At approximately 63 seconds into the flight 
of Skylab 1 on May 14, 1973, an anomaly oc- 
curred which resulted in the complete loss of 
the meteoroid shield around the orbital 
workshop. This was followed by the loss of 
one of the two solar array systems on the 
workshop and a failure of the interstage 
adapter to separate from the S-II stage of the 
Saturn V launch vehicle. The investigation 
reported herein identified the most probable 
cause of this flight anomaly to be the 
breakup and loss of the meteoroid shield due 
to aerodynamic loads that were not account- 
ed for in its design. The breakup of the mete- 
oroid shield, in turn, broke the tie downs 
that secured one of the solar array systems to 
the workshop. Complete loss of this solar ar- 
ray system occurred at 593 seconds when the 
exhaust plume of the S-II stage retro-rockets 
impacted the partially deployed solar array 
system. Falling debris from the meteoroid 
shield also damaged the S-II interstage 
adapter ordnance system in such a manner 
as to preclude separation. 

Of several possible failure modes of the 
meteoroid shield that were identified, the 
most probable in this particular flight was 
internal pressurization of its auxiliary tun- 
nel which acted to force the forward end of 
the meteoroid shield away from the shell of 
the workshop and into the supersonic air 
stream. The pressurization of the auxiliary 
tunnel was due to the existence of several 
openings in the aft region of the tunnel. An- 
other possible failure mode was the separa- 
tion of the leading edge of the meteoroid 
shield from the shell of the workshop (par- 
ticularly in the region of the folded ordnance 
panel) of sufficient extent to admit ram air 
pressures under the shield. 

The venting analysis for the auxiliary 
tunnel was predicated on a completely sealed 
aft end; the openings in the tunnel thus re- 



among aerodynamics, structural design, and 
manufacturing personnel. The failure to 
recognize the design deficiencies of the mete- 
oroid shield through six years of analysis, 
design and test was due, in part, to a pre- 
sumption that the shield would be "tight to 
the tank" and "structurally integral with the 
S-IVB tank" as set forth in the design crite- 
ria. In practice, the meteoroid shield was a 
large, flexible, limp system that proved diffi- 
cult to rig to the tank and to obtain the close 
fit that was presumed by the design. These 
design deficiencies of the meteoroid shield, 
as well as the failure to communicate within 
the project the critical nature of its proper 
venting, must therefore be attributed to an 
absence of sound engineering judgment and 
alert engineering leadership concerning this 
particular system over a considerable period 

of time. 

The overall management system used for 
Skylab was essentially the the same as that 
developed in the Apollo program. This sys- 
tem was fully operational for Skylab; no con- 
flicts or inconsistencies were found in the 
records of the management reviews. None- 
theless, the significance of the aerodynamic 
loads on the meteoroid shield during launch 
were not revealed by the extensive review 
process. Possibly contributing to this over- 
sight was the basic view of the meteoroid 
shield as a piece of structure, rather than as 
a complex system involving several different 
technical disciplines. Complex, multidisci- 
plinary systems such as the meteoroid shield 
should have a designated project engineer 
who is responsible for all aspects of analysis, 
design, fabrication, test and assembly. 

The Board found no evidence that the de- 
sign deficiencies of the meteoroid shield were 
the result of, or were masked by, the content 
and processes of the management systems 



PRE©£DING PAGE BLANK NOT FILMED 



181 



as 



,H(Bt 



JfftiftfSSftAirtt 8M»' : 



y 



READINGS IN SYSTEMS ENGINEERING 



that were used for Skylab. On the contrary, 
the rigor, detail, and thoroughness of the sys- 
tems are doubtless necessary for a program 
of this magnitude. At the same time, as a 
cautionary note for the future, it is empha- 
sized that management must always be alert 
to the potential hazards of its systems and 
take care that an attention to rigor, detail 
and thoroughness does not inject an undue 
emphasis on formalism, documentation, and 
visibility in detail. Such an emphasis can 
submerje the concerned individual and de- 
press the role of the intuitive engineer or 
analyst. It will always be of importance to 
achieve a cross-fertilization and broadened 
experience of engineers in analysis, design, 
test or operations. Positive steps must al- 
ways be taken to assure that engineers be- 
come familiar with actual hardware, develop 
an intuitive understanding of computer- 
developed results, and make productive use 
of flight data in this learning process. The 
experienced chief engineer, who can spend 
most of the time in a subtle integration of all 
elements of the system under purview, free 
of administrative and managerial duties, 
can also be a major asset to an engineering 
organization. 

the Skylab program 

Skylab missions have several distinct goals: 
to conduct Earth resources observations, 
advance scientific knowledge of the sun and 
stars, study the effects of weightlessness on 
living organisms, particularly human, and 
study and understand methods for the 
processing of materials in the absence of 
gravity. The Skylab mission utilizes the as- 
tronaut as an engineer and as a research 
scientist, and provides an opportunity for 
assessing potential human capabilities for 
future space missions. 

Skylab uses the knowledge, experience 
and technical systems developed during the 
Apollo program along with specialized equip- 
ment necessary to meet the program objec- 
tives. 



Figure 1 shows the Skylab in orbit. Its 
largest element is the orbital workshop, a 
cylindrical container 48 feet long and 22 feet 
in diameter weighing some 78,000 pounds. 
The basic structure of the orbital workshop 
is the upper stage, or S-IVB stage, of the S-IB 
and S-V rockets which served as the Apollo 
program launch vehicle. The orbital work- 
shop has no engines, except attitude control 
thrusters, and has been modified internally 
to provide a large orbiting space laboratory 
and living quarters for the crew. The Sky- 
lab 1 (SL-1) space vehicle included a payload 
consisting of four major units — orbital work- 
shop, airlock module, multiple docking 
adapter, Apollo telescope mount — and a 
two-stage Saturn-V (S-IC and S-II) launch 
vehicle as depicted in Figure 2. To provide 
meteoroid protection and thermal control, an 
external meteoroid shield was added to cover 
the orbital workshop habitable volume. A 
solar array system (SAS) was attached to the 
orbital workshop to provide electrical power. 
The original concept called for a "wet 
workshop." In this concept, a specially con- 
structed S-IVB stage was to be launched 
"wet" as a propulsive stage on the S-IB 
,. launch system filled with propellants. The 
empty hydrogen tank would then be purged 
and filled with a life-supporting atmosphere. 
A major redirection of Skylab was made on 
July 22, 1969, six days after the Apollo 11 
lunar landing. As a result of the successful 
lunar landing, S-V launch vehicles became 
available to the Skylab program. Conse- 
quently, it became feasible to completely 
equip the S-IVB on the ground for immediate 
occupancy and use by a crew after it was in 
orbit. Thus it would not carry fuel and 
earned the name of "dry workshop." 

The nominal Skylab mission called for 
the launch of the unmanned S-V vehicle and 
workshop payload SL-1 into a near -circular 
(235 nautical miles) orbit inclined 50 degrees 
to the equator. About 24 hours after the first 
launch, the manned Skylab 2 (SL-2) launch 
would take place using a command service 
module payload atop the S-IB vehicle. After 



182 



SKYLAB 1 



the command service module rendezvous and 
docking with the orbiting cluster, the crew 
enters and activates the workshop; Skylab is 
then ready for its first operational period of 
28 days. At the end of this period, the crew 
returns to Earth with the command service 
module, and the Skylab continues in an 
unmanned quiescent mode for some 60 days. 
The second three-person crew is launched 
with a second S-IB, this time for a second 
56-day period in orbit after which they will 
return to Earth. The total Skylab mission 
activities cover a period of roughly eight 
months, with about 140 days of manned 
operation. 



The Flight of Skylab l 

Skylab 1 was launched at 1730:00 (range 
time, R = 0) on May 14, 1973, from Complex 
39 A, Kennedy Space Center. At this time, 
the Cape Kennedy launch area was exper- 
iencing cloudy conditions with warm tem- 
peratures and gentle surface winds. Total 
sky cover consisted of scattered cumulus at 
2,400 feet, scattered stratocumulus at 5,000 
feet, broken altocumulus at 12,000 feet, and 
cirrus at 23,000 feet. During ascent, the 
vehicle passed through the cloud layers but 
no lightning was observed in the area. Upper 
area wind conditions were being compared to 



General Characteristics 
Condition work volume 12,700 cu ft (354 cubic meters) 
Overall length 117 ft (35.1 meters) 
Weight including CSM 199,750 (90,606 Kilograms) 
Width OWS including solar array 90 ft (27 meters) 



Apollo Telescope 
Mount 



Multiple 
Docking ■ 
Adapter 

Command & 

Service 

Module 




Solar Panels 



Experiments 

Micrometeoroid 
* Shield 



Airlock Module* 



Ward Room 
Waste Compartment 

Sleep Compartment 
Saturn Workshop 



Figure 1 Skylab Cluster 



183 



READINGS IN SYSTEMS ENGINEERING 







PS Payload Shroud 

Diameter 6.6 meters (21.7 feet) 

Length 16.8 meters 

Weight 11,794 kilograms (26,000 lbs.) 

ATM Apollo Telescope Mount 
Wi Width 3.3 meters 

Length 4.4 meters 

Weight 11.181 kilograms (24,650 lbs.) 

MDA Multiple Docking Adapter 
Diameter 3 meters (lo feet) 
Length 5.2 meters (17.3 feet) 
Weight 6,260 kilograms (13,800 lbs.) 

AM Airlock Module 

Diameter STS 3 meters (10 feet) 
Diameter FAS 6.6 meters (21.7feet) 
Length 5.3 meters (17.5 feet) 
Weight 22,226 kilograms (49,000 lbs.) 

IU Instrument Unit 

Diameter 6.6 meters (21.7 feet) 

Length 0.9 meter (3 feet) 

Weight 2,064 kilograms (4,550 lbs.) 

OWS Orbital Workshop 

Diameter 6.6 meters (21.7 feet) 
Length 14.6 meters (48.5 feet) 
Weight 35,380 kilograms (78,000 lbs.) 



S-II 



S-IC 



Second Stage 

Diameter 10 meters (33 feet) 

Length 24.8 meters (81.5 feet) 

Weight 488,074 kilograms (1,076,000 lbs.) 

fueled 

35,403 kilograms (78,050 lbs.) dry 

Engines J-2 (5) 

Propellants: Liquid Oxygen 333,837 liters 
(88,200 gallons) 
Liquid Hydrogen 1,030,655 
liters (272,300 gallons) 

Thrust 5,150,000 Newtons (1,150,000 lbs.) 

Interstage Approx. 5,171 kilograms (11,400) 

lbs.) 



First Stage 
Diameter 10 meters (33 feet) 
Length 42 meters (138 feet) 
Weight 2,245,320 kilograms (4,950,000 lbs.) 
fueled 

130,410 kilograms (287,500 lbs.) dry 
Engines F-l (5) 
Propellants: Liquid Oxygen 1 ,318,315 liters 

(348,300 gallons) 
RP-1 (Kerosene) 814,910 liters 
(215,300 gallons) 
Thrust 31,356,856 Newtons (7,723,726 lbs.) 



Figure 2 SL-1 vehicle 



184 



SKYLAB 1 



most other Saturn-V flights. The flight envi- 
ronment was quite favorable. 

The automatic countdown proceeded nor- 
mally with Guidance Reference Release oc- 
curring at R- 17.0 seconds and orbit insertion 
occurring at R + 599.0 seconds. The orbital 
workshop solar array deployment was com- 
manded on time; however, real-time data in- 
dicated that the system did not deploy fully. 

The solar array system (SAS) on the or- 
bital workshop consists of two large beams 
enclosing three major sections of solar cell 
assemblies within each. During ascent, the 
sections are folded like an accordion inside 
the beams which in turn are stowed against 
the workshop. The meteoroid shield is a 
lightweight structure wrapped around the 
converted S-IVB stage orbital workshop and 
is exposed to the flight environment. The two 
hinged solar array system wings are secured 
to the orbital workshop by tie downs above 
and below the meteoroid shield. Seals at- 
tached to the solar array system perimeter 
actually press against the shield to form an 
airtight cavity prior to launch. Once in orbit, 
the solar array system beams are first de- 
ployed out 90 degrees. The meteoroid shield 
is deployed later to a distance of about five 
inches from the orbital workshop wall. After 
the ordnance release is fired, meteoroid 
shield deployment is effected by torsion rods 
and swing links spaced around the structure 
fore and aft. The rods are torqued prior to 
launch and simply unwind in orbit to move 
the meteoroid shield away from the tank, 
Detection of pertinent conditions associated 
with the meteoroid shield and solar array 
system is afforded by measuring various pa- 
rameters by telemetered instrumentation. 

When the orbital workshop solar array 
system was commanded to deploy, telemeter- 
ed data indicated that events did not occur as 
planned. The flight data was analyzed by 
flight operations personnel to reveal the pos- 
sible source of the problem. At about R + 60 
seconds, the S-II telemetry reflected power 
increased slightly. At about 63 seconds, 
numerous measurements indicated the 



apparent early deployment and loss of the 
meteoroid shield. At this time, the vehicle 
was at about 28,600 feet altjtude and at a 
velocity of about Mach 1. 

At this time, vehicle dynamic measure- 
ments such as vibration, acceleration, atti- 
tude error, and acoustics indicated strong 
disturbances. Measurements which are nor- 
mally relatively static at this time, such as 
torsion rod strain gauges, tension strap 
breakwires, temperatures, and solar array 
system position indicators, indicated a loss of 
the meteoroid shield and unlatch of the 
SAS-2 wing. Further preliminary evaluation 
revealed abnormal vehicle accelerations, vi- 
brations, and solar array system tempera- 
ture and voltage anomalies at about R + 593 
seconds. Temperature data loss and sudden 
voltage drops indicated that the SAS-2 wing 
was separated from the orbital workshop at 
this time. Other data later in the flight indi- 
cated the SAS-1 wing did not fully deploy 
when commanded to do so. Although not ap- 
parently associated with the 63-second and 
593-second anomalies, the S-II stage range 
safety receiver signal strengths showed sev- 
eral drops throughout the flight beginning at 
about R + 260 seconds. 

63-second anomaly: loss of 
Meteroid Shield 

The Investigation Board evaluated the te- 
lemetry data in order to explain the various 
anomalies that occurred on Skylab 1. The 
first anomalous indication was an increase 
in S-II telemetry reflected power from a 
steady 1.5 W beginning at R + 59.80 seconds. 
At this time the telemetry forward power 
remained steady at 58.13 W. By 61.04 sec- 
onds, the reflected power had reached 
1.75 W, and by 80.38 seconds, the reflected 
power had stabilized at about 2.0 W. This 
abnormal increase in power might be in- 
dicative of a vehicle physical configuration 
change which altered the antenna ground 
plane characteristic. 



185 



READINGS IN SYSTEMS ENGINEERING 



Shortly after the telemetry reflected 
power increase, the meteoroid shield torsion 
rod 7 forward (measurement G7036) indicat- 
ed a slight change toward the deployed 
condition. This occurred at R + 60.12 sec- 
onds, and at 61.78 seconds the vehicle roll 
rate decreased slightly from a normal value 
of 1.1 degrees per second clockwise looking 
forward. The next torsion rod 7 forward 
sample at about 62.52 seconds revealed a 
further relaxation. The increase in telemetry 
reflected power and the movement of torsion 
rod 7 forward tend to indicate meteoroid 
shield lifting between positions I and II. 

Between R + 62.75 and 63.31 seconds, 
several vehicle dynamic measurements 
indicated a significant disturbance. A sensor 
on the orbital workshop film vault showed an 
abnormal vibration at 62.75 seconds fol- 
lowed by disturbances sensed by X and Y 
accelerometer pickups in the instrument 
unit, the pitch, yaw, and longitudinal 
accelerometers, and the pitch, yaw, and roll 
rate gyros. At 62.78 seconds, the roll rate 
gyro sensed a sudden clockwise roll rate re- 
sulting in a peak amplitude of 3.0 degrees 
per second clockwise 62.94 seconds. A sensor 
at the instrument unit upper mounting 
showed a maximum peak-to-peak shock of 
17.2 g"s at 63.17 seconds. In addition, the S-II 
engine actuators experienced pressure fluc- 
tuations caused by vehicle movement 
against the inertia of the non-thrusting 
engine nozzles. 

The data indicate that the most probable 
sequence of meteoroid shield failure was 
initial structural failure of the meteoroid 
shield between the SAS-2 wing and the main 
tunnel (between positions I and II). The 
initial failure propagation from this area 
appears likely since the wardroom window 
thermocouple indication (C7013) remained 
normal at 62.94 seconds after SAS-2 indicat- 
ed unlatched at 62.90 seconds and after the 
K7010 and K7011 tension strap measure- 
ments failed. 



593-SECOND ANOMALY 

As a consequence of the meteoroid shield 
failure at approximately 63 seconds, the 
SAS-2 wing was unlatched and partially de- 
ployed as evidenced by minor variations in 
the main solar array system electrical volt- 
ages and SAS-2 temperatures. Full deploy- 
ment was prevented due to the aerodynamic 
forces and accelerations during the remain- 
der of powered flight. 

At the completion of the S-II phase of 
flight, the four 35,000-pound thrust retro- 
rockets fired for approximately two seconds 
commencing at R + 591.10 seconds followed 
by spacecraft separation at 591.2 seconds. 
The effect of retro-rocket plume impinge- 
ment was observed almost immediately on 
the SAS-2 temperature and on vehicle body 
rates. 

At 593.4 seconds the wing imparted mo- 
mentum to the vehicle, probably by hitting 
and breaking the 90 degree fully deployed 
stops, and at 593.9 imparted a final kick as it 
tore completely free at the hinge link. In- 
orbit photographs show clearly the hinge 
separation plane and the various wires 
which were torn loose at the interface. 

interstage second plane 
Separation anomaly 

Post-flight analysis revealed unexpectedly 
high temperatures and pressures in the S-II 
engine compartment following ignition and 
continued high after interstage separation 
command. The unusually high temperatures 
from S-II ignition and until the S-II inter- 
stage separation signal are considered by 
Marshall Space Flight Center (MSFC) to be 
caused by a change in the engine heat shield 
skirts introduced on this flight, and there- 
fore do not indicate a problem. However, the 
increasing temperatures after the time of 
normal S-II interstage separation are indica- 
tive of an abnormal condition. More detailed 



186 



SKYLAB 1 



investigation based on performance evalua- 
tion and axial acceleration time history re- 
vealed that the interstage had not been 
jettisoned; however, due to the vehicle per- 
formance characteristics and performance 
margin, the desired orbit was achieved. 

Data analysis confirms that the primary 
ordnance command was properly issued at 
R + 189.9 seconds. The backup command was 
issued 100 milliseconds later but the explod- 
ing bridge wire circuit discharge was charac- 
teristic of an open circuit consistent with 
separation of the interstage disconnect by a 
minimum of 0.25 inch. 

The linear shaped charge is mounted cir- 
cumferentially around the S-II interstage. 
When fired by the primary command, the 
charge cuts the tension straps (in the direc- 
tion of position II to position I) allowing the 
skirt to drop away. Normal propagation time 
of the linear shaped charge is approximately 
four milliseconds. Assuming a failure to 
propagate completely around the structure, 
analyses were made by appropriate contrac- 
tor and government personnel to determine 
what area must remain intact in order to re- 
tain the skirt and what area must have been 
cut to allow rotation of the skirt sufficient to 
disconnect the connector panel. The various 
analyses isolate the region of failure to an 
arc extending from approximately © = 100 
degrees to as much as © = 200 degrees. 

This ordnance installation was different 
from prior Saturn flights. Previously, a sin- 
gle fire command from the instrumentation 
unit was issued which simultaneously deto- 
nated the linear shaped charge from both 
ends allowing the charge to propagate from 
both directions. On this flight, in an attempt 
to provide redundant firing commands, the 
detonators at each end of the linear shaped 
charge were separately connected to two 
command channels spaced 100 milliseconds 
apart due to the characteristics of the air- 
borne equipment. As a result of the partial 
cutting of the interstage, it rotated suffi- 
ciently to separate the electrical connector 
prior to issuing the backup command. 



A review of the history of manufacturing, 
acceptance, checkout, qualification and 
flight environment revealed no basic cause 
for failure. The most probable cause is secon- 
dary damage as a result of the meteoroid 
shield failure, attributed to falling debris as 
evidenced by the various shock and acoustic 
disturbances occurring in the 63-second time 
period. 

The redundant mode of ordnance opera- 
tion of all prior Saturn flights in which both 
ends of the linear shaped charge are fired at 
once from a single command would probably 
have prevented the failure, depending on the 
extent of damage experienced by the linear 
shaped charge. 

Forward Interstage Internal 
Pressure Anomaly 

Flight data indicated a deviation of the S-II 
forward interstage pressure from analytical 
values commencing at approximately 63 sec- 
onds. Inasmuch as the deviation from the 
analytical curve of the internal pressure ver- 
sus time appeared to be coincident with the 
meteoroid shield failure, it was postulated 
that a portion of the shield had punctured 
the forward interstage. On this basis, it was 
possible to correlate the flight data with ei- 
ther an assumed 2.0 square foot hole in the 
conical section or an assumed 0.75 square 
foot hole in the cylindrical section. 

Range Safety Receiver anomaly 

During the S-II portion of the flight, the sig- 
nal strength indications from both range 
safety receivers showed drops in level. From 
liftoff through R + 259 seconds, both receiv- 
ers maintained relatively stable values 
above range requirements. At R + 259.57 
seconds, receiver 2 signal strength began to 
drop and between this time and 522.1 sec- 
onds, both receivers indicated various de- 
grees of signal strength shift. These signal 
strength shifts dropped below the 12 db safe- 
ty margins required by Air Force Eastern 



187 



READINGS IN SYSTEMS ENGINEERING 



Test Range Manual 127-1. At R + 327.81 sec- 
onds the receiver 2 signal strength dropped 
briefly below its threshold sensitivity. At 
this instant this receiver probably would not 
have responded to any range safety com- 
mands. Receiver 1 was, however, capable of 
receiving commands. At R + 521.16, receiv- 
er 2 strength again dropped briefly to its 
threshold sensitivity. None of these drops 
could be correlated to ground system perfor- 
mance. 

Analysis indicates that the most probable 
cause of the S-II receiver signal strength 
dropout was a variable phase shift within 
the vehicle's hybrid coupler due to the chang- 
ing aspect angle produced by the moving 
vehicle and the fixed transmitting site. Be- 
cause the decrease in receiver signal 
strength occurred with only one receiver at a 
time, range safety commands could have 
been received continuously throughout pow- 
er flight. During two of these drops, however, 
the planned redundancy of range safety re- 
ceivers was not available. 

During this investigation, it was revealed 
that the Wallops Island and Bermuda 
ground stations did not continuously record 
ground transmitter power levels. The Board 
considers that such continuous recordings 
would be of value. 

The Meteoroid Shield Design 

Although fairly simple in concept, the mete- 
oroid shield had to provide such a variety of 
functions that it was, in fact, a quite compli- 
cated device. It was, foremost, a very lightly 
built cylindrical structure 270 inches in di- 
ameter (in the deployed condition) by 265 
inches long. 

In brief, the meteoroid shield is formed of 
a set of sixteen curved sheets of 2014 T6 alu- 
minum panels, 0.025 inches thick, assem- 
bled at flanges and other fittings to form the 
cylinder shown. The forward and aft ends 
were reinforced with curved 7075 T6 angles. 

Various special details were included in 
the assembly in order to hold it in place, 



deploy it in orbit, and provide access to the 
orbital workshop interior during prelaunch 
activities. The principal means of holding 
the shield in place in orbit (and to a lesser 
extent during powered flight) was a set of 
tension straps under the main tunnel. These 
straps were bonded to the orbital workshop 
wall and fitted with a hinge on each end to 
take the butterfly hinge that attaches to the 
adjacent meteoroid shield panel. These 
butterfly hinges were designed to rotate so 
as to lie against the sides of the main tunnel 
which enclosed the tension straps and var- 
ious cable runs on the orbital workshop. 

Clockwise from the tension straps and 
butterfly hinge, the next special feature is 
the auxiliary tunnel. This tunnel extends in 
an arch between panels of the thin meteoroid 
shield. The 28 titanium frames of this tunnel 
provide a very springy section in the rela- 
tively rigid hoop provided by the rest of the 
shield. The auxiliary tunnel also encloses a 
smaller tunnel covering the wiring for the 
thruster attitude control system. Farther 
around, in position I, there are two curved 
rectangular smaller panels, included to pro- 
vide access to the orbital workshop. 

Between positions I and IV, the two 
halves of the meteoroid shield overlap and 
are joined by a series of 14 trunnion bolts and 
straps. These trunnion bolts were used to ad- 
just the tension with which the shield was 
held against the orbital workshop. Adjusting 
the bolts in the trunnion assemblies was a 
major aspect in positioning and tightening 
the meteoroid shield against the orbital 
workshop (rigging). 

In order to provide the extra 30 inches of 
perimeter required when the meteoroid 
shield was deployed, a foldout panel assem- 
bly is included in the panel adjacent to the 
trunnions. The only remaining distinctive 
features of the meteoroid shield are the 
panels located over the scientific airlock and 
wardroom window at position III. The mete- 
oroid shield is completed at the butterfly 
hinges and tension straps at position I. 



188 



SKYLAB 1 



Deployment Provisions 

The deployment of the 265-inch-long meteor - 
oid shield was accomplished by providing 
two folding panel sections on each side of a 
contained explosive pyrotechnic chain which 
extended axially for the full length of the 
shield except for short end reinforcements. 
When the ordnance strip is fired and sepa- 
rates the fold-over panel, the segments are 
released and the shield is deployed. After re- 
lease of this folded panel, a number of swing 
arms are used to displace the shield away 
from the orbital workshop wall and hold it 
there. A rotational force is applied to these 
swing arms by a total of sixteen torsion rods 
suitably spaced around the ends of the mete- 
oroid shield. When the meteoroid shield is 
stowed for launch, there is a larger twist in 
the torsion rods than after deployment. The 
links on one side of the ordnance chain swing 
in a direction opposite to those on the other 
side. The butterfly hinges on each side of the 
main tunnel permit the radial displacement 
of the shield at the location of the tension 
straps. 

The meteoroid shield should therefore be 
regarded as a very limp system, which de- 
pends on being stretched tight around the 
orbital workshop to withstand the aerody- 
namic, vibratory, flutter and thrust loads at 
launch. After deployment, it needs very little 
strength to serve its primary objective as a 
meteoroid shield. 

The Auxiliary Tunnel 

The auxiliary tunnel extends from the for- 
ward skirt, down the full length of the mete- 
oroid shield shield, and below the meteoroid 
shield by about 57 inches. Venting of this 
tunnel was provided through an outlet of 10 
square inches under the corrugations of the 
tunnel cover at the aft end of the forward 
fairing. The tunnel was intended to be sealed 
at the aft end by a rubber boot assembly in 
both the stowed and deployed position. Note 
that the tunnel is displaced some 5 or 6 



inches circumferentially upon deployment of 
the shield. 

The main structural members of the aux- 
iliary tunnel are titanium, arch-shaped, 
frame springs. These frames provide the 
structural tie between two meteoroid shield 
panels and provide both regulation of the 
pre-loading of the meteoroid shield to the 
orbital workshop and act as a flexible relief 
for diametrical changes resulting from ther- 
mal and pressure changes of the orbital 
workshop. 

The tunnel also serves to protect the 
thrust attitude control system cables located 
in a small channel-shaped cover permanent- 
ly attached to the orbital workshop. A seg- 
mented and corrugated outer skin form an 
aerodynamic fairing for the complete system 
and seals between forward and aft fairings. 

Thermal Control 

Although the primary purpose of the meteor- 
oid shield is that of providing protection of 
the orbital workshop from meteoroids, it also 
plays a significant role in the thermal con- 
trol system. Much of the overall thermal de- 
sign was accomplished passively by painting 
the outer surfaces of the meteoroid shield 
black except for a large white cross-shaped 
pattern on the Earth side during flight. The 
entire surface of the orbital workshop wall 
was covered with gold foil. The overall choice 
of finishes biased the thermal design toward 
the cold side, it being easier to vernier con- 
trol by heating rather than cooling. 

Friction between the Meteoroid Shield 
and Orbital Workshop Wall 

To provide a uniform tension throughout the 
meteoroid shield upon assembly and rigging 
for flight, and to permit transfer of the trun- 
nion bolt tension into the frames of the auxil- 
iary tunnel, it was necessary to minimize 
friction between the shield and the external 
surface of the orbital workshop. This was 
accomplished by applying a Teflon coating to 



189 



READINGS IN SYSTEMS ENGINEERING 



the entire inner surface of the meteoroid 
shield assembly. Special care was also taken 
to assure that all fastening rivets be either 
flush with or below the Teflon surface of the 
shield. In addition to considerations of 
friction, the elimination of rivet head 
protrusions was important in not damaging 
the rather delicate gold surface used to pro- 
vide the proper emissivity of the outer orbit- 
al workshop wall surfaces as mentioned 
above. This was a vapor -deposited gold sur- 
face applied to a Kapton backing and bonded 
to the outer workshop wall with an adhesive. 

Panel Details 

The sixteen panels comprising the meteoroid 
shield were formed of 0.025 inch thick alumi- 



num stock fitted with doublers and angles to 
permit their assembly. In each of these panel 
joints, 96 holes of 1/8-inch diameter were 
drilled to vent any air trapped under the me- 
teoroid shield skin. The special panel joint is 
required next to the SAS-1 wing because of 
the unavailability of sufficiently wide panel 
stock for the panel under SAS-1. It was a 
strap of metal of this special joint that be- 
came embedded in the SAS-1 cover and pre- 
vented automatic deployment of SAS-1 in or- 
bit. It is, perhaps, of passing interest to note 
the longer length of exposed bolts in this par- 
ticular joint. 

Around the top of the panels is located an 
angle and a neoprene rubber rain or weather 
seal. This seal was not intended to be an 
aerodynamic seal and could not be expected 




Forward 
Fairing 



High Pressure Leaks 



Auxiliary 
Tunnel 



Shocks from 

Forward 

Fairing 




Meteoroid 
Shield 



Figure 3 Compressibility waves from the forward auxiliary tunnel fairing 



190 



SKYLAB 1 



to accommodate significant relative deflec- 
tions between the orbital workshop and me- 
teoroid shield surfaces. To provide meteoroid 
protection at the two ends of the meteoroid 
shield, small strips of thin stainless steel 
"fingers" were squeezed down between the 
orbital workshop and the meteoroid shield 
when stowed. The thrust load of the shield, 
which weighs some 1200 pounds, is trans- 
ferred to the forward flange of the aft skirt 
through a group of twelve thrust blocks. 

SUMMARY AND RECOMMENDATIONS 

The preceding analysis and discussion of pos- 
sible failure modes of the meteoroid shield 
have identified at least two ways that it 
could fail in flight. Although the most prob- 
able cause of the present failure was the lift- 
ing of the shield from the orbital workshop 
tank by excessive pressures in the auxiliary 
tunnel, other failure modes could have oc- 
curred in other regions of flight or under 
more severe flight environments that were 
encountered by Skylab 1. 

Among these other modes of potential 
failure, which could combine in various ways 
under varying conditions of flight, are exces- 
sive pressures under the forward edge of the 
shield, or inadequate venting of the folded 
ordnance panel. The inherently light spring 
force of the auxiliary tunnel frames, the 
crushing loads on these frames in flight, the 
inherent longitudinal flexibility of the shield 
assembly, the forces applied by the swing 
links to deploy the shield, the possible 
breathing of the shield panels as cavities are 
vented, the noncylindrical nature of the un- 
derlying pressurized tank, and the uncertain 
tension loads applied to the shield in rigging 
for flight all contribute to a lack of rigidity of 
the shield and a weakness of its structural 
integrity with the underlying tank struc- 
ture. 

A simple and straightforward solution to 
these inherent problems of the present shield 
design is therefore not likely. A fundamen- 
tally different design concept seems in order. 



One solution is, of course, to simply omit the 
meteoroid shield, suitably coat the orbital 
workshop for thermal control and accept the 
meteoroid protection afforded by the orbital 
workshop tank walls. Although the Board 
has not conducted an analysis, meteoroid 
flux levels are now known to be considerably 
lower than those used in the original calcula- 
tions. A new analysis, based on these flux 
levels, may show acceptable protection. 

Should some additional meteoroid protec- 
tion be required, the Board is attracted to the 
concept of a fixed, nondeployable shield. 
Although the inherent weight advantages of 
a separable bumper are not available in this 
approach, the mission of Skylab could prob- 
ably be satisfied in this manner. One concept 
would be to bond an additional layer of metal 
skin to the surface of the tank with a layer of 
nonventing foam between the orbital work- 
shop tank and the external skin. The prob- 
lem being statistical in nature, the entire 
shell of the orbital workshop would not have 
to be covered. 

Postulated Sequence of the Most 
Probable Failure Mode 

The availability of flight data from the in- 
strumentation on the meteoroid shield and 
the vehicle disturbances, the design features 
of the meteoroid shield, the solar array sys- 
tem photographs taken in orbit, descriptions 
by the astronauts, and other information 
permit the following postulation of the prob- 
able sequence of events associated with the 
meteoroid shield failure. 

In Figure 4, sketches and details of sa- 
lient events are correlated to the roll rate 
data around the 63 second anomaly period. 
The events are designated on the figures by 
times which are consistent with the avail- 
able data. 

60.12 Seconds - Meteoroid shield liftoff 
and local inflation in the vicinity of the aux- 
iliary tunnel was indicated by a small shift 



191 



READINGS IN SYSTEMS ENGINEERING 



in position of the torsion rod on the forward 
edge just to the left of the tunnel. 

61.78 Seconds - Air entered the forward 
fairing opening, raised the pressure under 
the shield and high mass flows escaped 
through the adjacent holes in the butterfly 
hinge. This flow produced reactive force 
causing a gradual decrease in roll rate be- 
tween 61.78 seconds and 62.74 seconds. 

62.74 to 62.79 Seconds - Burst pressure 
under the auxiliary tunnel and adjacent me- 
teoroid shield caused a large tangential load 
on the forward section of the butterfly hinge, 
causing the whole hinge to unzip. Fly around 
inspection indicated that the failure of the 
butterfly hinge occurred at the hinge line ad- 
jacent to the main tunnel. 

The butterfly hinge was now completely 
broken. Aerodynamic drag on the meteoroid 
shield including the bulky auxiliary tunnel 
produced tension in the shield and pulled on 
the vehicle so as to roll it in the direction 
shown, that is, opposite to that noted earlier. 
The large area and mass of this metal flag 
induced a more rapid change in roll rate than 
the earlier jetting through the butterfly 
hinge. This process terminated as the mete- 
oroid shield started to wrap around and lift 
the SAS-2 wing. 

62.79 to 62.90 Seconds - During this in- 
terval the shield was wrapping around the 
SAS-2 wing producing a negative roll torque 
in the vehicle. At about 62.85 seconds the 
SAS-2 tie-downs were broken. 

62.90 Seconds - Upon release of the 
SAS-2, the tension in the shield was trans- 
ferred to the trunnions, causing failure of the 
trunnion straps. Upon separation of this sec- 
tion of the shield, the negative roll torque 
ended. 

62.90 to 62.95 Seconds - In this interval, 
the remaining section of the meteoroid shield 
began unwinding, introducing a large posi- 
tive roll torque. 

63. 1 7 Seconds - A large shock was detect- 
ed by the instrument unit upper mounting 
ring vibration sensor due to the impact of the 
separated section of the meteoroid shield 



upon the conical adapter between the orbital 
workshop and the SAS-1 stage. 

63. 7 Seconds - The meteoroid shield con- 
tinued to unwind and whip until 63.7 sec- 
onds when it reached SAS-1 wing. As the me- 
teoroid shield began to wrap around the 
SAS-1 wing, a negative roll torque resulted. 
The meteoroid shield then ripped apart from 
top to bottom at the longitudinal joint adja- 
cent to SAS-1, pulling a portion of the joint 
assembly over the SAS-1 wing as the meteor- 
oid shield section departed. From this point 
on the vehicle showed normal response to its 
roll control system. 

Possible Impact of Costs and 
Schedules on the Meteoroid Shield 

The origin of Skylab in late 1966 — as an ex- 
tension of the use of Apollo hardware for ex- 
periments in Earth orbit — imposed an initial 
environment of limited funding and strong 
schedule pressures on the program. Skylab, 
then designated the Apollo Applications Pro- 
gram (AAP), was to fit in among the Apollo 
flights under schedules imposed by the main- 
line Apollo program. Funding was provided 
out of the Apollo program and thus the needs 
of Skylab competed with those of the higher 
priority Apollo program. 

The situation changed in mid-1969 when 
Skylab became a major line item in its own 
right and was to use a Saturn-V launch vehi- 
cle with a dedicated, dry, orbital workshop. 
From that point on, increased funding and 
new flight schedules were established for 
Skylab. Nonetheless, the original concept of 
the meteoroid shield was retained when the 
orbital workshop changed from Saturn-IB 
propulsion stage to a dry workshop launched 
by a Saturn-V. The Board was therefore 
interested in determining the extent, if any, 
that either the initial limitation of funds and 
time, or any subsequent limitations, deter- 
mined the design or thoroughness of develop- 
ment of the meteoroid shield. This inquiry 
was limited to the possible effect of funding 
and schedule of the meteoroid shield as 



192 



SKYLAB 1 



designed and flown on Skylab 1 and did not 
consider whether meteoroid protection could 
have or should have been provided in some 
other way had the program not evolved as it 

did. 

In the Board's review of the evolution of 
the meteoroid shield from initial design con- 
cept, through testing and development, to fi- 



nal assembly for flight, particular attention 
was devoted to any impacts arising from 
limitation of funds or time. Extensive discus- 
sions were also held with management per- 
sonnel of MDAC-W, MSFC, JSC, and NASA 
Headquarters on this matter. In no instance 
could the Board find any evidence that the 
design or testing of the meteoroid shield was 



posm 



SAS-l 



SAS-2 




PITCH 
AXIS 



SAS-2 



j Situation at 62.79 




POSH 



SAS-2 




SAS-2 



SAS-2 - 



Situation at 62.85 




Situation at 62.90 




SAS-2 



r^F^ 



I Situation at 63.4 





SAS-l 



Situation at 63.70 



Figure 4 — Postulated Sequence Failure Mode 



193 



READINGS IN SYSTEMS ENGINEERING 



compromised by lack of funds or time. Pro- 
gram personnel, both government and 
contractor, had full confidence in the basic 
concept of the meteoroid shield and thus saw 
no need to alter the design when the change 
to a dry, Saturn-V launched orbital work- 
shop occurred. Given the concept that the 
shield was to be maintained tight to the or- 
bital workshop tank, and thus structurally 
integrated with the well-established S-IVB 
structure, the emphasis of testing given to 
ordnance reliability and shield deployment 
was considered proper. Neither the records of 
Skylab nor the memories of key personnel 
revealed any tests or analyses of the meteor- 
oid shield that were considered desirable at 
the time and which were precluded by lack of 
funds or time. 

The Skylab Management System 

The management system utilized for the 
Skylab program was derived directly from 
that which had been developed and used in 
the Apollo program. As such, it included a 
series of formal reviews and certifications at 
progressive points in the program life cycle 
that are intended to provide visibility to con- 
tractor and NASA management on program 
status, problems and their resolution. The 
selected review points and their primary 
purpose are set forth in Skylab Program 
Directive No. 11 A, which is summarized as 
follows: 

Preliminary Requirements Review (PRR). 
"To verify by formal review the suitability of 
the conceptual configuration and to establish 
the requirements and action necessary to 
achieve a design baseline." 

Preliminary Design Review (PDR). "To 
verify by formal review the suitability of the 
baseline design of the Contract End Item." 

Critical Design Review (CDR). "To verify 
by formal review the suitability of the design 
of a Contract End Item when the design is es- 
sentially complete." 

Configuration Inspection (CI). "To certify 
that the configuration for the Contract End 



Item as being offered for delivery is in confor- 
mance with the baseline established at the 
CDR." 

Certification of Flight Worthiness 
(COFW). "To certify that each flight stage 
module and experiment is a complete and 
qualified item of hardware prior to ship- 
ment." 

Design Certification Review (DCR). "To 
examine the design of the total mission com- 
plex for proof of design and development ma- 
turity." 

Flight Readiness Review (FRR). "A con- 
solidated review of the hardware, operation- 
al and support elements to assess their 
readiness to begin the mission." 

The primary thrust of these key program 
milestones is thus a formal review and certi- 
fication of equipment design or program sta- 
tus; the primary purpose being served is to 
provide visibility into these matters to senior 
NASA and contractor program manage- 
ment. As noted in the Skylab Program Direc- 
tive, the organization and conduct of the 
review is a major responsibility of a senior 
program or management official. For each 
review, specific objectives are to be satisfied, 
in conformance with preestablished criteria 
and supported by specified documentation. 
The reviews are thus highly structured and 
formal in nature, with a major emphasis on 
design details, status of various items and 
thoroughness of documentation. Several 
hundred specialists, subsystem engineers 
and schedule managers are generally in at- 
tendance. 

The material presented in these reviews 
is, of course, developed over a period of time 
in many lower-level reviews and in monthly 
progress reports dealing with various sys- 
tems and subsystems. In addition, several 
other major reviews peculiar to Skylab were 
conducted, including the following: 

• Cluster System Review of December 1967 

• Mathew's Subsystem Review Team of 
August 1970 July 1971 



194 



SKYLAB 1 



• Critical Mechanisms Review of March 
1971 

• Systems Operations Compatibility 
Assessment Review of October 1971-June 

1972 

• Structural/Mechanical Subsystem 
Reviews of July 1971-May 1972 

• Hardware Integrity Review of March 
1973 

• MSFC Center Director's Program 
Reviews 

There was thus no shortage of reviews. In 
order to determine the consideration given to 
the meteoroid shield throughout the pro- 
gram, the Board examined the minutes, pre- 
sentation material, action items, and 
closeout of data of each of these reviews and 
progress reports. In every case, complete 
records and documentation were available 
for inspection. In no case did the Board un- 
cover any conflict or inconsistency in the 
record. All reviews appeared to be in com- 
plete conformance to Program Directive 11 A 
and were attended by personnel appropriate 
to the subject matter under consideration. 
The system was fully operational. 

And yet, a major omission occurred 
throughout this process— consideration of 
aerodynamic loads on the meteoroid shield 
during the launch phase of the mission. 
Throughout this six year period of progres- 
sive reviews and certifications the principal 
attention devoted to the meteoroid shield 
was that of achieving a satisfactory deploy- 
ment in orbit and containment of the ord- 
nance used to initiate the deployment. As 
noted in the preceding section on possible 
failure modes, design attention was also giv- 
en to the strength of the hinges, trunnion 
straps and bolts, to the crushing pressures on 
the frames of the auxiliary tunnel, to flutter 
and to the venting of both the auxiliary 
tunnel and the several panels of the shield. 
But never did the matter of aerodynamic 
loads on the shield or aeroelastic interactions 
between the shield and its external pressure 
environment during launch receive the at- 



tention and understanding during the design 
and review process which in retrospect it de- 
served. 

This omission, serious as it was, is not 
surprising. From the beginning, a basic de- 
sign concept and requirement was that the 
shield be tight to the tank. As clearly stated 
in much of the early documentation, the me- 
teoroid shield was to be structurally integral 
with the S-IVB tank— a piece of structure 
that was well proven in many previous 
flights. The auxiliary tunnel frames, the con- 
trolled torque on the trunnion bolts and the 
rigging procedure itself were all specifically 
intended to keep the shield tight against the 
tank. The question of whether the shield 
would stay there under the dynamics of 
flight through the atmosphere was simply 
not considered in any coordinated manner— 
at least insofar as the Board could determine 
by this concentrated investigation. 

Possibly contributing to this oversight 
was the basic view of the meteoroid shield as 
a piece of structure. Organizationally, re- 
sponsibility for the meteoroid shield at 
MDAC-W was established to develop it as 
one of the several structural subsystems, 
along with such items as spacecraft struc- 
ture and penetrations, pressure vessels, sci- 
entific airlocks, protective covers and fin- 
ishes. Neither the government, (MSFC), or 
the contractor, (MDAC-W), had a full-time 
subsystem engineer assigned to the meteor- 
oid shield. While it is recognized that one 
cannot have a full-time engineer on every 
piece of equipment, it is nonetheless possible 
that the complex interactions and integra- 
tion of aerodynamics, structure, rigging 
procedures, ordnance, deployment mecha- 
nisms, and thermal requirements of the me- 
teoroid shield would have been enhanced by 
such an arrangement. Clearly, a serious fail- 
ure of communications among aerodynamics, 
structures, manufacturing and assembly 
personnel, and a breakdown of a systems 
engineering approach to the shield, existed 
over a considerable period of time. Further, 
the extensive management review and 



195 



READINGS IN SYSTEMS ENGINEERING 



certification process itself, in its primary 
purpose of providing visibility of program 
status to management, did not identify these 
faults. 

Further insight into this treatment of the 
meteoroid shield as one of several structural 
subsystems is obtained by a comparison of a 
listing of the design reviews conducted on 
both the meteoroid shield and the solar array 
system. At MDAC-W, the solar array system 
was considered a major subsystem and was 
placed under the direction of a full-time pro- 
ject engineer. 

The Board is impressed with the thor- 
oughness, rigor and formalism of the man- 
agement review system developed by Apollo 
and used by Skylab. Great discipline is im- 
posed upon everyone by this system and it 
has served very well. In a large program as 
geographically dispersed and intrinsically 
complex as Skylab, such visibility of pro- 
gram status and problems is a management 
necessity. We therefore have no wish to alter 
this management system in any basic man- 
ner. But all systems created by humans have 
their potential flaws and inherent hazards. 
Such inherent flaws and weaknesses must be 
understood by those who operate the system 
if it is not to become their master. We there- 
fore wish to identify some of those potential 
flaws as they have occurred to us in this in- 
vestigation, not to find fault or to identify a 
specific cause of this particular flight failure 
but to use this experience to further 
strengthen the management processes of 
large and complex endeavors. 

As previously noted, the management 
system developed by NASA for manned 
space flight places large emphasis on rigor, 
detail and thoroughness. In hand with this 
emphasis comes formalism, extensive docu- 
mentation, and visibility in detail to senior 
management. While nearly perfect, such a 
system can submerge the concerned individ- 
ual and depress the role of the intuitive engi- 
neer or analyst. It may not allow full play for 
the intuitive judgment or past experience of 
the individual. An emphasis on a manage- 



ment system, can, in itself, serve to separate 
the people engaged in the program from the 
real world of hardware. To counteract these 
potential hazards and flaws, we offer the fol- 
lowing suggestions. 

• Deployable systems or structures that 
have to move, or that involve other 
mechanisms, devices, or components in 
their operation, should not be considered 
as a piece of structure or be the basic re- 
sponsibility of a structures organization. 

• A complex, multi-disciplinary system 
such as the meteoroid shield should possi- 
bly have a designated project engineer 
who is responsible for overseeing all as- 
pects of analysis, design, fabrication, test 
and assembly. 

• Management must always strive to coun- 
teract the natural tendency of engineers 
to believe that a drawing is the real 
world. First-hand experience with how 
hardware behaves and can fail is of the 
essence to design engineers. Possibly, 
some design engineers should be required 
to spend time in testing, operations, or 
failure analysis. Such experience may not 
contribute to cleverness or sophistication 
of analysis, but something equally 
valuable — actual experience — may be ad- 
ded to the design group. An unfamiliarity 
with hardware, first hand, makes it diffi- 
cult to conceptualize a living, breathing, 
piece of hardware from an analysis or a 
drawing. 

• The, extensive use of the computer for 
complex analyses can serve to remove the 
analyst from the real world. One should, 
therefore, require a simplified or support- 
ing analysis that provides an understand- 
able rationale for the phenomena under 
consideration before accepting the results 
of a computer analysis. 

• The emphasis on "visibility to manage- 
ment" in the review process should not be 
extended to the point that one can be led 
to believe the job is completed, or the de- 
sign is satisfactory, when such visibility 



196 



SKYLAB 1 



is provided. A major emphasis on status, 
on design details, or on documentation 
can detract from a productive examina- 
tion of "how does it work" or "what do you 
think." 
• Today's organizations seldom include the 
old-fashioned chief engineer who, rela- 
tively devoid of administrative or man- 
agerial duties, brings total experience 
and spends most of the time in the subtle 
integration of all elements of the system 
under purview. Perhaps we should more 
actively seek and utilize these talented 
individuals in an engineering organiza- 
tion. 

Significant Findings 

1) The launch anomaly that occurred at ap- 
proximately 63 seconds after lift-off was 
a failure of the meteoroid shield of the 
orbital workshop. 

2) The SAS-2 wing tie downs were broken 
by the action of the meteoroid shield at 
63 seconds. Subsequent loss of the SAS-2 
wing was caused by retro-rocket plume 
impingement on the partially deployed 
wing at 593 seconds. 

3) The failure of the S-II interstage adapter 
to separate in flight was probably due to 
damage to the ordnance separation de- 
vice by falling debris from the meteoroid 
shield. 

4) The most probable cause of the failure of 
the meteoroid shield was internal pres- 
surization of its auxiliary tunnel. This 
internal pressurization acted to force the 
forward end of the tunnel and meteoroid 
shield away from the orbital workshop 
and into the supersonic air stream. The 
resulting forces tore the meteoroid 
shield from the orbital workshop. 

5) The pressurization of the auxiliary tun- 
nel resulted from the admission of high 
pressure air into the tunnel through 
several openings in the aft end. These 
openings were: (1) an imperfect fit of the 
tunnel with the aft fairing; (2) an open 



boot seal between the tunnel and tank 
surface; and (3) open stringers on the aft 
skirt under the tunnel. 

6) The venting analysis for the tunnel was 
predicated on a completely sealed aft 
end. The openings in the aft end of the 
tunnel thus resulted from a failure to 
communicate this critical design feature 
among aerodynamics, structural design, 
and manufacturing personnel. 

7) Other marginal aspects of the design of 
the meteoroid shield which, when taken 
together, could also result in failure dur- 
ing launch are: 

a) The proximity of the meteoroid 
shield forward reinforcing angle to 
the air stream 

b) The existence of gaps between the or- 
bital workshop and the forward ends 
of the meteoroid shield 

c) The light spring force of the auxil- 
iary tunnel frames 

d) The aerodynamic crushing loads on 
the auxiliary tunnel frames in flight 

e) The action of the torsion-bar actu- 
ated swing links applying an out- 
ward radial force to the meteoroid 
shield 

f) The inherent longitudinal flexibility 
of the shield assembly 

g) The nonuniform expansion of the 
orbital workshop tank when pressur- 
ized 

h) The inherent difficulty in rigging for 
flight and associated uncertain ten- 
sion loads in the shield. 

8) The failure to recognize many of these 
marginal design features through six 
years of analysis, design and test was 
due, in part, to a presumption that the 
meteoroid shield would be "tight to the 
tank" and "structurally integral with 
the S-IVB tank" as set forth in the 
design criteria. 

9) Organizationally, the meteoroid shield 
was treated as a structural subsystem. 
The absence of a designated project engi- 
neer for the shield contributed to the 



197 



READINGS IN SYSTEMS ENGINEERING 



lack of effective integration of the 
various structural, aerodynamic, aeroe- 
lastic, test fabrication, and assembly 
aspects of the meteoroid shield system. 

10) The overall management system used 
for Skylab was essentially the same as 
that developed in the Apollo program. 
This system was fully operational for 
Skylab; no conflicts or inconsistencies 
were found in the records of the manage- 
ment reviews. Nonetheless, the signifi- 
carce of the aerodynamic loads on the 
meteoroid shield during launch was not 
revealed by the extensive review pro- 
cess. 

11) No evidence was found to indicate that 
the design, development and testing of 
the meteoroid shield were compromised 
by limitations of funds or time. The 
quality of workmanship applied to the 
meteoroid shield was adequate for its 
intended purpose. 

12) Given the basic view that the meteoroid 
shield was to be completely in contact 
with and perform as structurally inte- 
gral with the S-IVB tank, the testing 
emphasis on ordnance performance and 
shield deployment was appropriate. 

13) Engineering and management person- 
nel on Skylab, on the part of both con- 
tractor and government, were available 
from the prior Saturn development and 
were highly experienced and adequate 
in number. 

14) The failure to recognize these design 
deficiencies of the meteoroid shield, as 
well as to communicate within the pro- 
ject the critical nature of its proper vent- 
ing, must therefore be attributed to an 
absence of sound engineering judgment 
and alert engineering leadership con- 
cerning this particular system over a 
considerable period of time. 

Corrective actions 

1) If the backup orbital workshop or a simi- 
lar spacecraft is to be flown in the 



future, a possible course of action is to 
omit the meteoroid shield, suitably coat 
the orbital workshop for thermal con- 
trol, and accept the meteoroid protection 
afforded by the orbital workshop tank 
walls. If, on the other hand, additional 
protection should be necessary, the 
Board is attracted to the concept of a 
fixed, nondeployable shield. 

2) To reduce the probability of separation 
failures such as occurred at the S-II in- 
terstage Second Separation Plane, both 
linear shaped charges should be detonat- 
ed simultaneously from both ends. In 
addition, all other similar ordnance 
applications should be reviewed for a 
similar failure mode. 

3) "Structural" systems that have to move 
or deploy, or that involve other mecha- 
nisms, equipment or components for 
their operation, should not be the exclu- 
sive responsibility of a structures orga- 
nization. 

4) Complex, multi-disciplinary systems 
such as the meteoroid shield should have 
a designated project engineer who is 
responsible for all aspects of analysis, 
design, fabrication, test and assembly. 

Observations on the 
Management System 

The Board found no evidence that the design 
deficiencies of the meteoroid shield were the 
result of, or were masked by, the content and 
processes of the management system that 
were used for Skylab. On the contrary, the 
rigor, detail, and thoroughness of the system 
are doubtless necessary for a program of this 
magnitude. At the same time, as a caution- 
ary note for the future, it is emphasized that 
management must always be alert to the po- 
tential hazards of its systems and take care 
that an attention to rigor, detail and thor- 
oughness does not inject an undue emphasis 
on formalism, documentation, and visibility 
in detail. Such an emphasis can submerge 
the concerned individual and depress the 



198 



SKYLAB 1 



role of the intuitive engineer or analyst. It 
will always be of importance to achieve a 
cross-fertilization and broadened experience 
of engineers in analysis, design, test or oper- 
ations. Positive steps must always be taken 
to assure that engineers become familiar 
with actual hardware, develop an intuitive 
understanding of computer-developed re- 



sults, and make productive use of flight data 
in this learning process. The experienced 
chief engineer, whose time can be spent in 
the subtle integration of all elements of the 
system under review, free of administrative 
and managerial duties, can also be a major 
asset to an engineering organization. 



199 



THE SEASAT FAILURE 



N 9 3 • 2^§9Ji 
Report of the Seasat Failure Review Board ; ^ ^g£~ 



by the NASA Investigation Board 

The Seasat spacecraft failed on October 9, 
1978, after satisfactory operation in orbit for 
105 days, as a result of a loss of electrical 
power in the Agena bus that was used as a 
part of the spacecraft. The loss of power was 
caused by a massive and progressive short in 
one of the slip ring assemblies that was used 
to connect the rotating solar arrays into the 
power subsystem. The most likely cause of 
this short was the initiation of an arc be- 
tween adjacent slip ring brush assemblies. 
The triggering mechanism of this arc could 
have been either a wire-to-brush assembly 
contact, a brush-to-brush contact, or a mo- 
mentary short caused by a contaminant that 
bridged internal components of opposite elec- 
trical polarity. 

The slip ring assembly, as used in the 
Seasat spacecraft, was connected into the 
power subsystem in such a way that most of 
the adjacent brush assemblies were of oppo- 
site electrical polarity. This wiring arrange- 
ment, together with the congested nature of 
the design itself, made the Seasat slip ring 
assembly a unique, first-of-a-kind component 
that was particularly prone to shorting. 

The possibility of slip ring failures result- 
ing from placing opposite electrical polarities 
on adjacent brush assemblies was known at 
least as early as the summer of 1977 to other 
projects within the contractor's organization. 
Furthermore, failures of slip ring assemblies 
due to shorting between brushes had been 
experienced by the prime contractor on the 
slip ring assemblies used by other programs. 
That the Seasat organization was not fully 
aware of these potential failure modes was 
due to a breakdown in communication within 
the contractor's organization. 

In addition to this small, though fatal, 
breakdown in communications, the failure to 
give the slip ring assembly the attention it 
deserved was due, in large part, to an under- 



PREQEDING PAGE BLANK NOT FILMED 



p. IS 



lying program policy and a pervasive view 
that Seasat's Agena bus was a standard, 
well-proven piece of equipment that had 
been used on other programs. In actuality, 
however, three major subsystems — the elec- 
trical power subsystem, the attitude control 
subsystem, and the data subsystem — were 
substantially modified for use on Seasat's 
Agena bus. So firmly rooted was this princi- 
ple of using a "standard Agena bus" that, 
even after the engineering staffs of both the 
government and the contractor were well 
aware of the final uniqueness of their bus, 
the words, and the associated way of doing 
business, persisted to the end. 

The point of view that the Seasat bus was 
flight proven, standard equipment proved to 
have far-reaching consequences. It became 
program policy to minimize testing and docu- 
mentation, to qualify components by similar- 
ity wherever possible, and to minimize the 
penetration into the Agena bus by the gov- 
ernment. It led to a concentration by project 
management of the sensors, sensor integra- 
tion, and the data management system to the 
near exclusion of the bus subsystems. Impor- 
tant component failures were not reported to 
project management, a test was waived with- 
out proper approval, and compliance with 
specifications was weak. The component that 
failed — the slip ring assembly — was never 
mentioned in the briefing charts for either 
the Consent to Ship meeting or the Critical 
Design Review. 

The Failure Modes, Effects and Critical- 
ity Analysis that was conducted for the elec- 
trical power subsystem did not consider 
shorts as a failure mode and thus did not re- 
veal the presence of single point failure 
modes in the system or provide a basis for the 
development of a full complement of safing 
command sequences that could be used by 
the flight controllers in responding to 



^^sSEmmmm 



201 



READINGS IN SYSTEMS ENGINEERING 



anomalies in the power subsystem. A lack of 
clarity and rigor in the operating require- 
ments and constraints documents for the 
power subsystem of the bus, together with 
this lack of safing command sequences, pre- 
vented the flight controllers from having all 
the tools they needed to do their job. The 
flight controller for the power subsystem was 
also new to his job at the time of the failure 
and thus was not sufficiently knowledgeable 
of the system he was controlling. While no 
action of the flight controllers contributed to 
the failure, they did fail to follow the pre- 
scribed procedures in response to the infor- 
mation available to them at the time of the 
failure. 

The advantages of using standard, well 
proven equipment in terms of both cost and 
mission success are well recognized. But the 
experience of Seasat illustrates the risks that 
are associated with the use of equipment that 
is classified as "standard" or "flight proven." 
The uncritical acceptance of such classifica- 
tions by the Seasat engineering staff sub- 
merged important differences in both design 
and application from previously used equip- 
ment. It is therefore important that thorough 
planning be conducted at the start of a 
project to fully evaluate the heritage of pre- 
viously used equipment and to establish 
project plans and procedures that enable the 
system to be selectively penetrated. 

The Seasat Mission and Its 
Spacecraft 

The Seasat Project was a proof-of-concept 
mission whose objectives included demon- 
stration of techniques for global monitoring 
of oceanographic and surface meteorological 
phenomena and features, provision of 
oceanographic data for both application and 
scientific areas, and the determination of key 
features of an operational ocean dynamics 
monitoring system. 

To fulfill these objectives, the Seasat sen- 
sor complement comprised a radar altimeter 
(ALT), a synthetic aperture radar (SAR), a 



Seasat-A scatterometer system (SASS), a 
scanning multichannel microwave radiome- 
ter (SMMR), and a visual and infrared radi- 
ometer (VIRR). All of these sensors except 
the SAR operated continuously; telemetry 
from them, as well as from all engineering 
subsystems, was sent in real-time when over 
a ground station and recorded on a tape re- 
corder for later transmission to provide data 
for a full orbit. SAR data had to be transmit- 
ted in real-time, without the use of the on- 
board recorder, to specially equipped stations 
because of its high data rate. The normal 
duty cycle for the SAR was four percent. 

The five sensors were integrated into a 
sensor module that provided mounting, ther- 
mal control, power conditioning, telemetry, 
and command support to the instruments. 
The second major element of the spacecraft 
was an Agena bus which provided attitude 
control, electrical power, telemetry and com- 
mand functions to the sensor module. In ad- 
dition to these on-orbit functions, the Agena 
bus also provided injection stage propulsion 
and guidance to orbit. The spacecraft was 
three-axis stabilized with all sensors Earth 
pointing and is shown in its on-orbit configu- 
ration in Figure 1. To provide near global 
coverage, the spacecraft was injected into a 
790 kilometer, near circular orbit with an 
inclination of 108 degrees and a period of ap- 
proximately 101 minutes. Design lifetime 
was one year on orbit, with expendables pro- 
vided for a three-year life. 

The sensors were provided by various 
NASA Centers. The sensor module, the Age- 
na bus and the integration of the sensors, 
sensor module and Agena bus into a space- 
craft was provided by the Lockheed Missies 
and Space Company under contract to the Jet 
Propulsion Laboratory (JPL). 

Responsibility for Seasat project manage- 
ment, mission planning and direction, mis- 
sion operations and experiment data process- 
ing resided at JPL. The Goddard Space 
Flight Center (GSFC) provided network 
support and spacecraft orbit and attitude de- 
terminations; use was therefore made of the 



202 



THE SEASAT FAILURE 



__ r 



existing Spaceflight Tracking and Data 
Network, the NASA Communications (NAS- 
COM) network, and the Project Operations 
Control Center that are operated by GSFC. 

To place this failure review in a proper 
perspective, it is noted that the Seasat space- 
craft operated in orbit in a generally satisfac- 
tory maneuver for over three months and 
provided a large amount of scientific data. 
The sensors represented a significant ad- 
vance in technology and their integration 
into the sensor module, a large engineering 
challenge. In addition, Seasat also required 
the creation of significantly enlarged capa- 
bilities in the acquisition and processing of 
flight data. That the important and signifi- 
cant technical and engineering advance- 
ments were achieved is a tribute to the skill 
and dedication of all who were associated 
with this program. 

The Seasat spacecraft was successfully 
launched on June 26, 1978, and thus operat- 
ed for 105 days until the failure occurred on 
October 9, 1978. During this time in orbit, 
the spacecraft operation was generally satis- 
factory with considerable data being ob- 
tained from all of the sensors. Three signifi- 
cant anomalies were experienced during the 
life of Seasat in orbit, one involving sun in- 
terference in the attitude control system scan 
wheels, one caused by a sticking thermostat 
in a sensor heater circuit, and one in which 
the spacecraft suffered an abnormally low 
bus voltage for several orbits. Because of a 
possible relationship of these latter two 
anomalies with the failure of October 9, 
1978, they were specifically investigated by 
the Board. 

Program History and Management 

The Seasat program was conceived and 
initiated in a period of transition in the 
philosophy of management of NASA pro- 
grams following the Apollo program. Apollo, 
and to varying degrees other NASA flight 
programs, were characterized by extensive 
test programs, large formal documentation 



systems, and comprehensive and frequent 
technical and management reviews. A large 
in-house staff was required in order to imple- 
ment this approach. The high cost of conduct- 
ing space programs in this mode severely 
constrained the future uses of space. During 
the final phases of the Apollo program, 
NASA management accordingly instituted a 
policy aimed at reducing the cost space mis- 
sions. This policy was aggressively pursued 
by the highest levels of management. 

A Low Cost Systems Office was estab- 
lished in Headquarters to oversee a stan- 
dardization program and to encourage the 
use of existing hardware. This program in- 
cluded the development of standard compo- 
nents as well as a multimission spacecraft. 

A major emphasis was placed on shifting 
work from in-house to out-of-house in consid- 
eration of reducing the NASA manpower 
base. Design-to-cost techniques and cost 
benefits of heritage through the use of hard- 
ware and software developed for other pro- 
grams were subjects to be addressed at each 
step in the approval cycle. 

The basic philosophy of the Seasat pro- 
gram was thus established in an environ- 
ment in which management emphasis was 
shifting from one of demonstrating a nation- 
al capability to operate reliably in space to 
one of reducing the cost of utilizing space. 
Design-to-cost was a fundamental tenet of 
the Seasat project definition. A cost estimate 
of $58.2 million was established as a target 
cost at the end of the feasibility study phase 
in mid- 1973 and was imposed as a design-to- 
cost ceiling in December 1973 by NASA 
management. Any overruns were to be offset 
by descoping the mission content. 

In attempting to define a program which 
would both satisfy the user community and 
live within the ceiling cost, the concept of 
making maximum use of proven existing 
hardware and software was adopted early in 
the program planning phase. This in turn 
provided for a reduction in design and devel- 
opment effort and in the size of the in-house 
staff needed to monitor the activity. 



203 



READINGS IN SYSTEMS ENGINEERING 



Solar Arrays (2) 



Agena Bus 




Sensor Module 



S AR Antenna 



Earth Pointing Sensors 



Figure 1 On-Orbit Configuration of the Seasat Spacecraft 



These were key elements of the manage- 
ment philosophy which influenced the struc- 
ture and conduct of the program. 

Program Planning 

Feasibility Studies (Phase A) - Feasi- 
bility for the Seasat mission was established 
in '73 through three studies conducted by the 
JPL, GSFC, and the Applied Physics Labora- 
tory of the Johns Hopkins University. These 
studies were aimed at meeting the set of user 
requirements generated at a series of meet- 
ings held in the first half of 1973 among 
NASA and representatives of the govern- 
mental, commercial, and institutional com- 
munities of users of ocean dynamics data. 



With the user requirements as a basis, the 
feasibility studies examined the Seasat mis- 
sion from an overall systems viewpoint, in- 
cluding a review of instrumentation and pos- 
sible spacecraft (bus) approaches to accom- 
modate the instrumentation. 

Subsequent to the submission of the 
Phase A studies in July 1973, a joint 
NASA/User Study Task Team was formed to 
review the Phase A studies, integrate the 
results, and provide technical and program- 
matic guidance for more in-depth Definition 
Phase studies. 

As a result of this review, the Task Team 
recommended a Baseline Mission which in- 
cluded a complement of the five sensor types 
that actually ended up flying on Seasat. 



204 



THE SEASAT FAILURE 



Based upon cost estimates prepared by 
the Phase A study participants, the Task 
Team recommended a target cost of $58.2 
million for the Baseline Mission. This includ- 
ed the cost of the spacecraft bus and instru- 
ments, the launch vehicles, and tracking and 
data acquisition. An Alternate Payload Mis- 
sion of reduced capability, excluding the syn- 
thetic aperture radar, was also recommended 
for further study with a target cost of $43.2 
million. 

There was some discussion in the Seasat 
Study Study Task Team Report (October 
1973) of the use of an existing bus to mini- 
mize cost. The idea, however, was addressed 
with some skepticism. While it was believed 
that the use of subsystems with a high de- 
gree of inheritance from existing programs 
was desirable and possible, it was not clear at 
that time that an existing bus could be 
adapted economically. 

Definition Studies and Preliminary 
Design (Phase B) - Definition Phase Studies 
of the Baseline and Alternate Payload Mis- 
sions recommended by the Seasat Study 
Task Team were conducted from November 
1973 to the summer of 1974. The Wallops 
Flight Center managed the Definition Phase 
Study of the Baseline Mission which was con- 
ducted by the Applied Physics Laboratory. 
The JPL, assisted by various aerospace com- 
panies familiar with Earth satellite design, 
conducted the Definition Phase Study of the 
Alternate Mission. 

In December 1973, NASA management 
adopted the $58.2 million figure recommend- 
ed by the Task Team as a not to exceed ceiling 
for the Seasat Baseline Mission. The efforts 
of the Definition Phase Study participants 
were accordingly intensified to develop the 
most economical satellite system possible 
that would best suit the user requirements 
within the cost ceiling. 

GSFC declined to participate in the Defi- 
nition Phase activity as they had serious 
doubts as to their ability to structure a full 



Baseline Mission within the design-to-cost 

ceiling. 

With the stimulus of the design-to-cost 
ceiling, and management emphasis on the 
maximum use of existing subsystem hard- 
ware, the JPL Definition Phase Group pro- 
posed the of idea building a spacecraft sys- 
tem comprising two major elements: a sensor 
module designed specifically for Seasat, and 
a spacecraft bus based on an existing, flight 
proven bus devloped for other Air Force or 
NASA programs. The JPL viewed the results 
of the Phase A studies as indicating that the 
requirements of the sensors could be satisfied 
by standard support subsystems for attitude 
control, power, structures, thermal control, 
etc. On the other hand, the area of greatest 
uncertainty was seen to be the definition of 
the sensor's operating capabilities, data re- 
quirements and sensor system integration. It 
was therefore proposed that if a suitable 
spacecraft bus were available, the design and 
development effort could be concentrated on 
the sensors and their integration with a sen- 
sor module that could then be mated to the 
bus via a mechanical/electrical interface. 

The JPL entered into four $15,000 study 
contracts with aerospace companies (Boeing, 
General Electric, Lockheed, and TRW) that 
had existing spacecraft designs with capabil- 
ities in the range of Seasat requirements to 
evaluate the concepts that: (1) there are ex- 
isting buses that could be used, without 
modification, to supply the necessary support 
functions for the sensor payload, and (2) new 
design functions could be incorporated in a 
separate module along with the sensors and 
thereby reduce the systems development 
task to a sensor system development task. 
The studies were conducted from November 
15, 1973 to March 30, 1974. The sensors were 
described to the study contractors as they 
were developed on December 15, 1973, with 
updates as appropriate until the end of these 
studies. 

It was concluded as a result of these stud- 
ies that basic sensor support requirements 



205 



READINGS IN SYSTEMS ENGINEERING 



could be satisfied by the existing spacecraft 
bus designs studied with "no major changes," 
although "minor modifications" were ac- 
knowledged to be required. It was contem- 
plated, for example, that minor modifications 
would be required of the attitude control, 
power, and temperature control subsystems. 
Telemetry, tracking and command subsys- 
tems were reported to be off-the-shelf de- 
signs, but required significant modification. 
It should be noted that the contractor bus 
studies were concerned almost solely with 
mission performance requirements. The re- 
ports did not sufficiently define the sub- 
system design or component selections to 
provide a basis for an adequate penetration 
of heritage. The JPL Definition Phase Final 
Report nevertheless concluded that the exist- 
ing bus approach had significant cost, sched- 
ule and risk advantages, and permitted a 
concentration of development efforts on the 
sensor system. 

Midterm reports in May 1974 of the JPL 
and the Wallops Flight Center and Applied 
Physics Laboratory Definition Phase study 
groups demonstrated that neither the Base- 
line nor Alternate Payload Mission was 
achievable within the $58.2 million ceiling. 
The Wallops Flight Center and Applied 
Physics Laboratory's estimate for the Base- 
line Mission, which included an in-house de- 
signed spacecraft, was $85.2 million. At this 
point in time the Wallops Flight Center and 
the Applied Physics Laboratory adopted the 
sensor module/existing bus concept that JPL 
was pursuing. JPL's midterm estimate for 
the Alternate Payload Mission using the ex- 
isting bus concept was $65.9 million. 

The JPL and the Wallops Flight Center 
and Applied Physics Laboratory searched for 
ways to descope the project in order to stay 
within the cost ceiling. Each group per- 
formed a number of iterations wherein sen- 
sor performance and sensor combinations 
were varied in order to decrease the cost and 
yet meet the basic user requirements. 

A final presentation of the JPL and 
Wallops Flight Center and Applied Physics 



Laboratory's Definition Phase studies to 
NASA Headquarters management in August 
1974 resulted in a reduced baseline payload 
at the $58.2 million ceiling which eliminated 
the microwave radiometer and combined the 
altimeter and scatterometer into a single in- 
strument, but which retained the synthetic 
aperture radar, as well as the visual and in- 
frared radiometer. 

Spacecraft Requirements and 
Documentation 

The two primary contractual documents on 
Seasat were the Satellite Vehicle Specifica- 
tion (Part I and Part II) and the Satellite Ve- 
hicle System Test Plan. There were 13 other 
documents which required JPL approval, but 
these were primarily implementation and 
operations type plans; i.e., Data Manage- 
ment Plan, Quality Assurance Plan, etc. One 
of these plans, the Reliability Assurance 
Plan, is relevant to this chapter and will be 
discussed herein. 

Part I of the Satellite Vehicle Specifica- 
tion established the performance, design, de- 
velopment, and qualification requirements 
for the Seasat mission. Part II of the specifi- 
cation established the product configuration 
and system test acceptance requirements. 
This specification is similar to a typical Part 
I, Part II Contract End Item specification 
used for most NASA programs. 

The Satellite Vehicle Systems Test Plan 
established the test program for assembling, 
testing, monitoring and operating the Seasat 
spacecraft from manufacturing through 
launch. The Satellite Vehicle Systems in- 
cluded all Lockheed and government fur- 
nished hardware installed in the Agena bus 
assembly and the sensor module. The test 
plan was the controlling test document and 
subordinate only to the Satellite Vehicle 
Specification. An evaluation was made re- 
garding this flow of requirements and the in- 
terrelationships of Lockheed and JPL rela- 
tive to control and the visibility of require- 
ments. 



206 



THE SEASAT FAILURE 



Compliance with Requirements - Dur- 
ing the Board's review, it was determined 
that a significant test required by the JPL 
approved test plan was not conducted. The 
Satellite Vehicle Test Plan required elec- 
tronic assemblies to be subjected to eight 
cycles in thermal environment of which, as a 
minimum, two cycles should be in a vacuum 
chamber (acceptance test). The Slip Ring 
Assembly Component Specification, howev- 
er, did not require a thermal vacuum test. 
This noncompliance was not recognized by 
JPL or Lockheed systems engineering until 
the present failure investigation was begun. 
Discussions with Lockheed and JPL person- 
nel revealed that there was not a closed loop 
system to assure compliance with contractu- 
al requirements identified in the test plan. 

The fact that a component specification 
that violated a contractual requirement 
could be issued is indicative of a lack of 
checks and balances in the system. Another 
indication of this lack surfaced in reviewing 
the qualification requirements. In at least 
two cases, to be discussed below, qualifica- 
tion requirements noncompliance was not 
documented. In fact, in the areas where the 
Board performed an in-depth evaluation, in- 
consistencies in requirements were noted in 
many cases. Most inconsistencies were mi- 
nor; however, the impression left was that 
both compliance with requirements by Lock- 
heed and the check and balance system at 
Lockheed and JPL were deficient. 

Engineering Memoranda - Environ- 
mental derivations, test criteria and detailed 
test requirements were documented in engi- 
neering memoranda (EMs). Lockheed stated 
that EMs were used to allow early genera- 
tion of requirements while the spacecraft de- 
sign was being finalized. A considerable 
number of EMs were developed during the 
course of the Seasat program, and it accord- 
ingly became very difficult to establish a 
documentation trail as to how test require- 
ments were established, modified, and satis- 
fied. In fact, two particular incidents were 



uncovered during detailed evaluation into 
the qualification status of the electrical pow- 
er subsystem components that point out the 
weakness of the EM system. 

In one case, the Seasat environmental 
requirements specified a five minute per axis 
random vibration level but several compo- 
nents were qualified by similarity to a pro- 
gram that required only a three minute per 
axis vibration. This five minute per axis 
requirement was also specified in Part I of 
the Satellite Vehicle Specification. There 
was no documented evidence that this non- 
compliance was acceptable. In the second in- 
cident, pyro shock levels for Seasat were not 
enveloped by the program to which the Sea- 
sat slip ring assemblies were "qualified by 
similarity." While an EM stated that the slip 
ring assemblies are "not highly sensitive to 
pyro shock," there was no documentation or 
analysis to support the stated conclusion. 

Because Seasat was a one-of-a-kind vehi- 
cle, Lockheed did not summarize the require- 
ments contained in the various EMs into a 
single baseline document. A baseline docu- 
ment, with change control, would have been 
a systematic approach to assuring require- 
ments were satisfied and would have pro- 
vided a feedback mechanism to all parties. 
The large number of EMs produced in the 
Seasat program made it very difficult for 
Lockheed to use the EMs to manage the 
program and to assure continuity in require- 
ments, as exemplified above, and equally 
difficult for JPL to effectively penetrate the 
system. 

The Failure Modes, Effects and 
Criticality Analysis (FMECA) - The 
FMECA prepared for Seasat utilized the 
Fault Tree Analysis Technique. In effect, 
this was a method for studying the factors 
that could cause an undesired event to occur 
and inputting these factors into a computer 
model to which probability data could be 
applied to determine the most critical and 
probable sequence of events that could pro- 
duce the undesirable event. 



207 



READINGS IN SYSTEMS ENGINEERING 



The Reliability Assurance Program Plan 
required that a FMECA be performed at the 
system level. Further evaluation revealed 
that "critical/new equipment" would also be 
subjected to an FMECA. Out of the 74 criti- 
cal items identified on Seasat, only three 
were judged to require component level 
FMECAs. These were the command timing 
unit (CTU), the telemetry sensor unit (TSU) 
and the synthetic aperture radar (SAR) an- 
tenna (supplier performed). 

The FMECA for the electrical power sub- 
system stated that there were "no single 
point failures" and listed a number of redun- 
dancies, including main bus power supply 
channels, batteries, charge controllers, and 
others. Electrical shorts were, however, not 
included as possible failure modes; almost all 
of the effort was directed toward consider- 
ation of failure modes that would result in 
loss of solar array power, and the only slip 
ring assembly failure mode considered was 
"slip ring contact failure." The lack of consid- 
eration of electrical shorts in effect prevented 
the FMECA from serving as a tool for direct- 
ing attention to those portions of the system 
where electrical shorts could occur and led to 
the erroneous conclusions that there were no 
single point failure modes in the electrical 
power subsystem. 

Component Specifications - Compo- 
nent specifications were used on Seasat to de- 
fine the design, performance, acceptance, 
and qualification requirements of the major 
hardware items and subassemblies. Because 
the program intent was to utilize as much 
off-the-shelf hardware as possible, many ex- 
isting specifications were redlined and up- 
dated for the Seasat Agena bus. These red- 
lined specifications were then converted into 
component specifications by the responsible 
equipment engineers. After April 1976, a 
program directive established that all com- 
ponent specifications on Seasat required the 
signature approval of reliability engineer- 
ing, of space technology, and of the chief sys- 
tems engineer in addition to the responsible 



equipment engineer and the program engi- 
neer. Two specifications were released prior 
to April 1976 and never received the full 
complement of signature approvals. These 
two specifications were for the Slip Ring As- 
semblies and the Solar Array Drive Motors. 
Had the other three engineering organiza- 
tions reviewed the specifications, quite possi- 
bly the Slip Ring Assembly thermal vacuum 
test deletion may have been prevented and 
inconsistencies in the qualification require- 
ments may have been avoided. The compo- 
nent specifications were not reviewed and 
approved by JPL. 

Qualification for Flight - The Seasat 
program used the classical methods of quali- 
fying hardware for flight. These were: 

a) Qualification by test to demonstrate the 
capability of an item to meet specification 
requirements. 

b) Qualification by design similarity where- 
by an unqualified item is compared with 
an item qualified by test to determine 
whether the requirements for both items 
and their configurations are sufficiently 
similar to justify not testing the unquali- 
fied item. 

c) Qualification by engineering analysis, in- 
dependently or in conjunction with test 
and/or similarity, to meet a specific quali- 
fication in the specifications. The use of 
engineering analysis alone could not be 
used to satisfy all qualification require- 
ments. 

In September 1976, the Lockheed Seasat pro- 
ject issued a directive creating an Equipment 
Qualification Review Board for the purpose 
of reviewing and approving all qualification 
and design similarity certificates. The pri- 
mary membership of the board included the 
program engineering managers, the chief 
systems engineer, the program reliability en- 
gineer, the quality assurance manager, and 
the applicable space technology manager. 
This Board met every two weeks to review 



208 



THE SEASAT FAILURE 



the status of the qualification program and to 
determine what additional tasks were re- 
quired to qualify a given item. Status reports 
were issued by program reliability engineer- 
ing which tracked the qualification progress 
and documented open items. 

The qualification cycle concluded with a 
meeting to review all test data, design simi- 
larity statements, engineering analyses, and 
individual component pedigree packages. In- 
dividual Certificates of Qualification were is- 
sued stating that the specific component had 
been qualified to the intended environment 
and was acceptable for flight. A JPL engi- 
neering representative attended these quali- 
fication review meetings but was not re- 
quired to approve the qualification certif- 
icate. A JPL reliability representative at- 
tended approximately 25 percent of the re- 
view meetings. 

Review of Build Paper - An evaluation 
of the Seasat "build" paper was made with 
primary attention focused on the electrical 
power subsystem. The review encompassed 
the electrical harness fabrication and instal- 
lation, the "pedigree packages" on electrical 
components and assemblies, nonconformance 
reports on anomalies encountered in assem- 
bly and test, vehicle log books, and the vehi- 
cle acceptance summary. 

Because the Board's failure analysis 
eventually identified the slip ring assembly 
as the component responsible for the Seasat 
failure, the detailed build paper associated 
with only this component will be discussed in 
the next section. However, some brief obser- 
vations are presented below that deal with 
other findings made during the course of the 
investigation. 

The nonconformance reports are used by 
Lockheed to document nonconforming condi- 
tions and resultant dispositions and correc- 
tion actions. In general, the nonconformance 
report system at Lockheed was found to be 
acceptable. At the Board's request, Lockheed 
reviewed, cataloged, and summarized all 
electrical power subsystem nonconformance 



reports and made a conscious decision as to 
the possible effect of the anomaly in contri- 
buting to the Seasat failure. None of the non- 
conformances were judged to be contributory 

to the failure. 

Evaluation of the spacecraft build paper 
of the electrical power subsystem indicated 
that the Air Force Plant Representative Of- 
fice involvement, operating under delegation 
from JPL, was shallow. Inspection coverage 
was concentrated at the system level with 
few in-process mandatory inspection points. 

Early negotiations surfaced the fact that 
the Air Force Plant Representative Office 
could provide neither the number of person- 
nel nor the required skill levels to perform 
electronic inspections. As a result of these 
negotiations, JPL elected to send three JPL 
inspectors on extended temporary duty to 
perform 100 percent of the solder joint in- 
spections and electronic component accep- 
tance testing. While it cannot be stated that 
a more in-depth involvement by the govern- 
ment would have prevented the failure, it is 
the opinion of the Board that the depth of 
penetration was inappropriate and a more 
selective penetration would have been in or- 
der rather than a nearly total reliance on 
system level audits and shakedown inspec- 
tions for the bus assembly operations. 

SLIP RING HERITAGE 

Consistent with the basic philosophy of the 
Seasat program to use, to the maximum ex- 
tent possible, standard flight-proven equip- 
ment, the solar array drive motors and slip 
ring assemblies for Seasat were adapted from 
another Lockheed program. At the time of 
initial contract negotiations, this other Lock- 
heed program had just developed a slip ring 
assembly and was in the process of perform- 
ing qualification testing. This slip ring was 
also being considered for still other Lockheed 
programs and it was anticipated that the as- 
sembly would be a qualified and flight- 
proven design by the time Seasat was flown. 
As it turns out, however, the program for 



209 



READINGS IN SYSTEMS ENGINEERING 



which the design was originally developed 
was canceled after completion of slip ring 
qualification but prior to flight; however, one 
other Lockheed program did fly a slip ring 
assembly of this design shortly before Seasat 
was launched. While the designs of the slip 
ring assembly for Seasat and this "previously 
flown" program were identical, the wiring se- 
quence of the individual rings and brushes 
was different in the two programs. As noted 
earlier, the Seasat slip rings were wired such 
that most of the adjacent power brushes were 
of opposite DC polarity while the other Lock- 
heed program was wired such that the adja- 
cent power brushes had the same polarity. 
This difference in how the slip ring assem- 
blies were connected into the electrical power 
subsystem thus became crucial to the heri- 
tage of the Seasat slip ring assembly; when 
the Seasat slip ring assembly became, in its 
application, connected in a manner that was 
different from its sole predecessor it became 
a unique, first of a kind component. 

Two significant problems were noted as a 
result of random vibration testing of the slip 
ring assemblies used for the other Lockheed 
flight program. An isolation failure was 
found after vibration testing in two adjacent 
brush/ring circuits. The corrective action was 
to separate the brushes. Also, when the as- 
sembly was opened for this operation, a crack 
was noted in the brush mounting block at a 
mounting hole. This block was replaced on 
the failed unit and a "T" strengthener was 
added to all identical slip ring assemblies, in- 
cluding the Seasat units, to distribute the 
mounting loads away from the mounting 
point. 

Failure History - Slip ring assemblies of 
the design flown by Seasat experienced two 
nonconformances that provide evidence of 
two separate failure mode possibilities. One 
of these was the isolation failure noted above 
on the other Lockheed flight program that 
was indicative of a possible failure mode due 
to contact between adjacent brushes of oppo- 
site polarity. Another failure mode identified 



on one of the Seasat assemblies was caused 
by shorting of a wire to ground due to cold 
flow of the Teflon insulation in the region 
where high stresses were imposed on the 
wire. This incident will be described later. 

Considerable evidence exists in published 
reports that the sliding friction between 
brushes and rings will generate debris parti- 
cles that can accumulate and produce electri- 
cal noise or, in some cases, short circuits be- 
tween adjacent rings and brushes. Lockheed 
experienced a shorting failure in a slip as- 
sembly used in ground tests of a control mo- 
ment gyro prior to June 1977, which was at- 
tributed to accumulation of brush-generated 
debris and subsequent arcing between adja- 
cent power brushes. Discussion with engi- 
neering personnel from TRW, Ball Corpora- 
tion, and Sperry Flight Systems have indi- 
cated that other aerospace contractors have 
experienced similar slip ring shorts in 
ground tests. As a result of their experience 
with slip rings, Sperry initiated an experi- 
mental study of the possible effects of debris. 
While the Board recognizes that there are 
significant differences between the design 
and application of the Seasat slip ring assem- 
bly and these other units, experience illus- 
trates a third possible failure mode due to 
shorting caused by contaminants or debris 
within the assembly. 

Seasat Slip Ring History - A portion of 
the build history of components is assembled 
by Lockheed into pedigree packages. These 
packages contain component drawings, a 
component specification including accep- 
tance and qualification test requirements, 
nonconformance reports, and some vendor 
documentation including specified testing 
and plans test records. Component selection 
for pedigree packages was determined by the 
Seasat Program Office and the quality assur- 
ance organization at Lockheed. The Seasat 
slip ring assemblies are documented by such 
pedigree packages. Relevant component his- 
tory not contained in the slip ring pedigree 
packages include vendor assembly and test 



210 



THE SEASAT FAILURE 



nonconformance reports (including failure 
reports), assembly test procedures and 
records (including brush alignments and 
pressure checks and brush "run-in" proce- 
dures), and relevant vendor and customer 
correspondence. 

The timing of the Seasat contract was 
such that Lockheed was able to acquire two 
partially assembled slip ring assemblies 
when another Lockheed program referred to 
herein as Program A, was canceled. Program 
A had initially contracted for 10 assemblies 
and, at the time of termination, had accepted 
delivery of one qualification unit, one devel- 
opment unit, and two production units leav- 
ing six partially assembled units at the ven- 
dor. The Seasat program picked up two of 
these units and Lockheed Program B picked 
up the additional units. Reference will be 
made to Program B in other portions of this 
report relative to test experience and use of 
Program B qualification testing as a basis for 
qualifying the Seasat slip rings by similar- 
Program A personnel were informed by 
Poly-Scientific in late 1973 that the con- 
straints placed upon the length of the assem- 
bly were found to be restrictive and that re- 
lief of the specifications would enhance reli- 
ability. Program A, however, could not relax 
the specification. Although the Seasat appli- 
cation was not constrained by length, the 
program desire to use available off-the-shelf 
hardware precluded the development of a 
new unit having increased dimensional tol- 
erances between the rings and brush assem- 
blies with possibly enhanced inherent reli- 
ability. 

Seasat personnel initiated discussions 
with Poly-Scientific in late 1975 using the 
Lockheed Program A specification as a base- 
line. On February 3, 1976, Poly-Scientific 
submitted its first written quote for two as- 
semblies to be fabricated and tested per the 
Program A specification. This initial quote 
was not acceptable to Lockheed, and the re- 
sponsible equipment engineer and buyer re- 
sponded on March 5, 1976, with a Seasat red- 



lined version of the Program A specification. 
It was in this March 5, 1976, specification 
that the Program A requirement for 10 cy- 
cles of thermal vacuum acceptance testing 
was deleted. This deletion occurred even 
though: (1) the majority of the Seasat elec- 
tronic assemblies and electromechanical as- 
semblies were subjected to a thermal vacuum 
acceptance test; (2) Seasat reliability and 
systems engineering personnel, and JPL per- 
sonnel were unaware of this deletion until 
the present failure investigation; and (3) the 
thermal vacuum test was contractually re- 
quired and a waiver of the requirement was 
never issued 

Upon pursuing the thermal vacuum dele- 
tion further, it was determined from inter- 
views with involved personnel that the test 
was deleted during verbal negotiations be- 
tween both the responsible equipment engi- 
neer and the buyer at Lockheed, and the ven- 
dor in order to reduce unit cost of the slip 
ring assemblies. The responsible Lockheed 
program engineer approved the deletion but, 
at that time, there was no requirement to co- 
ordinate specifications with the Seasat pro- 
gram reliability engineer or the chief sys- 
tems engineer. The fact that a waiver was 
not issued on this and other contract noncom- 
pliances is indicative of a weak compliance 
system between Lockheed and JPL. 

On March 25, 1976, Lockheed issued a 
formal Request for Quote to Poly-Scientific 
for two Seasat slip ring assemblies built to 
the March 5, 1976 specification with a re- 
quested delivery date of one year. On May 
26, 1976, Lockheed authorized contract go 
ahead for two slip ring assemblies at a unit 
price of $8,953.50. 

Researching the manufacturing history 
and fabrication and test anomalies at Poly- 
Scientific resulted in the following: 

a) There were four anomalies noted on slip 
ring unit 1001. Three were minor and ap- 
pear to have had no real impact on assem- 
bly reliability. The fourth anomaly was a 
Teflon wire short to an adjacent ground 



211 



READINGS IN SYSTEMS ENGINEERING 



lug. The repair action, approved by Lock- 
heed engineering, was to insulate the 
ground terminal and repot with ES 222-2 
cement. The damaged insulation on the 
wire was not repaired. This discrepancy 
report was not included in the vendor's 
data package and consequently this fail- 
ure was not contained in the Lockheed 
pedigree package. 

b) Slip Ring Unit 1002 (-Y solar array) had 
the more significant anomalies noted dur- 
ing fabrication and test. These anomalies 
are summarized as follows: 

1) 9/20/76 - 80 minute run-in of brushes 
to rings at 100 ± 10 rpm. Run-in time 
should have been for 100 to 115 min- 
utes. This discrepancy was missed and 
not documented. 

2) 9/23/76 - discrepancy No. 146522 - dis- 
colored rings noted after above run-in 
test. Unit had to be completely disas- 
sembled, brushes and rings recleaned, 
unit reassembled and another run-in 
performed. The exact run-in time was 
not recorded nor entered into the log 
book. 

3) 11/12/76 - discrepancy No. 151887 - ex- 
cessive noise noted caused by moisture 
pick-up in the brush material. Correc- 
tive action was to run the unit in vacu- 
um at 14.4 rpm for 1£ hours. No vacu- 
um cleanup was performed after this 
14.4 rpm run-in test. This run time 
was not entered into the log book. 

c) Review of vendor documentation and sub- 
sequent teleconferences with Poly- 
Scientific personnel revealed the follow- 
ing assembly technique and procedures: 
1) The assembly planning documenta- 
tion specified that the brushes were to 
be aligned "in center of the rings." 
This requirement was verified visual- 
ly by the inspector, but no dimensional 
checks were made. Proper alignment 
of the brushes is dependent, therefore, 
on the inspector's judgment. 



2) Poly-Scientific stated that the toler- 
ances within the slip ring assembly 
could allow adjacent brushes to touch. 
It is noted here that an identical slip 
ring assembly experienced an isola- 
tion failure during acceptance testing 
which was probably caused by adja- 
cent brushes touching. (Program B 
hardware). 

Both Seasat slip ring assemblies were 
shipped from Poly -Scientific on February 22, 
1977. These units were received and accepted 
at Lockheed on March 11, 1977, where they 
remained in storage until required for instal- 
lation on their respective solar array mod- 
ules. 

In approximately July 1977, Lockheed 
Program B, which utilized identical slip ring 
assemblies, made a wiring change external 
to the slip rings that separated the polarity 
arrangement of adjacent slip rings. By 
changing connector pin functions, the power 
applied to individual rings was changed from 
a configuration in which adjacent rings were 
of opposite polarity to one having positive 
contacts on one end of the slip ring assembly 
and negative contacts on the opposite end. 
This wiring change significantly reduced the 
possibility of internal shorts within the slip 
ring assembly. 

The Seasat chief system engineer was 
contacted by a system engineer from Pro- 
gram B about this change in wiring in Au- 
gust 1977. The explanation given for the wir- 
ing change was a concern that the ascent vi- 
bration environment could cause adjacent 
brushes to make contact and thus produce an 
electrical short because Program B slip rings 
had power applied during launch. The chief 
system engineer discussed this change with 
the Seasat program engineer and they decid- 
ed not to make a similar wiring change be- 
cause Seasat did not see the same launch vi- 
bration levels and because Seasat slip rings 
were not planned to be powered during 
launch. It is noted that in April 1978, a 
change in launch relay configuration was 



212 



THE SEASAT FAILURE 



made which did apply power to the slip ring 
assemblies. In retrospect, the decision not to 
change the wiring sequence for Seasat was a 
crucial one. When the other program 
changed its wiring and Seasat did not, Seasat 
became the first program to fly a 52-brush 
slip ring assembly with adjacent brushes of 
opposite polarity. Had there been better visi- 
bility to the problems experienced with slip 
rings by both the vendor and by other organi- 
zations within Lockheed, the Seasat engi- 
neering managers may have been more sen- 
sitive to the failure prone nature of this com- 
plicated device and to the importance of the 
electrical polarity of adjacent brushes. Un- 
fortunately, such visibility, which may only 
have needed to have been slight to have been 
effective, was lacking. 

Slip Ring Assembly serial number 1002 
was installed on the -Y solar array module on 
August 17, 1977. On August 30, 1977, a non- 
conformance report was written because the 
mechanic "lost" an undetermined number of 
shim washers. 

Review of the installation drawing re- 
vealed that four number 10 washers were re- 
quired between the solar array mounting 
structure and the slip ring assembly. The 
cover of the assembly is made of thin sheet 
metal and is prone to bow up during installa- 
tion operations. Because the mounting bolts 
go through the cover plate into the threaded 
holes in the slip ring body, the mechanic had 
to place the round washers over the bolts be- 
tween the structure and the cover plate. It 
was during this operation that the mechanic 
lost the washers. The S/N 1002 slip ring as- 
sembly was removed from the solar array 
module, the cover plate removed and three 
washers were found. Because some areas 
were still obscured, an x-ray of the slip ring 
was taken. No additional washers were locat- 
ed. A nonconformance report was then writ- 
ten against Slip Ring Assembly 1001 and no 
washers were found by either visual or x-ray 
inspection. It is interesting to note two 
things: (1) there were no downstream electri- 
cal functional checks after installation of the 



slip ring assembly which could have detected 
missing washers in the slip rings, and (2) it 
was never conclusively determined if all lost 
washers were found. 

The solar array modules, including the 
slip ring assemblies, were shipped to the 
launch site in April 1978. The last reported 
anomaly on the slip rings was high contact 
resistance on unit 1002 during interface tests 
performed when the solar array modules 
were mated to the vehicle. The resistance 
reading recorded was 2.38 ohms; the specifi- 
cation value was 2.00 ohms maximum. The 
engineering disposition in the nonconfor- 
mance report was "use-as-is" because in- 
flight operation would decrease the contact 
resistance. 

SIGNIFICANT FINDINGS 

1) The spacecraft failure that occurred on 
October 9, 1978, was due to a loss of elec- 
trical power in the Agena bus as a result 
of a massive and progressive electrical 
short within the slip ring assembly of the 
-Y solar array. 

2) The electrical short was most probably 
initiated by an arc between adjacent com- 
ponents in the slip ring assembly. Possi- 
ble triggering mechanisms for this arc are 
momentary shorts caused by wire-to- 
brush assembly contact, brush-to-brush 
contact, or by a contaminant. 

3) The congested nature of the slip ring de- 
sign, coupled with a wiring arrangement 
for connecting the slip rings into the pow- 
er subsystem that resulted in most of the 
adjacent brush assemblies being of oppo- 
site polarity, made the Seasat slip ring as- 
sembly particularly prone to shorting. 

4) The combination of design and wiring se- 
quence used for the Seasat slip ring as- 
semblies made these unique, first-of-a- 
kind components. 

5) The possibility of slip ring failures result- 
ing from placing opposite electrical po- 
larities on adjacent brush assemblies was 
known at least as early as the summer 



213 



READINGS IN SYSTEMS ENGINEERING 



1977 to other projects within the prime 
contractor's organization. That the Seasat 
organization was not fully aware of these 
potential failure modes was due to a 
breakdown in communications within the 
contractor's organization. 

6) The failure to recognize the potential fail- 
ure modes of the slip ring assembly and to 
give this critical component the attention 
it deserved was due, in part, to the under- 
lying program policy and pervasive view 
that it was an existing component of a 
well-proven and extensively used stan- 
dard Agena bus. This program policy fur- 
ther led to a concentration by project 
management on the sensors and sensor 
module of the spacecraft to the near ex- 
clusion of the bus subsystems. In actual- 
ity, many of these subsystems, including 
the power subsystem, contained compo- 
nents that were neither flight proven nor 
truly qualified by similarity. 

7) Lack of proper attention by both Lock- 
heed and JPL Seasat program engineer- 
ing to the new and unproven components 
on the Agena bus resulted in several in- 
stances of both noncompliance with con- 
tractual, qualification and acceptance re- 
quirements and failure to document such 
noncompliances. 

8) The Failure Modes, Effects, and Critical- 
ity Analysis that was conducted for the 
electrical power subsystem did not consid- 
er shorts as a failure mode and thus did 
not reveal the presence of single point 
failure modes in the subsystem nor pro- 
vide a basis for the development of a full 
complement of safing command se- 
quences that could be used by the flight 
controllers in responding to anomalies. 

9) The strong desire on the part of all con- 
cerned to initiate the project as soon as 
possible resulted in inadequate time for 
an effective Phase B study. As a result, 
the project office did not have the opportu- 
nity to plan the activity thoughtfully and 
establish the preliminary designs, compo- 
nent evaluations, test plans, and other 



Phase B project plans before becoming en- 
gaged in the actual spacecraft develop- 
ment. 

Although unrelated to the failure of the Sea- 
sat, certain deficiencies in flight control pro- 
cedures were present that are worthy of note 
as a lesson for the future. The flight control- 
lers were not provided with an adequate set 
of safing command sequences to use in re- 
sponse to anomalies, were not sufficiently fa- 
miliar with the system they were controlling, 
received insufficient anomaly training and, 
during the failure event itself, failed to fol- 
low the prescribed procedures in response to 
the flight data available to them. Compound- 
ing these difficulties were the frequent 
breakdowns of the ground data acquisition 
and processing system throughout the mis- 
sion. 

It is ironic, and yet typical, of spacecraft 
failures that the termination of the Seasat 
flight was caused not by a malfunction of a 
new or sophisticated device, but by a failure 
in a very common component of a type that 
has flown in many spacecraft for many years. 
It is also ironic, and instructive, that the 
smallest of events or the slightest of commu- 
nications could have prevented the failure. 
Better clarity in an oral communication, a 
brief memorandum of the right kind at the 
right time, a failure report coming to the 
right person, or an alert engineer could have 
made all the difference. 

Basic to the Seasat mission was the con- 
cept of using an existing, flight-proven space- 
craft bus for the services and housekeeping 
functions required by the sensors in order to 
minimize program costs and to permit a con- 
centration of effort on the sensors and their 
integration into the spacecraft. Thus the use 
of a "standard Agena bus" as part of the Sea- 
sat spacecraft became an enduring tenet of 
the program. So firmly rooted was this prin- 
ciple in program philosophy that, even after 
the engineering staffs of both the govern- 
ment and the contractor were well aware of 
the final uniqueness of their Agena bus, the 



214 



THE SEASAT FAILURE 



words, and the associated way of doing busi- 
ness, persisted. They became deceived by 
their own words. 

Consistent with the concept of the "stan- 
dard Agena bus" was the policy decision to 
minimize testing and documentation, to 
qualify components by similarity wherever 
possible and to minimize the penetration into 
the Agena bus by the government. As a re- 
sult, a test was waived without proper ap- 
proval, important component failures were 
not reported to project management, compli- 
ance with specifications was weak, and flight 
controllers were inadequately prepared for 
their task. Significantly, the Seasat slip ring 
assembly had no applicable flight history at 
the time of its launch and, in its application 
to the spacecraft, was a new device. 

There can, of course, be no quarrel with 
the policy of using existing and well proven 
equipment. The use of such equipment has 
certainly reduced the costs and contributed 
to the success of many space missions. But 
the world of space flight is an unforgiving 
one and words like "standard," "existing," 
and "similar to" can be traps for the unwary. 
The technical risks of using standard equip- 
ment can be as high as those present in a new 
or untried piece of equipment, but the ap- 
proach, both technical and managerial, must 
be different. For new equipment, one designs 
carefully, reviews thoroughly, and tests com- 
pletely — and that we know how to do. For 
standard equipment, one should diligently 
and thoroughly probe the heritage that justi- 
fies the classification and identify, compo- 
nent by component and piece by piece, those 
that are truly standard and those that are 
not. One should assume that each space vehi- 
cle is unique until proven otherwise. Then, 
for those parts that are standard or well 
proven, and that are applied in the same 
way, one can forego design, reviews, testing 
and extensive documentation. Conversely, 



components that are different should be 
treated as new. The policy of limited pene- 
tration into Seasat's Agena bus by the gov- 
ernment was appropriate, but a limited pene- 
tration must be a selective penetration and 
not a reduced effort everywhere. 

This identification of the heritage of pre- 
viously used equipment, in both design and 
application, need not require a large staff or 
a lot of money. But it does take time, both at 
the start of the project and at the time of the 
Critical Design Review. And here, respond- 
ing to strong desires by all concerned to get 
the project on contract and underway, the 
Seasat project was denied the advantage of 
an effective Phase B study. Had there been 
an effective Phase B study period, prelimi- 
nary designs would have been completed, 
component selections better understood, test 
plans and qualification requirements better 
established, and possibly, the critical role 
and inherent complexities of the slip ring as- 
sembly might have been more apparent to 
the Seasat engineering staffs. Whether such 
a Phase B study period would have precluded 
the Seasat failure is, of course, uncertain for 
history does not reveal its alternatives. But 
such a carefully conducted planning and 
study period would have minimized the 
chances for the type of failure that did occur. 
The policy of using existing, flight-proven 
equipment can be both valid and cost effec- 
tive. But it is the main lesson of Seasat that 
an uncritical acceptance of such classifica- 
tions as "standard" can submerge important 
differences from previously used equipment 
in both design and in application. It is impor- 
tant, therefore, that thorough planning be 
conducted at the start of a project to fully 
evaluate the heritage of such equipment, to 
identify those that are standard and those 
that are not, and to establish project plans 
and procedures that enable the system to be 
penetrated in a selective manner. 



215 



DEFINING SYSTEMS ENGINEERING 



Defining Systems Engineering 






by George S. Trimble 

Editors' Note 
Back on September 27, 1968, a NASA engi- 
neer by the name of George S. Trimble wrote 
to the Chief of the Management Analysis and 
University Programs Office after the Chief 
issued a letter to find a universally suitable 
definition for "systems engineer. " The engi- 
neer told the manager that the term had no 
particular meaning at all. "In fact," Trimble 
claimed, "I may know the guy who thought it 
up or resurrected it, as the case may be, for 
modern usage." His seemingly authoritative 
account follows: 

During the war, new management prac- 
tices were introduced at a great rate, and one 
of the functions that came to the fore was the 
business of writing job descriptions and eval- 
uating them. Certain industrial relations 
experts fell heir to this function, and there 
was a tendency for them to write very clear 
job descriptions for all jobs except their own. 
It soon became obvious that the value of a 
job, or, more importantly, the money it paid 
(or even more importantly, its draft-dodging 
power), was inversely proportional to the 
ease with which one could describe it. Indus- 
trial relations people were able to describe 
any engineering job in 25 words or less, 
whereas an industrial relations function 
might take two or three pages. Miserable to 
begin with, engineering salaries were futher 
threatened and so was draft status. 

Of course, everyone knows that engineers 
are very creative. They could see that the 
industrial relations boys had a good thing 
going, so they borrowed the approach and 
improved on it (typical engineering method). 
Soon it took five pages to describe the 
most menial engineering task, and the engi- 
neers were saved. It was a simple matter to 
spend three hours explaining to a job analyst 
from industrial relations why a 'systems 
engineering' blueprint file was much more 



complicated to run than a simple old 'engi- 
neering' blueprint file, which was, of course, 
familiar. The guy from industrial relations 
never did understand it because the guy who 
explained it, didn't. It takes a lot of words to 
explain something you don't understand or 
that isn't there. Try explaining 'zero' some- 
time. 

A parallel effort with the objective of em- 
phasizing *!!ENGINEERING!!* was carried 
out with great dispatch by the 'scientists,' all 
of whom became famous at the close of WWII 
because a couple of them invented and built 
the A-bomb, all by themselves, with great se- 
crecy. What they were really doing all that 
time, of course, wasn't science— it was engi- 
neering. When this was discovered, a mixed 
wave of nausea and terror ran through the 
brotherhood. It was worse than being caught 
reading a dirty book in church. Most learned 
scientists knew that engineers were people 
who ran around with special hats and oil 
cans and made steam locomotives go, and 
who, incidentally, made too much money. Be- 
ing identified as part of the same crowd was 
too much for the intellectuals to bear. Scien- 
tists had to be working on something more 
important than 'engineering,' which is super- 
vised by a Ph.D and is therefore high-class 
and also obvious to those schooled properly, 
but difficult if not impossible for anybody 
else to understand. 

Since, as we all know, very few, if any, 
Ph.Ds understand the meaning of plain, ordi- 
nary 'engineering,' it follows that 'systems 
engineering' has given engineering a bad 
name, and should be avoided for that reason 
alone. 

A third group who helped the cause for 
systems engineering were the pre-war 'hand- 
book' engineers who discovered creative 
engineering when they joined up with a war- 
time industrial engineering group to avoid 



PRE«€D1NG PAGE BLANK NOT FILMED 



Mty 



mmmm 



•B^M^-^iptna^K^SSSf^*, i&*)3M 



217 



READINGS IN SYSTEMS ENGINEERING 



being drafted. They had always thought that 
engineering was the choosing from a catalog 
of the proper washer for a quarter-inch bolt. 
It was difficult for them to use the same 
name for their new discovery, creative 
engineering (designing a washer for a 
quarter-inch bolt). The term 'systems engi- 
neering' suited well, and groups of people 
were noising it around by then. It sounded 
nice and, after all, a quarter-inch bolt is a 
fastening system of high complexity. It 
consists of a bolt with threads (helical in- 
clined plane), a nut of the proper size, hand 
and thread configuration (bolt interface 
problem), external shape (wrench interface 
problem), one or more washers (structures 
interface problem), and sometimes even a 
cotter pin (reliability). 



Moreover, one could dream of performing 
systems engineering at increased hierar- 
chical levels by considering at one and the 
same time not only the quarter-inch bolt, but 
also the half-inch bolt. Advanced systems 
engineering. 

So much for the history and meaning of 
systems engineering. You can demonstrate 
the validity of my story to yourself in several 
ways. Your letter, for instance, can be clari- 
fied by eliminating the word 'systems.' I 
believe it appears 10 times. Check the uni- 
versities for courses in systems engineering 
and find out what they are really teaching. 
Note also that the term 'systems engineer- 
ing' does not yet appear in an accredited 
dictionary. This is because Webster cannot 
figure it out either. Good luck! 